You are on page 1of 17

LAPORAN

PROYEK
MINGGU KE - 4
 

PEKERJAAN LAPANGAN
SLOPE STABILLITY USING WOODEN PILE AT ASH POND AREA

PERIODE : 03 - 09 Mei 2023

PT TANJUNG POWER INDONESIA

LOKASI : ASH POND AREA


MABU'UN, KALIMANTAN SELATAN

BY :
PROGRESS MINGGUAN PEKERJAAN
( MINGGU KE - 2)

Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 19 - 25 April 2023

Lokasi : Ash PondArea Kontraktor : CV. Berkah Mandiri Utama

Owner : PT Tanjung Power Indonesia Tahun : 2023

Volume Progress Mingguan


No Detail of work Bobot (%) Bobot Rencana Minggu Deviasi
Qty UoM Bobot minggu lalu Bobot minggu ini Bobot s/d minggu ini
Ini

I PREPARATION WORK

1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 5.64% 0.940% 0.940% 1.880% 1.880% 0.00%

2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 3.53% 0.588% 0.59% 1.175% 1.175% 0.00%

II SUPPORTING WORK

1 Cleaning of work area 1.00 Lot 1.18% 1.175% 0.00% 1.175% 1.175% 0.00%

2 Making shelters for manpower 1.00 Lot 1.41% 1.410% 0.00% 1.410% 1.410% 0.00%

3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 39.93% 39.925% 0.00% 39.925% 26.617% 13.31%

III SLOPE STABILITY AT ASH POND AREA

1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 17.47% 0.000% 0.00% 0.000% 0.000% 0.00%

2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 30.85% 8.853% 8.85% 17.706% 0.000% 17.71%

GRAND TOTAL 100.00% 52.89% 10.38% 63.27% 32.26% 31.01%

Dibuat oleh, Direview Oleh, Disetujui Oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia

Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy


Pengawas Lapangan Mechanical SPV Head Sect. Mechanical
PROGRESS MINGGUAN PEKERJAAN
( MINGGU KE - 1)

Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 12 - 18 April 2023

Lokasi : Ash PondArea Kontraktor : CV. Berkah Mandiri Utama

Owner : PT Tanjung Power Indonesia Tahun : 2023

Volume Progress Mingguan


No Detail of work Harga Satuan Total Harga Bobot (%) Bobot Rencana Minggu Deviasi
Qty UoM Bobot minggu ini Bobot s/d minggu ini
Ini

I PREPARATION WORK

1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 12,000,000.00 12,000,000.00 5.640% 0.940% 0.940% 0.940% 0.00%

2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 7,500,000.00 7,500,000.00 3.525% 0.59% 0.59% 0.588% 0.00%

II SUPPORTING WORK

1 Cleaning of work area 1.00 Lot 2,500,000.00 2,500,000.00 1.175% 1.18% 1.18% 1.175% 0.00%

2 Making shelters for manpower 1.00 Lot 3,000,000.00 3,000,000.00 1.410% 1.41% 1.41% 1.410% 0.00%

3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 96,500.00 84,944,125.00 39.925% 39.93% 39.93% 13.308% 26.62%

0.000%
III SLOPE STABILITY AT ASH POND AREA 0.000%

1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 175,000.00 37,170,000.00 17.471% 0.00% 0.00% 0.000% 0.00%

2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 175,000.00 65,642,500.00 30.853% 8.85% 8.85% 0.000% 8.85%

212,756,625.00

GRAND TOTAL 100.00% 52.89% 52.89% 17.42% 35.47%

Dibuat oleh, Direview Oleh, Disetujui Oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia

Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy


Pengawas Lapangan Mechanical SPV Head Sect. Mechanical
PROGRESS MINGGUAN PEKERJAAN
( MINGGU KE - 1)

Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 12 - 18 April 2023

Lokasi : Ash PondArea Kontraktor : CV. Berkah Mandiri Utama

Owner : PT Tanjung Power Indonesia Tahun : 2023

Volume Progress Mingguan


No Detail of work Harga Satuan Total Harga Bobot (%) Bobot Rencana Minggu Deviasi
Qty UoM Bobot minggu ini Bobot s/d minggu ini
Ini

