You are on page 1of 8

BILL OF QUANTITY (BQ)

TAHUN ANGGARAN 2018

KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN LINGKUNGAN PERMUKIMAN DI 4 KECAMATAN


PEKERJAAN : PEMBANGUNAN JALAN PAVING+SALURAN+TUTUP RT. 01,03 RW.01 KAVLING LC, JL. SLAMET RIYADI RT. 01,04,05 RW. 02; RT.01,02 RW.3 RT. 02 RW. 04 KELURAHAN
SEBANI
SUMBER DANA : DAU
LOKASI : KOTA PASURUAN

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH


1 2 3 4 5 6

PEMBANGUNAN JALAN PAVING & SALURAN AIR

A LOKASI RT 01 RW 01

I RUAS 1_PEK. PAVING P = 34,8 M; L = 1,10 M


1 Pek. Pengukuran Lokasi dan Pembersihan Lahan 1,00 Ls 200.000,00 200.000,00
2 Pek. Bongkaran Paving Lama 38,28 m2 18.700,00 715.836,00
3 Galian Tanah Kansteen 0,28 m3 49.775,00 13.937,00
4 Pek. Urugan Pasir Urug Padat t.6 cm 2,09 m3 214.060,00 447.385,40
5 Pek. Paving Stone K-300 t.6 cm 12,27 m2 103.845,00 1.274.178,15
6 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 13,92 m2 87.045,00 1.211.666,40
7 Pek. Topi Uskup K-300 t.6 cm 69,60 m' 26.554,00 1.848.158,40
8 Pek. Pas. Kansteen 40.20.10 K-300 34,80 m' 70.977,50 2.470.017,00
9 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
II RUAS 2_PEK. PAVING P = 34,0 M; L = 1,50 M
1 Pek. Bongkaran Paving Lama 51,00 m2 18.700,00 953.700,00
2 Galian Tanah Kansteen 0,27 m3 49.775,00 13.439,25
3 Pek. Urugan Pasir Urug Padat t.6 cm 2,86 m3 214.060,00 612.211,60
4 Pek. Paving Stone K-300 t.6 cm 25,59 m2 103.845,00 2.657.393,55
5 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 13,60 m2 87.045,00 1.183.812,00
6 Pek. Topi Uskup K-300 t.6 cm 68,00 m' 26.554,00 1.805.672,00
7 Pek. Pas. Kansteen 40.20.10 K-300 34,00 m' 70.977,50 2.413.235,00
8 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
RUAS 1 & 2_PEMB. SALURAN SAMPING P = 70 M
1 Pek. Pengukuran dan Pemasangan Bouwplank 7,00 Ls 200.000,00 1.400.000,00
2 Pek. Langsiran U-Ditch 6,72 m3 32.065,00 215.476,80
3 Pek. Galian Tanah U-Ditch 23,52 m3 49.775,00 1.170.708,00
4 Pek. Urugan Pasir t.10 4,20 m3 214.060,00 899.052,00
5 Pek. Pemasanga U-ditch 30.30-120 + Cover Gandar 5 Ton 70,00 Bh 457.601,68 32.032.117,60
6 Pek. Urugan Pasir Kembali 4,20 m3 52.800,00 221.760,00
7 Pek. Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K-100) Bawah Cover 0,63 m3 1.516.673,52 955.504,32
Sub Total
B LOKASI RT 03 RW 01

III RUAS 3_PEK. PAVING P = 72,0 M; L = 1,2 M (2 Sisi)


1 Pek. Pengukuran Lokasi dan Pembersihan Lahan 1,00 Ls 300.000,00 300.000,00
2 Galian Tanah Kansteen 1,15 m3 49.775,00 57.241,25
3 Pek. Urugan Pasir Urug Padat t.6 cm 9,50 m3 214.060,00 2.033.570,00
4 Pek. Paving Stone K-300 t.6 cm 65,16 m2 103.845,00 6.766.540,20
5 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 57,60 m2 87.045,00 5.013.792,00
6 Pek. Topi Uskup K-300 t.6 cm 288,00 m' 26.554,00 7.647.552,00
7 Pek. Pas. Kansteen 40.20.10 K-300 144,00 m' 70.977,50 10.220.760,00
8 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
RUAS 3_PEMB. SALURAN TENGAH P = 72 M
1 Pek. Pengukuran dan Pemasangan Bouwplank 7,20 Ls 200.000,00 1.440.000,00
2 Pek. Langsiran U-Ditch 6,91 m3 32.065,00 221.569,15
3 Pek. Galian Tanah U-Ditch 24,19 m3 49.775,00 1.204.057,25
4 Pek. Urugan Pasir t.10 4,32 m3 214.060,00 924.739,20
5 Pek. Pemasanga U-ditch 30.30-120 + Cover Gandar 5 Ton 72,00 Bh 457.601,68 32.947.320,96
6 Pek. Urugan Pasir Kembali 4,32 m3 52.800,00 228.096,00
7 Pek. Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K-100) Bawah Cover 0,65 m3 1.516.673,52 985.837,79
Sub Total
C LOKASI RT 01 RW 02

