PROYEK
MINGGU KE - 1
PEKERJAAN LAPANGAN
REPAIR OF EXISTING ASPHALT ROAD ACCESS
BY :
PROGRESS MINGGUAN PEKERJAAN
( MINGGU KE - 1)
I PRELIMENARY WORKS
1 Mobilization and Demobilization of Tools, Materials, Manpower, etc 1.00 Lot 3.022% 0.756% 0.756% 0.756% 0.00%
II SUPPORT WORKS
1 Cleaning Work Area 1.00 Lot 1.209% 0.60% 0.604% 0.604% 0.00%
2 Jack Hammer Rental 1.00 Lot 1.995% 0.00% 0.000% 0.000% 0.00%
3 Concrete Cutting (Gerinda 6 inch) 1.00 Lot 0.604% 0.00% 0.000% 0.000%
4 Concrete Ready Mix fc=29 Mpa (K-350) 7.00 m3 44.149% 0.00% 0.000% 0.000%
Periode Pekerjaan
Volume
Juni - Juli 2023 Skala
No Uraian Pekerjaan Bobot
Minggu 1 Minggu 2 Minggu 3 Minggu 4
Qty UoM
19 s/d 25 26 s/d 02 03 s/d 09 10 s/d 16
I PRELIMENARY WORKS
1 Mobilization and Demobilization of Tools, Materials, Manpower, etc 1.00 Lot 3.02% 0.76% 0.76% 0.76% 0.76% 100%
II SUPPORTING WORKS
TOTAL 100.00%
RENCANA MINGGUAN 23.69% 18.39% 51.45% 6.47%
0.00%
KOMULATIF RENCANA MINGGUAN 23.69% 42.08% 93.53% 100.00%
0.00%
AKTUAL PROGRES MINGGUAN 23.69%
0.00%
KOMULATIF AKTUAL MINGGUAN 23.69%
DEVIASI 0.00%
penggalian asphalt menggunakan PC 60 sekaligus Mobilisasi material besi ke site & Pengangkutan sisa
Perakitan rebar
merapikan galian asphalt menggunakan Jack Hammer material penggalian menggunakan DT
Minggu, 25/06/2023
Uraian Pekerjaan Awal Minggu Uraian Pekerjaan Akhir Minggu Juni 2023
No. Nama Jabatan Ket.
ke - 1 ke - 1 19 20 21 22 23 24 25
3 Assari Civil x x x x x √ √
7 Wahyudi Driver Mobilisasi Material, Peralatan & Manpower ke lokasi area kerja x x √ √ √ √ √
Jam Kerja
No Tanggal Ket.
08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00
Keterangan :