I PREPARATION WORK

1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 12,000,000.00 12,000,000.00 5.640% 5.640% 5.640% 5.640% 0.00%

2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 7,500,000.00 7,500,000.00 3.525% 0.59% 0.59% 0.59% 0.00%

II SUPPORTING WORK

1 Cleaning of work area 1.00 Lot 2,500,000.00 2,500,000.00 1.175% Err:509 Err:509 Err:509 Err:509

2 Making shelters for manpower 1.00 Lot 3,000,000.00 3,000,000.00 1.410% Err:509 Err:509 Err:509 Err:509

3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 96,500.00 84,944,125.00 39.925% Err:509 Err:509 Err:509 Err:509

III SLOPE STABILITY AT ASH POND AREA

1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 175,000.00 37,170,000.00 17.471% 0.00% 0.00% 0.00% 0.00%

2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 175,000.00 65,642,500.00 30.853% 0.00% 0.00% 0.00% 0.00%

212,756,625.00

GRAND TOTAL 100.00% Err:509 Err:509

Dibuat oleh, Direview Oleh, Disetujui Oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia

Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy


Pengawas Lapangan Mechanical SPV Head Sect. Mechanical
PROGRESS MINGGUAN PEKERJAAN
( MINGGU KE - 3)

Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 26 April - 02 Mei 2023

Lokasi : Ash PondArea Kontraktor : CV. Berkah Mandiri Utama

Owner : PT Tanjung Power Indonesia Tahun : 2023

Volume Progress Mingguan


No Detail of work Bobot (%) Bobot Rencana Minggu Deviasi
Qty UoM Bobot minggu lalu Bobot minggu ini Bobot s/d minggu ini
Ini

I PREPARATION WORK

1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 5.64% 1.88% 1.88% 3.76% 2.82% 0.94%

2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 3.53% 1.18% 1.18% 2.35% 1.76% 0.59%

II SUPPORTING WORK

1 Cleaning of work area 1.00 Lot 1.18% 1.18% 0.00% 1.18% 1.18% 0.00%

2 Making shelters for manpower 1.00 Lot 1.41% 1.41% 0.00% 1.41% 1.41% 0.00%

3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 39.93% 39.93% 0.00% 39.93% 39.93% 0.00%

III SLOPE STABILITY AT ASH POND AREA

1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 17.47% 0.00% 2.91% 2.91% 0.00% 2.91%

2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 30.85% 17.71% 17.71% 35.41% 0.00% 35.41%

GRAND TOTAL 100.00% 63.27% 23.67% 86.94% 47.09% 39.85%

Dibuat oleh, Direview Oleh, Disetujui Oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia

Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy


Pengawas Lapangan Mechanical SPV Head Sect. Mechanical
PROGRESS MINGGUAN PEKERJAAN
( MINGGU KE - 4)

Proyek : Slope Stabillity using wooden pile in ash pond area Periode : 03 - 09 Mei 2023

Lokasi : Ash PondArea Kontraktor : CV. Berkah Mandiri Utama

Owner : PT Tanjung Power Indonesia Tahun : 2023

Volume Progress Mingguan


No Detail of work Bobot (%) Bobot Rencana Minggu Deviasi
Qty UoM Bobot minggu lalu Bobot minggu ini Bobot s/d minggu ini
Ini

I PREPARATION WORK

1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 5.64% 3.76% 3.76% 7.52% 3.76% 3.76%

2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 3.53% 2.35% 2.35% 4.70% 2.35% 2.35%

II SUPPORTING WORK

1 Cleaning of work area 1.00 Lot 1.18% 1.18% 0.00% 1.18% 1.18% 0.00%

2 Making shelters for manpower 1.00 Lot 1.41% 1.41% 0.00% 1.41% 1.41% 0.00%

3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 39.93% 39.93% 0.00% 39.93% 39.93% 0.00%

III SLOPE STABILITY AT ASH POND AREA

1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 17.47% 2.91% 2.91% 5.82% 0.00% 5.82%

2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 30.85% 35.41% 35.41% 70.82% 15.43% 55.40%

GRAND TOTAL 100.00% 86.94% 44.43% 131.38% 64.05% 67.33%

Dibuat oleh, Direview Oleh, Disetujui Oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia

Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy


Pengawas Lapangan Mechanical SPV Head Sect. Mechanical
TIME SCHEDULE / JADWAL WAKTU PELAKSANAAN PEKERJAAN

Proyek : Slope Stabillity Using Wooden Pile at Ash Pond Area


Lokasi : Ash Pond Area
Owner : PT. Tanjung Power Indonesia

Periode Pekerjaan
Volume
April 2023 Apr - Mei 2023 Mei 2023 Skala
No Uraian Pekerjaan Bobot
M1 M2 M3 M4 M5 M6
Qty UoM
12 s/d 18 19 s/d 25 26 s/d 02 03 s/d 09 10 s/d 16 17 s/d 19

I PREPARATION WORK

1 Mobilizes and demobilizes tools, equipment, manpower, etc 1.00 Lot 5.640% 0.94% 0.94% 0.94% 0.94% 0.94% 0.94% 100%

2 Safety equipment for workers such as helmets, Safety shoes, etc 1.00 Lot 3.525% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59%

II SUPPORTING WORK

1 Cleaning Area 1.00 Lot 1.175% 1.18%

2 Making shelters for manpower 1.00 Lot 1.410% 1.41% 50%

3 Work on Making Road Access to the Work Area at the Rear of the ash pond 880.25 M2 39.925% 13.31% 13.31% 13.31%

III SLOPE STABILITY AT ASH POND AREA

1 Installation of Galam Wood with a Distance of 500 cm in Front Side Area 212.4 M2 17.471% 17.47%

2 Installation of Galam Wood with a Distance of 500 cm in the Back Side Area 375.1 M2 30.853% 15.43% 15.43% 0%

TOTAL 100.00%
RENCANA MINGGUAN 17.42% 14.84% 14.84% 16.95% 16.95% 19.00%
0.00%
KOMULATIF RENCANA MINGGUAN 17.42% 32.26% 47.09% 64.05% 81.00% 100.00%
0.00%
AKTUAL PROGRES MINGGUAN 52.89% 10.38% 23.67%
0.00%
KOMULATIF AKTUAL MINGGUAN 52.89% 63.27% 86.94%

DEVIASI 35.47% 31.01% 39.85%

Dibuat Oleh, Direview Oleh, Disetujui oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia

Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy


Pengawas Lapangan Mechanical Spv. Sect. Head Mechanical
TIME SCHEDULE / JADWAL WAKTU PELAKSANAAN PEKERJAAN

Proyek : Extend Lab QC Tahun 2022 Periode : 19 - 25 September 2022


Lokasi : Office Kontraktor : CV. Berkah Mandiri Utama
Owner : PT. Paramitha Cipta Sarana Tahun : 2022

Periode Pekerjaan
Volume
September - Oktober Oktober Oktober - November November Skala
No Uraian Pekerjaan Bobot
W1 W2 W3 W4 W5 W6 W7 W8
Qty UoM
19 s/d 25 26 s/d 02 03 s/d 09 10 s/d 16 17 s/d 23 24 s/d 30 31 s/d 06 07 s/d 13
I Pekerjaan Persiapan
1 Mobilisasi dan Demobilisasi 1.000 Ls 6.647% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 100%
2 Safety dan Peralatan Kerja 1.000 ls 1.447% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18% 0.18%

II Pekerjaan Sekat Dinding dan Meja Kerja Beton


1 Partisi double playwood t=9mm + rangka metal furing 9.22 m2 3.439% 3.44%

Pintu slilding dan Jendela Fixed Uk. 0,8 x 2,1m ; 3,1 x 1m Daun Pintu dan Jendela Kaca Polos tebal 10mm (include aksesoris
2 1.00 set 6.783% 6.78%
handle, engsel dll)

3 Pengecatan dinding interior 18.44 m2 0.788% 0.79%


4 Pembuatan mea beton uk. 1,5 1x0,8m + keramik 30x30 Besi D10-100 1 lapis T=10cm 1.00 Unit 3.550% 3.55%
5 Pembuatan mea beton uk. 3x0,7x0,8 + keramik 30x30 Besi D10-100 1 lapis T=10cm 1.00 Unit 4.970% 4.97%
6 Pembuatan mea beton uk. 4x0,8x0,8 + keramik 30x30 Besi D10-100 1 lapis T=10cm 1.00 Unit 7.573% 7.57%
7 Pembuatan mea beton uk. 2,3x1xx0,8 + keramik 30x30 Besi D10-100 1 lapis T=10cm 1.00 Unit 5.443% 5.44%

