Mawab, Davao De Oro Branch

Construction Progress
Date: March 9,2023
Scope of Works Percent Completion Contractor: Balfor Construction and
Demolition & Clearing Works 60% Development Corporation
Partition & Masonry Works 50% Start Date: March 6, 2023
Target Completion Date: March 20, 2023
Doors & Windows 50%
Flooring Works 0%
Ceiling Works 40%
Painting Works 10%
Specialties (Counters, Accent wall) 50%
Electrical Works 60%
Mechanical Works 0%
Plumbing Works 100%
Miscellaneous 0%