SCHEDULE KEBUTUHAN BETON

KUANTITAS PROGRESS SISA VOL SEP 2022 OKT 22 NOV 22


VOLUME
NO Item Pekerjaan SATUAN UPDATED 08 September 2022 MUTU BETON 08 09-Sep 12-Sep 19-Sep 26-Sep 03-Oct 10-Oct 17-Oct 24-Oct 31-Oct 07-Nov 14-Nov 21-Nov
BETON
SEPTEMBER 11-Sep 18-Sep 25-Sep 02-Oct 09-Oct 16-Oct 23-Oct 30-Oct 06-Nov 13-Nov 20-Nov 27-Nov
1 Lapis Pondasi bawah Beton Kurus m3 3 146.97 3 146.971 1 449.290 E 1 782.565 254.65 509.30 509.30 509.30
2 Perkerasan Beton Semen m3 8 654.17 8 654.170 1 327.330 P 7 693.182 824.27 2 289.64 2 289.64 2 289.64
3 Unit Lampu Penerangan Jalan Lengan Tunggal, Tipe LED unit 131.00 129.381 - B1 135.850 33.96 33.96 33.96 33.96
4 Unit Lampu Penerangan Jalan Lengan Ganda, Tipe LED unit 36.00 35.555 - B1 37.333 9.33 9.33 9.33 9.33
5 Beton Struktur Capping SRW, FC' 30 Mpa SISI PERURI m3 405.79 405.788 216.450 B1 198.805 28.40 56.80 56.80 56.80
6 LC Capping SRW m3 170.99 170.993 155.993 E 15.750 2.25 4.50 4.50 4.50
7 Pagar Barrier Beton tinggi 1m di Sisi Perum Peruri m3 360.70 360.700 159.906 B1 210.834 22.59 47.06 47.06 47.06 47.06
8 Inlet, Outlet, Suction Pipe Pond 1 m3 14.69 14.693 - B1 15.428 1.32 3.53 3.53 3.53 3.53
9 Inlet, Outlet, Suction Pipe Pond 2 m3 26.37 26.373 B1 27.692 3.16 6.13 6.13 6.13 6.13
10 Outlet, Suction Pipe Pond 3 m3 58.14 58.143 B1 61.050 5.23 13.95 13.95 13.95 13.95
11 Suction Pipe Pond 4 m3 3.46 3.459 B1 3.632 3.63
12 Pondasi Pagar m3 867.70 867.696 - B1 911.081 65.077 169.20 169.201 169.201 169.201 169.201
13 Pondasi Kanopi m3 234.75 234.755 B1 246.493 17.61 45.78 45.78 45.78 45.78 45.78
14 Saluran Drainase B.0 (lebar 1.2) m3 1 086.72 1 086.720 948.256 E 145.387 20.77 62.31 62.31
15 Saluran Drainase B.0 (lebar 0.6) m3 137.70 137.700 2.200 E 142.275 20.33 60.98 60.98
16 20 TITIK Bored Pile Dia. 80 cm Pile Loading Test fc' 25 Mpa (GEDUNG SPU) m3 271.434 271.434 81.430 25 Mpa 199.504 57.00 142.50
17 Pekerjaan Pilecap Jembatan Pond 1 Beton fc' 30 Mpa m3 14.336 14.336 - B1 15.053 7.53 7.53 - - -
18 Pekerjaan Struktur Balok Jembatan Pond 1 fc' 30 Mpa m3 18.470 18.470 - B1 19.394 6.46 6.46 6.46
19 Pekerjaan Struktur Slab Jembatan Pond 1 fc' 30 MPA m3 20.880 20.880 - B1 21.924 10.96 10.96
20 Pekerjaan Pilecap Jembatan Pond 2 Beton fc' 30 Mpa m3 7.890 7.890 - B1 8.285 4.14 4.14
21 Pekerjaan Struktur Balok Jembatan Pond 2 fc' 30 Mpa m3 9.710 9.710 - B1 10.196 3.40 3.40 3.40
22 Pekerjaan Struktur Slab Jembatan Pond 2 fc' 30 MPA m3 15.168 15.168 - B1 15.926 7.96 7.96
TOTAL NON RIGID 4 224.45 498.39 1 125.68 1 022.84 913.54 353.90 275.70 7.54 15.50 11.36 - - -
TOTAL RIGID 7 693.18 824.27 2 289.64 2 289.64 2 289.64 - - - - - - - -
RATA2/HARI NON-RIGID 166.13 160.81 146.12 130.51 - - - - - - - -
RATA2/HARI RIGID 274.76 327.09 327.09 327.09 - - - - - - - -
TOTAL / BULAN 11 253.63 652.65 11.36

Keterangan:
1. Jadwal Pengecoran Non-Rigid dilaksanakan setiap hari dari pukul 08.00 - 16.00 WIB
2. Jadwal Pengecoran Rigid dilaksanakan setiap hari dari pukul 16.00 WIB - Selesai