ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

rt Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
0 SCHEDULE GENOVA BL06 & BL09 v1R4 20231103 862 days 8/31/2022 1/23/2025
1 ASYA COMMERCIAL GENOVA (BL06 & BL09) 862 days 8/31/2022 1/23/2025
2 Kontrak 262 days 11/28/2022 8/31/2023
3 EoT 1 392 days 12/12/2022 1/22/2024
4 Final Schedule 392 days 12/12/2022 1/22/2024
5 Structure 403 days 8/31/2022 10/22/2023
6 Roof 45 days 8/31/2022 10/14/2022
7 LMR 45 days 6/16/2023 7/30/2023
8 Slab on Ground (SOG) 35 days 9/18/2023 10/22/2023
9 Pekerjaan Tanah dan Anti Rayap 10 days 9/18/2023 9/27/2023
10 Pengecoran LC 5 days 9/28/2023 10/2/2023 9
11 Install Pembesian Balok dan Slab 20 days 10/3/2023 10/22/2023 10
12 Pengecoran SOG 10 days 10/13/2023 10/22/2023 11SS+10 days
13 Finishing & MEP 219 days 8/24/2023 3/29/2024
14 1st Floor (Area Interior - BL06 & BL09) 193 days 8/24/2023 3/3/2024
15 Tenant area 190 days 8/24/2023 2/29/2024
16 GWT 48 days 8/24/2023 10/10/2023
17 Wall finish 65 days 10/11/2023 12/14/2023
18 - Pasangan dinding 30 days 10/11/2023 11/9/2023 16
19 - Plester Dinding 30 days 10/21/2023 11/19/2023 18SS+10 days
20 - Acian Dinding 30 days 10/31/2023 11/29/2023 19SS+10 days
21 - Cat Dinding (BARE) 30 days 11/15/2023 12/14/2023 20SS+15 days
22 Ceilling (BARE) 40 days 11/20/2023 12/29/2023
23 - Pasangan Rangka& Gypsum 30 days 11/20/2023 12/19/2023 20FS-10 days
24 - Compound& Cat (BARE) 20 days 12/10/2023 12/29/2023 23FS-10 days
25 Drylay Marmer (BARE) 30 days 11/30/2023 12/29/2023 20
26 Floor Marmer (BARE) 30 days 12/20/2023 1/18/2024
27 -Instal Marmer 30 days 12/20/2023 1/18/2024 25FS-10 days
28 Floor HT (BARE) 49 days 1/2/2024 2/19/2024
29 Waterproofing Dinding& Lantai 10 days 1/2/2024 1/11/2024 25
30 - Tes Rendam 5 days 1/12/2024 1/16/2024 29
31 Install HT 30 days 1/21/2024 2/19/2024 30
32 Door& Window wall (By Orther) 10 days 2/20/2024 2/29/2024 31
33 Underground Pipe 30 days 10/31/2023 11/29/2023 19SS+10 days
34 Electrical 40 days 11/10/2023 12/19/2023
35 Peralatan Utama 30 days 11/10/2023 12/9/2023 19SS+20 days
36 Kabel Feeder 30 days 11/20/2023 12/19/2023 35FS-20 days
37 Armature/Outlet& Instalasi 20 days 11/30/2023 12/19/2023 36FS-20 days
38 Elektronik 30 days 12/10/2023 1/8/2024
39 Peralatan Utama 30 days 12/10/2023 1/8/2024 35
40 Armature 20 days 12/20/2023 1/8/2024 39FS-20 days
41 Plumbing 40 days 10/31/2023 12/9/2023

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 1 19
ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
42 Sistem Air Bersih 30 days 10/31/2023 11/29/2023 19SS+10 days
43 Sistem Venting 30 days 11/10/2023 12/9/2023 42SS+10 days
44 MVAC 30 days 12/15/2023 1/13/2024 43SS+10 days
45 Pekerjaan Pemadam Kebakaran 20 days 12/25/2023 1/13/2024 44SS+10 days