III Pekerjaan Pembuatan Gas dan Compressor House


1 Galian Pondasi Batu Gunung 1.92 m3 0.196% 0.20%
2 Urugan Tanah 2.40 m3 0.336% 0.34%
3 Pondasi menerus batu gunung 1Pc : 4Ps 1.92 m3 2.251% 2.25%
4 Sloof 12/15 cm
a. Pengecoran K - 225 0.23 m3 0.332% 0.33%
b. Pembesian 45.93 kg 0.734% 0.73%
c. Bekisting 3.90 m2 0.534% 0.53%
5 Ringbalk 12/15 cm
a. Pengecoran K - 225 0.23 m3 0.332% 0.33%
b. Pembesian 45.93 kg 0.734% 0.73%
c. Bekisting 3.90 m2 0.866% 0.87%
6 Kolom K1 12/12 cm
a. Pengecoran K - 225 0.17 m3 0.245% 0.24%
b. Pembesian 42.40 kg 0.677% 0.68%
c. Bekisting 5.76 m2 1.235% 1.24%
7 Lantai Beton dengan Besi D8-150 1 lapis 0.90 m3 3.217% 3.22%

8 Pasangan dinding 1/2 bata 1PC:4Ps (include plester + Aci) 16.22 m2 6.641% 3.32% 3.32% 50%
9 Pemasangan dinding kawat harmonika include ragka hollow 4x4 10.00 m2 1.221% 1.22%
10 Partisi plywood t=9mm + rangka metal furing 2.00 m2 0.746% 0.75%
11 Pengecatan dinding interior 33.44 m2 1.429% 1.43%
12 Pengecatan dinding eksterior 33.44 m2 1.429% 1.43%
13 Instalasi lampu LED philips 13 watt c/w kabel, konduit, support & aksesoris 3.00 Titik 1.031% 1.03%
14 Instalasi saklar ganda c/w kabel, konduit, support & aksesoris 2.00 Titik 0.687% 0.69%
15 Pemasangan pintu Double Plywood lapis HPL Uk. 0,8 x 2,1m + aksesoris 2.00 Unit 6.964% 6.96%
16 Pemasangan atap genteng metal + rangka baja ringan 15.00 m2 2.486% 2.49%
17 Pemasangan Listplank 9.00 m1 0.860% 0.86%

IV Pekerjaan Pipe Line


1 Kabel Tray type U 200x50mm include besi penyangga besi siku 4x4 per 1m 62.50 m1 14.979% 4.99% 4.99% 4.99%

2 Pemasangan wastafel include pipa dan aksesoris (dipasang dimeja kerja beton) 1.00 unit 1.357% 1.36%

V Pekerjaan Lain-lain
1 Pembuatan dan pemasangan Tulisan Timbul 1.00 unit 4.115% 4.11%
2 Pembuatan dan pemasangan logo adaro mining 1.00 Unit 2.939% 2.94%
3 Pemasangan Cerucuk Galam 1.00 Ls 0.791% 0.79%

TOTAL 100.00%
RENCANA MINGGUAN 7.23% 10.97% 11.10% 9.30% 12.10% 13.38% 7.97% 27.94%
KOMULATIF RENCANA MINGGUAN 0.00% 7.23% 18.21% 29.31% 38.61% 50.71% 64.08% 72.06% 100.00%
AKTUAL PROGRES MINGGUAN 0.00% Err:509
KOMULATIF AKTUAL MINGGUAN 0.00% Err:509
DEVIASI Err:509

Dibuat Oleh, Diketahui Oleh, Disetujui oleh,


CV. Berkah Mandiri Utama CV. Berkah Mandiri Utama PT. Paramitha Cipta Sarana

Muhammad Saman Muhammad Fazeri Aris Yulianto


Pengawas Lapangan Penanggung Jawab Operasional Project Control
FOTO DOKUMENTASI PEKERJAAN
PROGRESS MINGGU KE - 4

