I PEKERJAAN PENDAHULUAN
1 Pengukuran dan pemasangan Bouwplank 196.900 Ls 15,000.00 2,953,500.00 2,953,500.00
2 Mobilisasi dan Demobilisasi 1.000 Ls 5,000,000.00 5,000,000.00 5,000,000.00
II PEKERJAAN TANAH
1 Galian Tanah Kolam 551.81 M3 16,072.99 8,869,204.44 8,869,204.44
2 Timbunan Jalan 594.303 M3 25,834.59 15,353,569.39 15,353,569.39
REKAPITULASI
I PEKERJAAN PENDAHULUAN 7,953,500.00
II PEKERJAAN TANAH 24,222,773.83
III PEKERJAAN PAGAR DINDING BATU BATA Tinggi 2,80 Meter 82,402,052.59
V TOTAL NILAI PEKERJAAN 114,578,326.42
VI Dibulatkan 114,570,000.00
Terbilang : SERATUS EMPAT BELAS JUTA LIMA RATUS TUJUH PULUH RIBU RUPIAH