46 Accessories 15 days 1/4/2024 1/18/2024 45SS+10 days
47 Toilet 131 days 10/21/2023 2/28/2024
48 Wall finish 40 days 10/21/2023 11/29/2023
49 - Pasangan dinding 30 days 10/21/2023 11/19/2023 18SS+10 days
50 - Plester Dinding 30 days 10/31/2023 11/29/2023 49SS+10 days
51 - Pasangan HT (BARE) 20 days 11/10/2023 11/29/2023 50SS+10 days
52 Ceilling (BARE) 40 days 11/20/2023 12/29/2023
53 - Pasangan Rangka& Gypsum 30 days 11/20/2023 12/19/2023 50FS-10 days
54 - Compound& Cat (BARE) 20 days 12/10/2023 12/29/2023 53FS-10 days
55 Floor HT (BARE) 31 days 1/14/2024 2/13/2024
56 Waterproofing Dinding& Lantai 10 days 1/14/2024 1/23/2024 50
57 -Tes rendam 5 days 1/19/2024 1/23/2024 56SS+5 days
58 Install HT 20 days 1/25/2024 2/13/2024 57
59 Door (By Orther) 15 days 2/14/2024 2/28/2024
60 - Instal Door 15 days 2/14/2024 2/28/2024 58
61 Underground Pipe 20 days 11/10/2023 11/29/2023 50SS+10 days
62 Electrical 30 days 11/30/2023 12/29/2023
63 Peralatan Utama 30 days 11/30/2023 12/29/2023 53SS+10 days
64 Armature/Outlet& Instalasi 20 days 12/10/2023 12/29/2023 63SS+10 days
65 Plumbing 50 days 11/10/2023 12/29/2023
66 Sistem Air Bersih 30 days 11/10/2023 12/9/2023 50SS+10 days
67 Sistem Air Kotor 30 days 11/20/2023 12/19/2023 66SS+10 days
68 Sistem Air Bekas 30 days 11/30/2023 12/29/2023 67SS+10 days
69 Accessories 15 days 12/30/2023 1/13/2024 64
70 Pantry 95 days 11/10/2023 2/12/2024
71 Wall finish 60 days 11/10/2023 1/8/2024
72 - Pasangan dinding 30 days 11/10/2023 12/9/2023 49FS-10 days
73 - Plester Dinding 30 days 11/20/2023 12/19/2023 72FS-20 days
74 - Acian Dinding 20 days 11/30/2023 12/19/2023 73FS-20 days
75 - Pasangan HT (BARE) 30 days 12/10/2023 1/8/2024 74FS-10 days
76 Ceilling (BARE) 40 days 12/20/2023 1/28/2024
77 - Pasangan Rangka& Gypsum 30 days 12/20/2023 1/18/2024 74
78 - Compound& Cat 20 days 1/9/2024 1/28/2024 77FS-10 days
79 Top table 20 days 12/10/2023 12/29/2023
80 -install Granit 20 days 12/10/2023 12/29/2023 75SS
81 Underground Pipe 20 days 11/20/2023 12/9/2023 72SS+10 days
82 Electrical 40 days 11/30/2023 1/8/2024
83 Peralatan Utama 30 days 11/30/2023 12/29/2023 73SS+10 days

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 2 29
ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
84 Kabel Feeder 30 days 12/10/2023 1/8/2024 83SS+10 days
85 Armature/Outlet& Instalasi 20 days 12/20/2023 1/8/2024 84SS+10 days
86 Elektronik 30 days 12/30/2023 1/28/2024
87 Peralatan Utama 30 days 12/30/2023 1/28/2024 85SS+10 days
88 Armature 20 days 1/9/2024 1/28/2024 87SS+10 days
89 Plumbing 40 days 11/30/2023 1/8/2024
90 Sistem Air Bersih 20 days 11/30/2023 12/19/2023 73SS+10 days
91 Sistem Air Kotor 20 days 12/5/2023 12/24/2023 90FS-15 days
92 Sistem Air Bekas 20 days 12/10/2023 12/29/2023 91FS-15 days
