PROYEK
MINGGU KE - 4
PEKERJAAN LAPANGAN
SLOPE STABILLITY USING WOODEN PILE AT ASH POND AREA
BY :
PROGRESS MINGGUAN PEKERJAAN
( MINGGU KE - 2)
Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 19 - 25 April 2023
I PREPARATION WORK
1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 5.64% 0.940% 0.940% 1.880% 1.880% 0.00%
2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 3.53% 0.588% 0.59% 1.175% 1.175% 0.00%
II SUPPORTING WORK
1 Cleaning of work area 1.00 Lot 1.18% 1.175% 0.00% 1.175% 1.175% 0.00%
2 Making shelters for manpower 1.00 Lot 1.41% 1.410% 0.00% 1.410% 1.410% 0.00%
3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 39.93% 39.925% 0.00% 39.925% 26.617% 13.31%
1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 17.47% 0.000% 0.00% 0.000% 0.000% 0.00%
2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 30.85% 8.853% 8.85% 17.706% 0.000% 17.71%
Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 12 - 18 April 2023
I PREPARATION WORK
1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 12,000,000.00 12,000,000.00 5.640% 0.940% 0.940% 0.940% 0.00%
2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 7,500,000.00 7,500,000.00 3.525% 0.59% 0.59% 0.588% 0.00%
II SUPPORTING WORK
1 Cleaning of work area 1.00 Lot 2,500,000.00 2,500,000.00 1.175% 1.18% 1.18% 1.175% 0.00%
2 Making shelters for manpower 1.00 Lot 3,000,000.00 3,000,000.00 1.410% 1.41% 1.41% 1.410% 0.00%
3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 96,500.00 84,944,125.00 39.925% 39.93% 39.93% 13.308% 26.62%
0.000%
III SLOPE STABILITY AT ASH POND AREA 0.000%
1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 175,000.00 37,170,000.00 17.471% 0.00% 0.00% 0.000% 0.00%
2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 175,000.00 65,642,500.00 30.853% 8.85% 8.85% 0.000% 8.85%
212,756,625.00
Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 12 - 18 April 2023
I PREPARATION WORK
1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 12,000,000.00 12,000,000.00 5.640% 5.640% 5.640% 5.640% 0.00%
2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 7,500,000.00 7,500,000.00 3.525% 0.59% 0.59% 0.59% 0.00%
II SUPPORTING WORK
1 Cleaning of work area 1.00 Lot 2,500,000.00 2,500,000.00 1.175% Err:509 Err:509 Err:509 Err:509
2 Making shelters for manpower 1.00 Lot 3,000,000.00 3,000,000.00 1.410% Err:509 Err:509 Err:509 Err:509
3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 96,500.00 84,944,125.00 39.925% Err:509 Err:509 Err:509 Err:509
1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 175,000.00 37,170,000.00 17.471% 0.00% 0.00% 0.00% 0.00%
2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 175,000.00 65,642,500.00 30.853% 0.00% 0.00% 0.00% 0.00%
212,756,625.00
Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 26 April - 02 Mei 2023
I PREPARATION WORK
1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 5.64% 1.88% 1.88% 3.76% 2.82% 0.94%
2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 3.53% 1.18% 1.18% 2.35% 1.76% 0.59%
II SUPPORTING WORK
1 Cleaning of work area 1.00 Lot 1.18% 1.18% 0.00% 1.18% 1.18% 0.00%
2 Making shelters for manpower 1.00 Lot 1.41% 1.41% 0.00% 1.41% 1.41% 0.00%
3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 39.93% 39.93% 0.00% 39.93% 39.93% 0.00%
1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 17.47% 0.00% 2.91% 2.91% 0.00% 2.91%
2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 30.85% 17.71% 17.71% 35.41% 0.00% 35.41%
Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 03 - 09 Mei 2023
I PREPARATION WORK
1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 5.64% 3.76% 3.76% 7.52% 3.76% 3.76%
2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 3.53% 2.35% 2.35% 4.70% 2.35% 2.35%
II SUPPORTING WORK
1 Cleaning of work area 1.00 Lot 1.18% 1.18% 0.00% 1.18% 1.18% 0.00%
2 Making shelters for manpower 1.00 Lot 1.41% 1.41% 0.00% 1.41% 1.41% 0.00%
3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 39.93% 39.93% 0.00% 39.93% 39.93% 0.00%