IV RUAS 4_PEK. PAVING P = 44,5 M; L = 1,0 M


1 Pek. Pengukuran Lokasi dan Pembersihan Lahan 1,000 Ls 300.000,00 300.000,00
2 Pek. Bongkaran Paving Lama 44,50 m2 18.700,00 832.150,00
3 Galian Tanah Kansteen 0,36 m3 49.775,00 17.919,00
4 Pek. Urugan Pasir Urug Padat t.6 cm 2,40 m3 214.060,00 513.744,00
5 Pek. Paving Stone K-300 t.6 cm 11,24 m2 103.845,00 1.167.217,80
6 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 17,80 m2 87.045,00 1.549.401,00
7 Pek. Topi Uskup K-300 t.6 cm 89,00 m' 26.554,00 2.363.306,00
8 Pek. Pas. Kansteen 40.20.10 K-300 44,50 m' 70.977,50 3.158.498,75
9 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
V RUAS 5_PEK. PAVING P = 4,2 M; L = 1,6 M
1 Pek. Bongkaran Paving Lama 6,72 m2 18.700,00 125.664,00
2 Galian Tanah Kansteen 0,02 m3 49.775,00 995,50
3 Pek. Urugan Pasir Urug Padat t.6 cm 0,38 m3 214.060,00 81.342,80
4 Pek. Paving Stone K-300 t.6 cm 3,58 m2 103.845,00 371.765,10
5 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 1,68 m2 87.045,00 146.235,60
6 Pek. Topi Uskup K-300 t.6 cm 8,40 m' 26.554,00 223.053,60
7 Pek. Pas. Kansteen 40.20.10 K-300 4,20 m' 70.977,50 298.105,50
8 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
VI RUAS 6_PEK. PAVING P = 14,9 M; L = 1,1 M
1 Pek. Bongkaran Paving Lama 16,36 m2 18.700,00 305.932,00
2 Galian Tanah Kansteen 0,12 m3 49.775,00 5.973,00
3 Pek. Urugan Pasir Urug Padat t.6 cm 0,89 m3 214.060,00 190.513,40
4 Pek. Paving Stone K-300 t.6 cm 5,24 m2 103.845,00 544.147,80
5 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 5,95 m2 87.045,00 517.917,75
6 Pek. Topi Uskup K-300 t.6 cm 29,74 m' 26.554,00 789.715,96
7 Pek. Pas. Kansteen 40.20.10 K-300 14,87 m' 70.977,50 1.055.435,43
8 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
RUAS 4, 5 & 6_PEMB. SALURAN SAMPING P = 63,6 M
1 Pek. Pengukuran dan Pemasangan Bouwplank 6,36 Ls 200.000,00 1.272.000,00
2 Pek. Langsiran U-Ditch 6,11 m3 32.065,00 195.917,15
3 Pek. Galian Tanah U-Ditch 21,37 m3 49.775,00 1.063.691,75
4 Pek. Urugan Pasir t.10 3,82 m3 214.060,00 817.709,20
5 Pek. Pemasanga U-ditch 30.30-120 + Cover Gandar 5 Ton 63,60 Bh 457.601,68 29.103.466,85
6 Pek. Urugan Pasir Kembali 3,82 m3 52.800,00 201.696,00
7 Pek. Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K-100) Bawah Cover 0,57 m3 1.516.673,52 864.503,91
Sub Total
KECAMATAN
RW. 02; RT.01,02 RW.3 RT. 02 RW. 04 KELURAHAN

JUMLAH PERPOS (RP)