93 Sistem Air Kotor Dapur 20 days 12/15/2023 1/3/2024 92FS-15 days
94 Sistem Venting 20 days 12/20/2023 1/8/2024 93FS-15 days
95 MVAC 20 days 1/19/2024 2/7/2024 87FS-10 days
96 Pekerjaan Pemadam Kebakaran 20 days 1/24/2024 2/12/2024 87FS-5 days
97 Accessories 10 days 2/3/2024 2/12/2024 96FS-10 days
98 Staircase 95 days 11/30/2023 3/3/2024
99 - Screed (BARE) 30 days 11/30/2023 12/29/2023 73SS+10 days
100 - install HT (BARE) 30 days 12/20/2023 1/18/2024 99FS-10 days
101 - Install Ralling (BARE) 30 days 12/30/2023 1/28/2024 100FS-20 days
102 - Finish cat (BARE) 20 days 1/19/2024 2/7/2024 101FS-10 days
103 Electrical 35 days 12/30/2023 2/2/2024
104 Peralatan Utama 20 days 12/30/2023 1/18/2024 83
105 Kabel Feeder 20 days 1/9/2024 1/28/2024 104FS-10 days
106 Armature/Outlet& Instalasi 15 days 1/19/2024 2/2/2024 105FS-10 days
107 Pekerjaan Pemadam Kebakaran 20 days 2/13/2024 3/3/2024 96
108 Accessories 10 days 2/23/2024 3/3/2024 107FS-10 days
109 Storage 75 days 11/20/2023 2/2/2024
110 Wall finish 50 days 11/20/2023 1/8/2024
111 - Pasangan dinding 30 days 11/20/2023 12/19/2023 72SS+10 days
112 - Plester Dinding 30 days 11/30/2023 12/29/2023 111FS-20 days
113 - Acian Dinding 20 days 12/20/2023 1/8/2024 112FS-10 days
114 Ceilling (BARE) 40 days 12/20/2023 1/28/2024
115 - Pasangan Rangka& Gypsum 30 days 12/20/2023 1/18/2024 112FS-10 days
116 - Compound& Cat 20 days 1/9/2024 1/28/2024 115FS-10 days
117 HT (BARE) 45 days 12/10/2023 1/23/2024
118 - screed 30 days 12/10/2023 1/8/2024 112SS+10 days
119 - install HT 30 days 12/25/2023 1/23/2024 118FS-15 days
120 Electrical 45 days 12/10/2023 1/23/2024
121 Peralatan Utama 30 days 12/10/2023 1/8/2024 112SS+10 days
122 Kabel Feeder 20 days 12/30/2023 1/18/2024 121FS-10 days
123 Armature/Outlet& Instalasi 10 days 1/14/2024 1/23/2024 122FS-5 days
124 Accessories 15 days 1/14/2024 1/28/2024 123FS-10 days
125 Door (By Orther) 10 days 1/24/2024 2/2/2024

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 3 39
ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
126 - install door 10 days 1/24/2024 2/2/2024 119
127 Hall 60 days 12/20/2023 2/17/2024
128 SKTR& SKSR Installation 30 days 12/20/2023 1/18/2024 121SS+10 days
129 Electricity Meter 30 days 12/30/2023 1/28/2024 128FS-20 days
130 Main Line Water Installation 30 days 1/9/2024 2/7/2024 129FS-20 days
131 Water Meter 30 days 1/19/2024 2/17/2024 130FS-20 days
132 2nd Floor (BL06&BL09) 124 days 10/31/2023 3/2/2024
133 Tenant area 120 days 10/31/2023 2/27/2024
134 Wall finish 60 days 10/31/2023 12/29/2023
135 - Pasangan dinding 30 days 10/31/2023 11/29/2023 18SS+20 days
136 - Plester Dinding 30 days 11/15/2023 12/14/2023 135SS+15 days
137 - Acian Dinding 30 days 11/30/2023 12/29/2023 136SS+15 days
138 Ceilling (BARE) 85 days 11/25/2023 2/17/2024