Proyek : Slope Stabillity Using Wooden Pile at Ash Pond Area : 03 - 09 Mei 2023
Lokasi : Ash Pond Area : CV. Berkah Mandiri Utama
Owner : PT. Tanjung Power Indonesia : 2023

Rabu, 03/05/2023 Kamis, 04/05/2023 Jum'at, 05/05/2023

Pemasangan kayu galam pada Land sliding area


Pemasangan kayu galam pada Land sliding area depan Ash Pemasangan kayu galam pada Land sliding area depan
depan Ash Pond & Repair Land Sliding area depan
Pond & Repair Land Sliding area depan Ash Pond Ash Pond & Repair Land Sliding area depan Ash Pond
Ash Pond

Sabtu, 06/05/2023 Minggu, 07/05/2023 Senin, 08/05/2023


Pembersihan Tanah yang Jatuh ke Drainase, Mobilisasi
Mengurug Top Soil Penanaman rumput gajah di area depan Ash Pond
Top Soil & Pengurukan Top Soil

Selasa, 09/05/2023

Dibuat oleh, Direview Oleh, Disetujui oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia
Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy
Pengawas Lapangan Mechanical Spv Head Sect. Mechanical
DATA MANPOWER
PROGRESS MINGGU KE - 4

Proyek : Slope Stabillity Using Wooden Pile at Ash Pond Area Periode : 03 - 09 Mei 2023
Lokasi : Ash Pond Area Kontraktor : CV. Berkah Mandiri Utama
Owner : PT. Tanjung Power Indonesia Tahun : 2023

Mei 2023
No. Nama Jabatan Uraian Pekerjaan Awal Minggu ke - 4 Uraian Pekerjaan Akhir Minggu ke - 4 Ket.
03 04 05 06 07 08 09

1 M. Ainur Rido Pengawas √ √ √ √ √ √ √

2 Adri Anggriawan Pengawas √ √ √ √ √ √ √

3 Mohamad Langa Civil √ √ √ √ √ √ √

4 Ramadan A. Rike Civil √ √ √ √ √ √ √


Pemasangan kayu galam pada Land sliding area
depan Ash Pond & Repair Land Sliding area Penanaman rumput gajah di area depan Ash Pond
depan Ash Pond
5 Bambang Hariadi Civil √ x √ √ √ √ √

6 Akhmad Maulidi Civil √ √ √ √ x √ √

7 Rahmadi Opt. Excavator √ √ √ x x x x

8 Wahyudi Driver √ √ √ √ √ √ √

Total 8 7 8 7 6 7 7

Dibuat oleh, Direview Oleh, Disetujui oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia

Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy


Pengawas Lapangan Mechanical SPV Head Sect. Mechanical
LAPORAN CUACA
PROGRESS MINGGU KE - 4

Proyek : Slope Stabillity Using Wooden Pile at Ash Pond Area Periode : 03 - 09 Mei 2023
Lokasi : Ash Pond Area Kontraktor : CV. Berkah Mandiri Utama
Owner : PT. Tanjung Power Indonesia Tahun : 2023

Jam Kerja
No Tanggal Ket.
08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00

1 Rabu, 03 Mei 2023 √ √ √ √ √ √ √ √ √ √ On Site

2 Kamis, 04 Mei 2023 √ √ √ √ √ √ √ √ √ √ On Site

3 Jum'at, 05 Mei 2023 √ √ √ √ √ On Site

4 Sabtu, 06 Mei 2023 √ √ √ √ √ √ √ √ √ √ On Site

5 Minggu, 07 Mei 2023 √ √ √ √ √ On Site

6 Senin, 08 Mei 2023 √ √ √ √ √ On Site

7 Selasa, 09 Mei 2023 √ √ √ √ On Site

Keterangan :

Mendung Gerimis Hujan √ Cerah

Dibuat oleh, Direview Oleh, Disetujui oleh,


CV. Berkah Mandiri Utama PT Tanjung Power Indonesia PT Tanjung Power Indonesia

Adri Anggriawan Muharrie Naiffie Steven A. Siwabessy


Pengawas Lapangan Mechanical Spv Head Sect. Mechanical

You might also like