7

8.181.178,35

9.639.463,40

36.894.618,72

32.039.455,45

37.951.620,35
9.902.236,55

1.247.162,10

3.409.635,34

33.518.984,85
D LOKASI RT 02 RW 03

VI RUAS 7_PEK. PAVING P = 24,8 M; L = 1,1 M


1 Pek. Bongkaran Paving Lama 37,20 m2 18.700,00 695.640,00
2 Galian Tanah Kansteen 0,20 m3 49.775,00 9.955,00
3 Pek. Urugan Pasir Urug Padat t.6 cm 1,49 m3 214.060,00 318.949,40
4 Pek. Paving Stone K-300 t.6 cm 8,74 m2 103.845,00 907.605,30
5 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 9,92 m2 87.045,00 863.486,40
6 Pek. Topi Uskup K-300 t.6 cm 49,60 m' 26.554,00 1.317.078,40
7 Pek. Pas. Kansteen 40.20.10 K-300 24,80 m' 70.977,50 1.760.242,00
8 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
VIII RUAS 8_PEK. PAVING P = 43,7 M; L = 0,9 M
1 Pek. Pengukuran Lokasi dan Pembersihan Lahan 1,00 Ls 300.000,00 300.000,00
2 Pek. Bongkaran Paving Lama 56,81 m2 18.700,00 1.062.347,00
3 Pek. Galian Tanah Kansteen 0,17 m3 49.775,00 8.461,75
4 Pek. Urugan Pasir Urug Padat t.6 cm 2,10 m3 214.060,00 449.526,00
5 Pek. Paving Stone K-300 t.6 cm 7,10 m2 103.845,00 737.299,50
6 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 17,48 m2 87.045,00 1.521.546,60
7 Pek. Topi Uskup K-300 t.6 cm 87,40 m' 26.554,00 2.320.819,60
8 Pek. Pas. Kansteen 40.20.10 K-300 43,70 m' 70.977,50 3.101.716,75
9 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
IX RUAS 9_PEK. PAVING P = 28,5 M; L = 1,5 M
1 Pek. Bongkaran Paving Lama 42,75 m2 18.700,00 799.425,00
2 Galian Tanah Kansteen 0,23 m3 49.775,00 11.448,25
3 Pek. Urugan Pasir Urug Padat t.6 cm 2,22 m3 214.060,00 475.213,20
4 Pek. Paving Stone K-300 t.6 cm 18,60 m2 103.845,00 1.931.517,00
5 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 11,40 m2 87.045,00 992.313,00
6 Pek. Topi Uskup K-300 t.6 cm 57,00 m' 26.554,00 1.513.578,00
7 Pek. Pas. Kansteen 40.20.10 K-300 28,50 m' 70.977,50 2.022.858,75
8 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
X RUAS 10_PEK. PAVING P = 30,0 M; L = 1,1 M
1 Pek. Bongkaran Paving Lama 33,00 m2 18.700,00 617.100,00
2 Galian Tanah Kansteen 0,24 m3 49.775,00 11.946,00
3 Pek. Urugan Pasir Urug Padat t.6 cm 1,62 m3 214.060,00 346.777,20
4 Pek. Paving Stone K-300 t.6 cm 7,58 m2 103.845,00 787.145,10
5 Pek. Paving Stone Warna K-300 t.6 cm (Strecher) 12,00 m2 87.045,00 1.044.540,00
6 Pek. Topi Uskup K-300 t.6 cm 60,00 m' 26.554,00 1.593.240,00
7 Pek. Pas. Kansteen 40.20.10 K-300 60,00 m' 70.977,50 4.258.650,00
8 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
RUAS 7 & 8_PEMB. SALURAN SAMPING P = 68,5 M
1 Pek. Pengukuran dan Pemasangan Bouwplank 6,85 Ls 200.000,00 1.370.000,00
2 Pek. Langsiran U-Ditch 6,58 m3 32.065,00 210.987,70
3 Pek. Galian Tanah U-Ditch 23,02 m3 49.775,00 1.145.820,50
4 Pek. Urugan Pasir t.10 4,11 m3 214.060,00 879.786,60
5 Pek. Pemasanga U-ditch 30.30-120 + Cover Gandar 5 Ton 68,50 Bh 457.601,68 31.345.715,08
6 Pek. Urugan Pasir Kembali 4,11 m3 52.800,00 217.008,00
7 Pek. Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K-100) Bawah Cover 0,62 m3 1.516.673,52 940.337,58
Sub Total
E LOKASI RT 03 RW 01 KAVLING LC
XI RUAS 11_PEK. PAVING P = 145,0 M; L = 3,0 M
1 Pek. Pengukuran Lokasi dan Pembersihan Lahan 1,00 Ls 300.000,00 300.000,00
2 Galian Tanah Kansteen 1,16 m3 49.775,00 57.739,00
3 Pek. Urugan Pasir Urug Padat t.10 cm 40,60 m3 214.060,00 8.690.836,00
4 Pek. Paving Stone K-400 t.6 cm 312,14 m2 103.845,00 32.414.178,30
5 Pek. Paving Stone Warna K-400 t.6 cm (Strecher) 58,00 m2 87.045,00 5.048.610,00
6 Pek. Topi Uskup K-400 t.6 cm 290,02 m' 26.554,00 7.701.191,08
7 Pek. Pas. Kansteen 40.20.10 145,01 m' 70.977,50 10.292.447,28
8 Pas. Beton Rabat K-175 - m3 1.586.339,85
Sub Total
RUAS 11_PEMB. SALURAN SAMPING P = 145 M
1 Pek. Pengukuran dan Pemasangan Bouwplank 14,50 Ls 200.000,00 2.900.000,00
2 Pek. Langsiran U-Ditch 13,92 m3 32.065,00 446.344,80
3 Pek. Galian Tanah U-Ditch 57,42 m3 49.775,00 2.858.080,50
4 Pek. Urugan Pasir t.10 8,70 m3 214.060,00 1.862.322,00
5 Pek. Pemasanga U-ditch 30.40-120 + Cover Gandar 5 Ton 145,01 Bh 457.601,68 66.356.819,62
6 Pek. Urugan Pasir Kembali 8,70 m3 52.800,00 459.360,00
7 Pek. Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K-100) Bawah Cover 1,31 m3 1.516.673,52 1.986.842,31
Sub Total
JUMLAH
PPN 10 %
JUMLAH TOTAL
DIBULATKAN
5.872.956,50

9.501.717,20

7.746.353,20

8.659.398,30

36.109.655,46

64.505.001,66

76.869.769,23
382.049.206,65
38.204.920,66
420.254.127,31
420.254.000,00