139 - Pasangan Rangka& Gypsum 30 days 11/25/2023 12/24/2023 136SS+10 days
140 - Compound& Cat 30 days 1/19/2024 2/17/2024 130SS+10 days
141 HT (BARE) 54 days 12/5/2023 1/27/2024
142 waterproofing Dinding& Lantai 15 days 12/5/2023 12/19/2023 136SS+20 days
143 - Tes Rendam 10 days 12/14/2023 12/23/2023 142FS-6 days
144 Install HT 30 days 12/29/2023 1/27/2024 143
145 Door& Window wall (By Orther) 10 days 2/18/2024 2/27/2024
146 - Door& Window wall (By Orther) 10 days 2/18/2024 2/27/2024 140
147 Electrical 50 days 11/30/2023 1/18/2024
148 Peralatan Utama 30 days 11/30/2023 12/29/2023 136SS+15 days
149 Kabel Feeder 30 days 12/10/2023 1/8/2024 148SS+10 days
150 Armature/Outlet& Instalasi 30 days 12/20/2023 1/18/2024 149SS+10 days
151 Elektronik 34 days 12/20/2023 1/22/2024
152 Peralatan Utama 30 days 12/20/2023 1/18/2024 149SS+10 days
153 Armature 20 days 1/3/2024 1/22/2024 152SS+10 days
154 Plumbing 55 days 12/10/2023 2/2/2024
155 Sistem Air Bersih 45 days 12/10/2023 1/23/2024 136SS+25 days
156 Sistem Venting 45 days 12/20/2023 2/2/2024 155SS+10 days
157 MVAC 30 days 1/18/2024 2/16/2024 153SS+15 days
158 Pekerjaan Pemadam Kebakaran 20 days 2/2/2024 2/21/2024 157SS+15 days
159 Accessories 15 days 2/7/2024 2/21/2024 157SS+20 days
160 Toilet 95 days 11/18/2023 2/20/2024
161 Wall finish 40 days 11/18/2023 12/27/2023
162 - Pasangan dinding 30 days 11/18/2023 12/17/2023 135SS+18 days
163 - Plester Dinding 30 days 11/28/2023 12/27/2023 162SS+10 days
164 - Pasangan HT (BARE) 20 days 12/8/2023 12/27/2023 163SS+10 days
165 Ceilling (BARE) 32 days 12/18/2023 1/18/2024
166 - Pasangan Rangka& Gypsum 30 days 12/18/2023 1/16/2024 163SS+20 days
167 - Compound& Cat 20 days 12/30/2023 1/18/2024 166SS+12 days

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 4 49
ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
168 Floor HT (BARE) 38 days 1/8/2024 2/14/2024
169 - Waterproofing Dinding& Lantai 15 days 1/8/2024 1/22/2024 163FS-10 days
170 - Tes Rendam 5 days 1/26/2024 1/30/2024 169FS-10 days
171 - Install HT 15 days 1/31/2024 2/14/2024 170
172 Door (By Orther) 10 days 12/8/2023 12/17/2023
173 - Instal Door 10 days 12/8/2023 12/17/2023 164SS
174 Coring Lantai 15 days 12/28/2023 1/11/2024 164
175 Electrical 38 days 12/18/2023 1/24/2024
176 Peralatan Utama 20 days 12/18/2023 1/6/2024 163SS+20 days
177 Kabel Feeder 20 days 12/28/2023 1/16/2024 176SS+10 days
178 Armature/Outlet& Instalasi 15 days 1/10/2024 1/24/2024 177SS+10 days
179 Plumbing 50 days 12/28/2023 2/15/2024
180 Sistem Air Bersih 30 days 12/28/2023 1/26/2024 176SS+10 days
181 Sistem Air Kotor 30 days 1/7/2024 2/5/2024 180SS+10 days
182 Sistem Air Bekas 30 days 1/17/2024 2/15/2024 181SS+10 days
183 Pekerjaan Pemadam Kebakaran 20 days 1/27/2024 2/15/2024 182SS+10 days
