RAB DAN REKAPITULASI BIAYA TOTAL

RENCANA ANGGARAN BIAYA (RAB)


KEGIATAN : PERENCANAAN RUSUN PUTRI
LOKASI : MAKASSAR PROPINSI SUL-SEL
TAHUN ANGGARAN : 2018

NO
URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA
.
1 2 3 4 5

I PEKERJAAN PENDAHULUAN Rp.


72,387,329.80

1.1 Pengukuran dan pemasangan bouwplank 109.70 m' Rp. 93,234.00 Rp. 10,227,769.80

1.3 Direksi Keet (Kantor Proyek) 24.00 m2 Rp. 2,548,315.00 Rp. 61,159,560.00

1.4 Papan nama proyek 1.00 Ls Rp. 1,000,000.00 Rp. 1,000,000.00

II PEKERJAAN TANAH & SITE WORKS


Rp. 1,125,000.00

Pematangan
2.1 Lahan

2.1.1 Galian (Cutting) Tanah 20.00 m3 Rp. 56,250.00 Rp. 1,125,000.00

2.1.2 Timbunan Tanah - m3 Rp. 119,000.00 Rp. -


II
PEKERJAAN STRUKTUR
I Rp. 3,782,139,216

3.1. Ponda
1 si
3.1.1.
1 Pondasi Tiang Pancang 25.60 m3 Rp. 761,614.00 Rp. 19,497,318.40

3.1.
3 Sloef
3.1.3.
1 Sloof S1 20x35 cm

a. Beton (K-400) 8.93 m3 Rp. 1,809,561.00 Rp. 16,150,331.93


Besi
b. Beton 2,048.40 Kg Rp. 10,449.50 Rp. 21,404,765.38

c. Bekisting 97.03 m2 Rp. 157,825.00 Rp. 15,312,970.63


3.1.3.
2 Sloof S2 20x35 cm

a. Beton (K-400) 10.71 m3 Rp. 1,809,561.00 Rp. 19,380,398.31


Besi
b. Beton 2,458.08 Kg Rp. 10,449.50 Rp. 25,685,718.46

c. Bekisting 115.31 m2 Rp. 157,825.00 Rp. 18,198,800.75

3.1.
4 Pekerjaan Dasar Lantai

3.1.4. Rabat Beton Lantai Kerja t=10 cm, (beton


1 K125) 48.77 m3 Rp. 1,146,162.75 Rp. 55,896,924.68
3.2.
1 Kolom
3.2.1.
1 Kolom type K1 40x40 cm

a. Beton (K400) 128.00 m3 Rp. 1,809,561.00 Rp. 231,623,808.00


Besi
b. Beton 23,356.05 Kg Rp. 10,449.50 Rp. 244,059,020.84

c. Bekisting 1,286.40 m2 Rp. 306,082.50 Rp. 393,744,528.00


3.2.
2 Balok
3.2.2.
1 Balok type BI 30x40 cm

a. Beton (K400) 116.28 m3 Rp. 1,809,561.00 Rp. 210,415,753.08


Besi
b. Beton 16,210.37 Kg Rp. 10,449.50 Rp. 169,390,308.06

c. Bekisting 1,120.62 m2 Rp. 314,250.00 Rp. 352,154,835.00

3.2.
3 Plat Beton

3.2.3.
1 Plat Lantai dan Atap t=10 cm

a. Beton (K400) 292.61 m3 Rp. 1,809,561.00 Rp. 529,500,168.11


Besi
b. Beton 37,464.64 Kg Rp. 10,449.50 Rp. 391,486,770.70

c. Bekisting 2,438.44 m2 Rp. 438,082.50 Rp. 1,068,236,796.09


IV PEKERJAAN AKHIR
Rp. 10,000,000.00

Pembersihan 10,000,000.0
7.1 Akhir 1.00 ls Rp. 0 Rp. 10,000,000.00
REKAPITULASI TOTAL

PEKERJAAN : PERENCANAAN RUSUN PUTRI


LOKASI : MAKASSAR PROPINSI SUL-SEL
TAHUN ANGGARAN : 2018

No URAIAN PEKERJAAN JUMLAH KETERANGAN

a b c d

I PEKERJAAN PENDAHULUAN Rp 72,387,329.80

II PEKERJAAN TANAH & SITE WORKS Rp 1,125,000.00

III PEKERJAAN STRUKTUR Rp 3,782,139,216.42

IV PEKERJAAN AKHIR Rp 10,000,000.00

A REAL COST Rp 3,865,651,546.22

B PPn 10% (10% x A) Rp 386,565,154.62

C JUMLAH (A+B) Rp 4,252,216,700.84


D DIBULATKAN Rp 4,252,200,000.00

TERBILANG : Empat Milyar Dua Ratus Lima Puluh Dua Juta Dua Ratus Ribu Rupiah,-