1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 17.47% 2.91% 2.91% 5.82% 0.00% 5.82%
2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 30.85% 35.41% 35.41% 70.82% 15.43% 55.40%
Periode Pekerjaan
Volume
April 2023 Apr - Mei 2023 Mei 2023 Skala
No Uraian Pekerjaan Bobot
M1 M2 M3 M4 M5 M6
Qty UoM
12 s/d 18 19 s/d 25 26 s/d 02 03 s/d 09 10 s/d 16 17 s/d 19
I PREPARATION WORK
1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 5.640% 0.94% 0.94% 0.94% 0.94% 0.94% 0.94% 100%
2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 3.525% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59%
II SUPPORTING WORK
3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 39.925% 13.31% 13.31% 13.31%
1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 17.471% 17.47%
2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 30.853% 15.43% 15.43% 0%
TOTAL 100.00%
RENCANA MINGGUAN 17.42% 14.84% 14.84% 16.95% 16.95% 19.00%
0.00%
KOMULATIF RENCANA MINGGUAN 17.42% 32.26% 47.09% 64.05% 81.00% 100.00%
0.00%
AKTUAL PROGRES MINGGUAN 52.89% 10.38% 23.67%
0.00%
KOMULATIF AKTUAL MINGGUAN 52.89% 63.27% 86.94%
Periode Pekerjaan
Volume
September - Oktober Oktober Oktober - November November Skala
No Uraian Pekerjaan Bobot
W1 W2 W3 W4 W5 W6 W7 W8
Qty UoM
19 s/d 25 26 s/d 02 03 s/d 09 10 s/d 16 17 s/d 23 24 s/d 30 31 s/d 06 07 s/d 13
I Pekerjaan Persiapan
1 Mobilisasi dan Demobilisasi 1.000 Ls 6.647% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 100%
2 Safety dan Peralatan Kerja 1.000 ls 1.447% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18%
Pintu slilding dan Jendela Fixed Uk. 0,8 x 2,1m ; 3,1 x 1m Daun Pintu dan Jendela Kaca Polos tebal 10mm (include aksesoris
2 1.00 set 6.783% 6.78%
handle, engsel dll)
8 Pasangan dinding 1/2 bata 1PC:4Ps (include plester + Aci) 16.22 m2 6.641% 3.32% 3.32% 50%
9 Pemasangan dinding kawat harmonika include ragka hollow 4x4 10.00 m2 1.221% 1.22%
10 Partisi plywood t=9mm + rangka metal furing 2.00 m2 0.746% 0.75%
11 Pengecatan dinding interior 33.44 m2 1.429% 1.43%
12 Pengecatan dinding eksterior 33.44 m2 1.429% 1.43%
13 Instalasi lampu LED philips 13 watt c/w kabel, konduit, support & aksesoris 3.00 Titik 1.031% 1.03%
14 Instalasi saklar ganda c/w kabel, konduit, support & aksesoris 2.00 Titik 0.687% 0.69%
15 Pemasangan pintu Double Plywood lapis HPL Uk. 0,8 x 2,1m + aksesoris 2.00 Unit 6.964% 6.96%
16 Pemasangan atap genteng metal + rangka baja ringan 15.00 m2 2.486% 2.49%
17 Pemasangan Listplank 9.00 m1 0.860% 0.86%
2 Pemasangan wastafel include pipa dan aksesoris (dipasang dimeja kerja beton) 1.00 unit 1.357% 1.36%
V Pekerjaan Lain-lain
1 Pembuatan dan pemasangan Tulisan Timbul 1.00 unit 4.115% 4.11%
2 Pembuatan dan pemasangan logo adaro mining 1.00 Unit 2.939% 2.94%
3 Pemasangan Cerucuk Galam 1.00 Ls 0.791% 0.79%
TOTAL 100.00%
RENCANA MINGGUAN 7.23% 10.97% 11.10% 9.30% 12.10% 13.38% 7.97% 27.94%
KOMULATIF RENCANA MINGGUAN 0.00% 7.23% 18.21% 29.31% 38.61% 50.71% 64.08% 72.06% 100.00%
AKTUAL PROGRES MINGGUAN 0.00% Err:509
KOMULATIF AKTUAL MINGGUAN 0.00% Err:509
DEVIASI Err:509
Proyek : Slope Stabillity Using Wooden Pile at Ash Pond Area : 03 - 09 Mei 2023
Lokasi : Ash Pond Area : CV. Berkah Mandiri Utama
Owner : PT. Tanjung Power Indonesia : 2023
Selasa, 09/05/2023
Proyek : Slope Stabillity Using Wooden Pile at Ash Pond Area Periode : 03 - 09 Mei 2023
Lokasi : Ash Pond Area Kontraktor : CV. Berkah Mandiri Utama
Owner : PT. Tanjung Power Indonesia Tahun : 2023
Mei 2023
No. Nama Jabatan Uraian Pekerjaan Awal Minggu ke - 4 Uraian Pekerjaan Akhir Minggu ke - 4 Ket.
03 04 05 06 07 08 09
8 Wahyudi Driver √ √ √ √ √ √ √
Total 8 7 8 7 6 7 7
Proyek : Slope Stabillity Using Wooden Pile at Ash Pond Area Periode : 03 - 09 Mei 2023
Lokasi : Ash Pond Area Kontraktor : CV. Berkah Mandiri Utama
Owner : PT. Tanjung Power Indonesia Tahun : 2023
Jam Kerja
No Tanggal Ket.
08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00
Keterangan :