184 Accessories 15 days 2/6/2024 2/20/2024 183SS+10 days
185 Pantry 100 days 11/24/2023 3/2/2024
186 Wall finish 60 days 11/24/2023 1/22/2024
187 - Pasangan dinding 30 days 11/24/2023 12/23/2023 135SS+24 days
188 - Plester Dinding 30 days 12/4/2023 1/2/2024 187SS+10 days
189 - Acian Dinding 30 days 12/14/2023 1/12/2024 188SS+10 days
190 - Pasangan HT (BARE) 30 days 12/24/2023 1/22/2024 189SS+10 days
191 Ceilling (BARE) 30 days 12/24/2023 1/22/2024
192 - Pasangan Rangka& Gypsum 30 days 12/24/2023 1/22/2024 189SS+10 days
193 - Compound& Cat 20 days 1/3/2024 1/22/2024 192SS+10 days
194 Top table 10 days 12/24/2023 1/2/2024
195 - Install top table 10 days 12/24/2023 1/2/2024 189SS+10 days
196 Coring Lantai 15 days 1/16/2024 1/30/2024 174
197 Electrical 50 days 12/19/2023 2/6/2024
198 Peralatan Utama 30 days 12/19/2023 1/17/2024 188SS+15 days
199 Kabel Feeder 30 days 12/29/2023 1/27/2024 198SS+10 days
200 Armature/Outlet& Instalasi 30 days 1/8/2024 2/6/2024 199SS+10 days
201 Elektronik 30 days 1/3/2024 2/1/2024
202 Peralatan Utama 25 days 1/3/2024 1/27/2024 198SS+15 days
203 Armature 20 days 1/13/2024 2/1/2024 202SS+10 days
204 Plumbing 70 days 12/24/2023 3/2/2024 19SS+14 days
205 Sistem Air Bersih 30 days 12/24/2023 1/22/2024 188SS+20 days
206 Sistem Air Kotor 30 days 1/3/2024 2/1/2024 205SS+10 days
207 Sistem Air Bekas 30 days 1/13/2024 2/11/2024 206SS+10 days
208 Sistem Air Kotor Dapur 30 days 1/23/2024 2/21/2024 207SS+10 days
209 Sistem Venting 30 days 2/2/2024 3/2/2024 208SS+10 days

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 5 59
ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
210 Pekerjaan Pemadam Kebakaran 20 days 2/1/2024 2/20/2024 203FS-10 days
211 Accessories 15 days 2/11/2024 2/25/2024 203FS-5 days
212 Staircase (BARE) 65 days 11/30/2023 2/2/2024
213 - Screed (BARE) 30 days 11/30/2023 12/29/2023 135SS+30 days
214 - install HT (BARE) 30 days 12/10/2023 1/8/2024 213SS+10 days
215 - Install Ralling (BARE) 30 days 12/20/2023 1/18/2024 214SS+10 days
216 - Finish cat (BARE) 20 days 12/30/2023 1/18/2024 215SS+10 days
217 Electrical 40 days 12/10/2023 1/18/2024
218 Peralatan Utama 30 days 12/10/2023 1/8/2024 213SS+10 days
219 Kabel Feeder 30 days 12/20/2023 1/18/2024 218SS+10 days
220 Armature/Outlet& Instalasi 20 days 12/30/2023 1/18/2024 219SS+10 days
221 Pekerjaan Pemadam Kebakaran 20 days 1/9/2024 1/28/2024 220SS+10 days
222 Accessories 15 days 1/19/2024 2/2/2024 221SS+10 days
223 3rd Floor (BL06 & BL09) 130 days 11/20/2023 3/28/2024
224 Tenant area 94 days 11/20/2023 2/21/2024
225 Wall finish 54 days 11/20/2023 1/12/2024
226 - Pasangan dinding 30 days 11/20/2023 12/19/2023 135SS+20 days
227 - Plester Dinding 30 days 11/30/2023 12/29/2023 226SS+10 days
