Professional Documents
Culture Documents
2 Mobilization 1 day
7 days
3 Excavation works (for anchor block and concrete pole)
9 days 01/12/2023 01/20/23 100.00%
7 days
4 Pole erection and pole dressing
3 days 01/18/23 01/20/23 100.00%
3 days
5 Guy wire installation
0 day 100.00%
3 days
6 Conductor stringing and full sag
1 day 01/20/23 01/22/23 100.00%
3 days
7 Installation of CT/VT metering equipment & kW-Hr
0 day 01/21/2023 01/21/2023 33.33%
7 days
8 Excavation of cable trench for U/G XLPE cable
4 days 01/12/2023 01/15/23 100.00%
3 days
9 Cable pulling for XLPE cable
3 days 01/17/23 01/19/23 100.00%
3 days
10 Backfilling of the cable trench
2 days 01/19/23 01/20/23 95.00%
3 days
11 Splicing and termination of XLPE cable
0 day 0.00%
3 days
12 Termination works at switchgear panel
0 day 0.00%
2 days
13 Testing and Commissioning
0 day 0.00%
3 days
14 Energization (by O&M)
0 day 0.00%
1 day
15 Demob/clean-out
0 day 0.00%
Legend:
- Plan
- Actual