1. The document is a bill of quantities (BOQ) for construction work to improve tourism infrastructure and facilities in Eremerasa Subdistrict, Bantaeng Regency, including building walking paths, pedestrian areas, and parking lots.
2. It provides details of the work items, quantities, unit prices and total costs. The total project cost is estimated at Rp. 531,228,420.49 based on items for site preparation, earthworks, foundations, concrete structures, plastering, floors, roofs, painting and finishing.
3. The BOQ will be used for procurement and construction management to ensure the project is completed according to the agreed specifications and within budget.
1. The document is a bill of quantities (BOQ) for construction work to improve tourism infrastructure and facilities in Eremerasa Subdistrict, Bantaeng Regency, including building walking paths, pedestrian areas, and parking lots.
2. It provides details of the work items, quantities, unit prices and total costs. The total project cost is estimated at Rp. 531,228,420.49 based on items for site preparation, earthworks, foundations, concrete structures, plastering, floors, roofs, painting and finishing.
3. The BOQ will be used for procurement and construction management to ensure the project is completed according to the agreed specifications and within budget.
1. The document is a bill of quantities (BOQ) for construction work to improve tourism infrastructure and facilities in Eremerasa Subdistrict, Bantaeng Regency, including building walking paths, pedestrian areas, and parking lots.
2. It provides details of the work items, quantities, unit prices and total costs. The total project cost is estimated at Rp. 531,228,420.49 based on items for site preparation, earthworks, foundations, concrete structures, plastering, floors, roofs, painting and finishing.
3. The BOQ will be used for procurement and construction management to ensure the project is completed according to the agreed specifications and within budget.
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA PARIWISATA
PEKERJAAN : PEMBUATAN JALUR PEJALAN KAKI/JALAN SETAPAK/JALAN DALAM KAWASAN/BOARDWALK, PEDISTRIAN DAN TEMPAT PARKIR LOKASI : KECAMATAN EREMERASA KAB. BANTAENG T.A : 2018
HARGA SATUAN JUMLAH HARGA
No URAIAN PEKERJAAN SAT VOL (Rp.) (Rp.) 1 2 3 4 5 6 I PEKERJAAN PENDAHULUAN 1 Pek. Pengukuran dan Pemasangan Bouplank ls 8,87 Rp 427.427,00 Rp 3.791.277,49 JUMLAH HARGA PEKERJAAN PERSIAPAN Rp 3.791.277,49 II PEKERJAAN TANAH 1 Galian Tanah m3 62,18 Rp 56.650,00 Rp 3.522.497,00 2 Urugan Kembali m3 31,09 Rp 41.800,00 Rp 1.299.562,00 3 Urugan Tanah m3 132,00 Rp 172.095,00 Rp 22.716.540,00 4 Pasir Urug Bawah Lantai m3 16,04 Rp 172.095,00 Rp 2.760.403,80 JUMLAH HARGA PEKERJAAN TANAH Rp 30.299.002,80 III PEKERJAAN PONDASI 1 Pasangan Batu Gunung 1:4 m3 76,68 Rp 844.213,23 Rp 64.734.270,53 2 Pasangan Batu Bata, 1 : 4 m2 65,52 Rp 131.018,91 Rp 8.584.358,81 JUMLAH HARGA PEKERJAAN PONDASI Rp 73.318.629,34 IV PEKERJAAN STRUKTUR BETON 1 Poer Plat - Bekisting 2x Pakai m2 5,00 Rp 217.085,00 Rp 1.085.425,00 - Besi Polos kg 124,67 Rp 14.596,18 Rp 1.819.705,14 - Beton K175 m3 1,00 Rp 1.092.228,41 Rp 1.092.228,41 2 Pek. Kolom (30/30) - Bekisting 2x Pakai m2 4,88 Rp 232.815,00 Rp 1.136.137,20 - Besi Polos kg 420,50 Rp 14.596,18 Rp 6.137.691,59 - Beton K175 m3 4,90 Rp 1.092.228,41 Rp 5.351.919,22 3 Pek. Balok (20/40) - Bekisting 2x Pakai m2 5,40 Rp 410.217,50 Rp 2.215.174,50 - Besi Polos kg 277,95 Rp 14.596,18 Rp 4.057.006,84 - Beton K175 m3 2,88 Rp 1.092.228,41 Rp 3.145.617,83 4 Pek. Kolom Tiang (15/15) - Bekisting 2x Pakai m2 5,31 Rp 381.177,50 Rp 2.024.052,53 - Besi Polos kg 195,30 Rp 14.596,18 Rp 2.850.632,98 - Beton K175 m3 1,59 Rp 1.092.228,41 Rp 1.736.643,18 5 Pek. Plat Beton - Bekisting 2x Pakai m2 6,75 Rp 301.730,00 Rp 2.036.677,50 - Besi Polos kg 324,09 Rp 14.596,18 Rp 4.730.474,36 - Beton K175 m3 3,92 Rp 1.092.228,41 Rp 4.281.535,38 JUMLAH HARGA PEKERJAAN STRUKTUR Rp 43.700.921,63 V PEKERJAAN PLESTERAN & REELING 1 Pek. Plasteran 1:4 m2 129,20 Rp 61.041,63 Rp 7.886.579,21 2 Pas. Railing Stainless Steel untuk Panggung m2 34,56 Rp 1.300.000,00 Rp 44.928.000,00 3 Pas. Railing Stainless Steel m2 87,22 Rp 1.300.000,00 Rp 113.386.000,00 4 Pas. Kursi Hias m2 12,00 Rp 3.500.000,00 Rp 42.000.000,00 JUMLAH HARGA PEKERJAAN PASANGAN Rp 208.200.579,21 VI PEKERJAAN LANTAI 1 Pek. Rabat Beton m3 12,35 Rp 927.301,58 Rp 11.452.174,56 2 Pas. Lantai Keramik 40 x 40 m2 43,17 Rp 253.426,76 Rp 10.940.433,37 3 Pas.Lantai/Tangga 30x60 cm (Kasar) m2 374,15 Rp 304.395,42 Rp 113.889.545,94 4 Pas. Paving Blok m2 60,41 Rp 99.301,40 Rp 5.998.797,57 JUMLAH HARGA PEKERJAAN LANTAI Rp 142.280.951,45 VII PEKERJAAN ATAP 1 Pek. Pipa Besi Ø2" m2 76,92 Rp 193.913,50 Rp 14.915.826,42 2 Pek. Atap spandek, 0.35 m2 75,23 Rp 89.903,00 Rp 6.763.402,69 JUMLAH HARGA PEKERJAAN PENUTUP ATAP Rp 21.679.229,11 VIII PEKERJAAN PENGECATAN DAN FINISHING 1 Cat m2 225,00 Rp 38.486,80 Rp 8.659.530,00 JUMLAH HARGA PEKERJAAN PENGECATAN Rp 8.659.530,00