228 - Acian Dinding 30 days 12/14/2023 1/12/2024 227SS+14 days
229 Ceilling (BARE) 30 days 12/20/2023 1/18/2024
230 - Pasangan Rangka& Gypsum 30 days 12/20/2023 1/18/2024 227SS+20 days
231 - Compound& Cat 20 days 12/30/2023 1/18/2024 230SS+10 days
232 Floor HT (BARE) 66 days 12/10/2023 2/13/2024
233 - Waterproofing Dinding& Lantai 20 days 12/10/2023 12/29/2023 227SS+10 days
234 - Tes Rendam 5 days 12/24/2023 12/28/2023 233FS-10 days
235 - Install HT 30 days 1/15/2024 2/13/2024 234SS+10 days
236 Door& Window wall (By Orther) 10 days 2/6/2024 2/15/2024
237 - Door& Window wall 10 days 2/6/2024 2/15/2024 235FS-10 days
238 Electrical 50 days 12/15/2023 2/2/2024
239 Peralatan Utama 30 days 12/15/2023 1/13/2024 227SS+15 days
240 Kabel Feeder 30 days 12/25/2023 1/23/2024 239SS+10 days
241 Armature/Outlet& Instalasi 30 days 1/4/2024 2/2/2024 240SS+10 days
242 Elektronik 30 days 1/8/2024 2/6/2024
243 Peralatan Utama 30 days 1/8/2024 2/6/2024 240SS+14 days
244 Armature 20 days 1/18/2024 2/6/2024 243SS+10 days
245 Plumbing 40 days 12/20/2023 1/28/2024
246 Sistem Air Bersih 30 days 12/20/2023 1/18/2024 227SS+20 days
247 Sistem Venting 30 days 12/30/2023 1/28/2024 246SS+10 days
248 MVAC 30 days 1/18/2024 2/16/2024 243SS+10 days
249 Pekerjaan Pemadam Kebakaran 20 days 1/23/2024 2/11/2024 243SS+15 days
250 Accessories 15 days 2/7/2024 2/21/2024 244SS+20 days
251 Toilet 112 days 12/8/2023 3/28/2024

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 6 69
ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
252 Wall finish 37 days 12/8/2023 1/13/2024
253 - Pasangan dinding 20 days 12/8/2023 12/27/2023 226SS+18 days
254 - Plester Dinding 15 days 12/20/2023 1/3/2024 253SS+10 days
255 - Pasangan HT (BARE) 15 days 12/30/2023 1/13/2024 254SS+10 days
256 Ceilling (BARE) 26 days 1/4/2024 1/29/2024
257 - Pasangan Rangka& Gypsum 20 days 1/4/2024 1/23/2024 254SS+15 days
258 - Compound& Cat 15 days 1/15/2024 1/29/2024 257SS+10 days
259 Floor HT (BARE) 26 days 1/9/2024 2/3/2024
260 - Waterproofing Dinding& Lantai 15 days 1/9/2024 1/23/2024 254SS+20 days
261 - Tes Rendam 5 days 1/14/2024 1/18/2024 260FS-10 days
262 - Install HT 15 days 1/20/2024 2/3/2024 261SS+6 days
263 Door (By Orther) 10 days 2/11/2024 2/20/2024
264 - Instal Door 10 days 2/11/2024 2/20/2024 262
265 Coring Lantai 10 days 1/9/2024 1/18/2024 255SS+10 days
266 Electrical 50 days 1/4/2024 2/22/2024
267 Peralatan Utama 30 days 1/4/2024 2/2/2024 254SS+15 days
268 Kabel Feeder 30 days 1/14/2024 2/12/2024 267SS+10 days
269 Armature/Outlet& Instalasi 30 days 1/24/2024 2/22/2024 268SS+10 days
270 Plumbing 50 days 1/9/2024 2/27/2024
271 Sistem Air Bersih 30 days 1/9/2024 2/7/2024 254SS+20 days
272 Sistem Air Kotor 30 days 1/19/2024 2/17/2024 271SS+10 days
273 Sistem Air Bekas 30 days 1/29/2024 2/27/2024 272SS+10 days
