WORK SCHDULE & ACCOMPLISHMENT

AS OF JANUARY 24, 2023


CY 2023
Work January 2023 February 2023 March 2023
Item Works Activities No. of days Start Finish
Percentage
12 to 14 15 to 21 22 to 28 29 to 31 1 to 4 5 to 11 12 to 18 19 to 25 26 to 28 1 to 4 5 to 11 12 to 18 19 to 25 26 to 31
Procurement of Materials & Equipment 14 days
a. All Concrete Poles are Free-issued from client 0 day

b. All Line Hardwares to be taken from FCI Ex-stock materials 0 day


1
c. Metering Equipment such as; CT, VT & 90 days

KWHr Meter 01/21/2023 01/21/2023 33.33%

2 Mobilization 1 day
7 days
3 Excavation works (for anchor block and concrete pole)
9 days 01/12/2023 01/20/23 100.00%
7 days
4 Pole erection and pole dressing
3 days 01/18/23 01/20/23 100.00%
3 days
5 Guy wire installation
0 day 100.00%
3 days
6 Conductor stringing and full sag
1 day 01/20/23 01/22/23 100.00%
3 days
7 Installation of CT/VT metering equipment & kW-Hr
0 day 01/21/2023 01/21/2023 33.33%
7 days
8 Excavation of cable trench for U/G XLPE cable
4 days 01/12/2023 01/15/23 100.00%
3 days
9 Cable pulling for XLPE cable
3 days 01/17/23 01/19/23 100.00%
3 days
10 Backfilling of the cable trench
2 days 01/19/23 01/20/23 95.00%
3 days
11 Splicing and termination of XLPE cable
0 day 0.00%
3 days
12 Termination works at switchgear panel
0 day 0.00%
2 days
13 Testing and Commissioning
0 day 0.00%
3 days
14 Energization (by O&M)
0 day 0.00%
1 day
15 Demob/clean-out
0 day 0.00%

Legend:
- Plan
- Actual

Prepared by: ALJAY E. SARAGOSA Submitted by: WIFREDO H. MENESES


Project In-Charge ProjectManager
FCI Project Manager