DAFTAR KUANTITAS & HARGA

PEMBANGUNAN PAGAR DAN FASILITAS LAHAN


LOKASI : DESA RANTAU PANJANG - KEC. PANTAI LABU

HARGA SATUAN JUMLAH HARGA


No URAIAN PEKERJAAN VOLUME STN. TOTAL HARGA (Rp)
BAHAN UPAH BAHAN UPAH
1 2 3 4 6 7 8 9 10

I PEKERJAAN PENDAHULUAN
1 Pengukuran dan pemasangan Bouwplank 196.900 Ls 15,000.00 2,953,500.00 2,953,500.00
2 Mobilisasi dan Demobilisasi 1.000 Ls 5,000,000.00 5,000,000.00 5,000,000.00

II PEKERJAAN TANAH
1 Galian Tanah Kolam 551.81 M3 16,072.99 8,869,204.44 8,869,204.44
2 Timbunan Jalan 594.303 M3 25,834.59 15,353,569.39 15,353,569.39

III PEKERJAAN PAGAR DINDING BATU BATA Tinggi 2,80 Meter


SEPANJANG 196,90 Meter
A Pekerjaan Pondasi
Galian Tanah 2.400 m3 96,000.00 230,400.00 230,400.00
Cor Pondasi Beton 2.400 m3
a. Semen Portland 19.560 zak 58,000.00 1,134,480.00 1,134,480.00
b. Pasir Beton 1.303 m3 100,000.00 130,285.71 130,285.71
c. Batu Pecah 2 - 3cm 1.372 m3 450,000.00 617,400.00 617,400.00
HARGA SATUAN JUMLAH HARGA
No URAIAN PEKERJAAN VOLUME STN. TOTAL HARGA (Rp)
BAHAN UPAH BAHAN UPAH
1 2 3 4 6 7 8 9 10
B Kolom Praktis 15x15 cm (Tiang)
1 Beton Tiang 3.713 m3 250,000.00 928,125.00 928,125.00
a. Semen Portland 30.257 zak 58,000.00 1,754,898.75 1,754,898.75
b. Pasir Beton 2.015 m3 100,000.00 201,535.71 201,535.71
c. Batu Pecah 2 - 3cm 2.122 m3 450,000.00 955,040.63 955,040.63
2 Pembesian Tiang 507.238 kg 5,000.00 2,536,187.50 2,536,187.50
a. Tulangan Utama - Besi Dia. 10mm 55.000 Btg. 74,440.00 4,094,200.00 4,094,200.00
b. Tulangan Behel - Besi Dia. 6 mm jarak 20 Cm 37.125 Btg. 48,000.00 1,782,000.00 1,782,000.00
c. Kawat Beton 76.086 kg 11,040.00 839,985.30 839,985.30
3 Mall / Bekisting Tiang 10.000 m2 78,000.00 780,000.00 780,000.00
a. Papan 2/20 12.500 Btg. 80,000.00 1,000,000.00 1,000,000.00
b. Paku 7" s.d 2,5" 3.00 kg 20,000.00 60,000.00 60,000.00
HARGA SATUAN JUMLAH HARGA
No URAIAN PEKERJAAN VOLUME STN. TOTAL HARGA (Rp)
BAHAN UPAH BAHAN UPAH
1 2 3 4 6 7 8 9 10
D Dinding Pasangan Batu Bata -
1 Dinding Pasangan Bata 548.800 m2 20,000.00 10,976,000.00 10,976,000.00
a. Bata merah 38,416.00 bh 520.00 19,976,320.00 19,976,320.00
b. Semen Portland 100.98 Kg 58,000.00 5,856,793.60 5,856,793.60
c. Pasir Beton 23.60 m3 100,000.00 2,359,840.00 2,359,840.00
2 Plesteran dan Acian ( 2 Sisi ) 1,097.60 m2 10,000.00 10,976,000.00 10,976,000.00
a. Semen Portland 224.44 Zak 58,000.00 13,017,360.38 13,017,360.38
b. Pasir Beton 21.95 m3 100,000.00 2,195,200.00 2,195,200.00

55,975,340.09 50,649,486.33 114,578,326.42

REKAPITULASI
I PEKERJAAN PENDAHULUAN 7,953,500.00
II PEKERJAAN TANAH 24,222,773.83
III PEKERJAAN PAGAR DINDING BATU BATA Tinggi 2,80 Meter 82,402,052.59
V TOTAL NILAI PEKERJAAN 114,578,326.42
VI Dibulatkan 114,570,000.00
Terbilang : SERATUS EMPAT BELAS JUTA LIMA RATUS TUJUH PULUH RIBU RUPIAH