274 Pekerjaan Pemadam Kebakaran 20 days 2/23/2024 3/13/2024 269
275 Accessories 15 days 3/14/2024 3/28/2024 274
276 Pantry 100 days 12/14/2023 3/22/2024
277 Wall finish 60 days 12/14/2023 2/11/2024
278 - Pasangan dinding 30 days 12/14/2023 1/12/2024 226SS+24 days
279 - Plester Dinding 30 days 12/24/2023 1/22/2024 278SS+10 days
280 - Acian Dinding 30 days 1/3/2024 2/1/2024 279SS+10 days
281 - Pasangan HT (BARE) 30 days 1/13/2024 2/11/2024 280SS+10 days
282 Ceilling (BARE) 40 days 1/3/2024 2/11/2024
283 - Pasangan Rangka& Gypsum 30 days 1/3/2024 2/1/2024 279SS+10 days
284 - Compound& Cat 30 days 1/13/2024 2/11/2024 283SS+10 days
285 Top table 10 days 1/19/2024 1/28/2024
286 install top table 10 days 1/19/2024 1/28/2024 284SS+6 days
287 Coring Lantai 10 days 1/23/2024 2/1/2024 281SS+10 days
288 Electrical 40 days 1/3/2024 2/11/2024
289 Peralatan Utama 30 days 1/3/2024 2/1/2024 279SS+10 days
290 Kabel Feeder 30 days 1/13/2024 2/11/2024 289SS+10 days
291 Armature/Outlet& Instalasi 20 days 1/23/2024 2/11/2024 290SS+10 days
292 Elektronik 30 days 1/8/2024 2/6/2024
293 Peralatan Utama 30 days 1/8/2024 2/6/2024 279SS+15 days

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 7 79
ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
294 Armature 20 days 1/18/2024 2/6/2024 293SS+10 days
295 Plumbing 70 days 1/13/2024 3/22/2024
296 Sistem Air Bersih 30 days 1/13/2024 2/11/2024 279SS+20 days
297 Sistem Air Kotor 30 days 1/23/2024 2/21/2024 296SS+10 days
298 Sistem Air Bekas 30 days 2/2/2024 3/2/2024 297SS+10 days
299 Sistem Air Kotor Dapur 30 days 2/12/2024 3/12/2024 298SS+10 days
300 Sistem Venting 30 days 2/22/2024 3/22/2024 299SS+10 days
301 MVAC 20 days 1/31/2024 2/19/2024 294FS-10 days
302 Pekerjaan Pemadam Kebakaran 20 days 2/10/2024 2/29/2024 301SS+10 days
303 Accessories 15 days 2/20/2024 3/5/2024 302SS+10 days
304 Staircase (BARE) 94 days 12/20/2023 3/22/2024
305 - Screed (BARE) 30 days 12/20/2023 1/18/2024 226SS+30 days
306 - install HT (BARE) 30 days 12/30/2023 1/28/2024 305SS+10 days
307 - Install Ralling (BARE) 20 days 1/9/2024 1/28/2024 306SS+10 days
308 - Finish cat (BARE) 20 days 1/19/2024 2/7/2024 307SS+10 days
309 Electrical 40 days 1/9/2024 2/17/2024
310 Peralatan Utama 30 days 1/9/2024 2/7/2024 305SS+20 days
311 Kabel Feeder 30 days 1/19/2024 2/17/2024 310SS+10 days
312 Armature/Outlet& Instalasi 20 days 1/29/2024 2/17/2024 311SS+10 days
313 Pekerjaan Pemadam Kebakaran 20 days 2/11/2024 3/1/2024 312FS-10 days
314 Accessories 15 days 3/8/2024 3/22/2024 313FS-10 days
315 Lantai atap& LMR (BL06 & BL09) 77 days 12/20/2023 3/5/2024
316 Wall finish 46 days 12/20/2023 2/3/2024
317 - Pasangan dinding 30 days 12/20/2023 1/18/2024 226
318 - Plester Dinding 30 days 12/28/2023 1/26/2024 317SS+8 days
