3 GF SLAB
Concrete 51.71 cum 350.00 18,098.64
Formworks 280.35 sm 250.00 70,087.50
Rebars 29,359.58 kgs 4.50 132,118.09
6 CATWALK
Concrete 1.94 cum 350.00 677.30
Formworks 23.22 sm 250.00 5,805.45
Rebars 240.63 kgs 4.50 1,082.83
7 ROOF BEAMS
Concrete 1.39 cum 350.00 487.45
Formworks 17.41 sm 250.00 4,352.25
Rebars 222.76 kgs 4.50 1,002.41
8 PLANTED COLUMNS
Concrete 1.01 cum 350.00 352.80
Formworks 15.12 sm 250.00 3,780.00
Rebars 145.22 kgs 4.50 653.51
9 PUMP room
CHB 4'' wall 45.00 sqm 180.00 8,100.00
Plastering on CHB wall 90.00 sqm 150.00 13,500.00
roof framing 17.27 sqm 250.00 4,317.50
roofing 17.27 sqm 300.00 5,181.00
13 exterior plastering
ground level tank 336 sqm 150.00 50,400.00
EXCLUSIONS:
1. WATER PROOFING AND PAINTING
2. PIPING AND EQUIPMENT
3. GRAVEL BEDDING
PREPARE BY:
Pheby Moog