319 - Acian Dinding 30 days 1/5/2024 2/3/2024 318SS+8 days
320 Waterproffing Bitumen + Screed 56 days 1/10/2024 3/5/2024
321 - Waterproofing Bitumen 10 days 1/10/2024 1/19/2024 318SS
322 - Tes Rendam Waterproofing Bitumen 5 days 1/24/2024 1/28/2024 321FS-10 days
323 - Screed 20 days 2/7/2024 2/26/2024 322SS+10 days
324 - Tes Rendam Screed 5 days 3/1/2024 3/5/2024 323FS-10 days
325 LIFT (By Other) 91 days 12/10/2023 3/9/2024
326 Mechanical Installation 45 days 12/10/2023 1/23/2024 35
327 Machine Installation 45 days 12/25/2023 2/7/2024 326SS+15 days
328 Wiring Electrical 45 days 1/9/2024 2/22/2024 327SS+15 days
329 Testing& Commisioning (SLO) 30 days 2/9/2024 3/9/2024 328FS-14 days
330 Façade 119 days 10/18/2023 2/13/2024
331 Wall Finish (1st Floor s.d Roof) 49 days 10/18/2023 12/5/2023
332 - Install Schaffolding Akses 15 days 10/18/2023 11/1/2023 12SS+5 days
333 - Plesteran Dinding Façade 30 days 10/24/2023 11/22/2023 332FS-10 days
334 - Acian Dinding Façade 30 days 11/6/2023 12/5/2023 333FS-20 days
335 Install GRC 65 days 11/20/2023 1/23/2024

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 8 89
ID Task Task Name Duration Start Finish Predecessors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025
Mode J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
336 - Rangka GRC 45 days 11/20/2023 1/3/2024 334FS-20 days
337 - GRC& Sealent 45 days 12/10/2023 1/23/2024 336FS-25 days
338 Pengecatan Façade 41 days 12/20/2023 1/29/2024
339 - Cat Dasar 30 days 12/20/2023 1/18/2024 337SS+10 days
340 - Cat Texture 30 days 12/25/2023 1/23/2024 339FS-25 days
341 - Checklist Eksternal 15 days 1/14/2024 1/28/2024 340FS-10 days
342 - Checklist Estate 10 days 1/20/2024 1/29/2024 341SS+6 days
343 Dismantle Scaffolding Akses 15 days 1/30/2024 2/13/2024 342
344 Canopy Façade 120 days 12/1/2023 3/29/2024
345 Kanopi Selasar dan Kanopi Separator 120 days 12/1/2023 3/29/2024
346 - Install Baja Kanopi 20 days 12/1/2023 12/20/2023 332
347 - Instal ACP Kanopi 30 days 2/14/2024 3/14/2024 343
348 - Install MEP 15 days 3/5/2024 3/19/2024 347FS-10 days
349 - Tes Rendam dan Final Cheklist 10 days 3/20/2024 3/29/2024 348
350 Checklist Internal Unit (ACSET-Sub&Vendor) 10 days 3/30/2024 4/8/2024 349
351 Final Checklist Eksternal Unit (ACSET-AML) 20 days 3/30/2024 4/18/2024 349
352 Final Checklist Unit (AML-Estate) 20 days 4/9/2024 4/28/2024 351SS+10 days
353 BAST 1 (FHO-1) 60 days 4/29/2024 6/27/2024 352
354 Masa Pemeliharaan 180 days 6/28/2024 12/24/2024 353
355 BAST 2 (FHO-2) 60 days 11/25/2024 1/23/2025 354FS-30 days

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: SCHEDULE GENOVA BL
Milestone Inactive Summary Start-only Late
Date: 11/3/2023
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split