B2R commissioning Programme

Open Activities
Activity ID Description At Completion Start Finish 2023 2024
Duration FebMar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

1 All Current Data - Schedule Toolkit Feb 24, 2023 Jun 30, 2023 All Current Data - Schedule Toolkit
2 B2R commissioning Programme Feb 24, 2023 Jun 30, 2023 B2R commissioning Programme
3 B2R commissioning programme Feb 24, 2023 Jun 30, 2023 B2R commissioning programme
4 1 B2R commissioning programme 107 Feb 24, 2023 Jun 30, 2023 B2R commissioning programme
5 Milestones Mar 10, 2023 Jun 30, 2023 Milestones
13 Rowdown Feb 24, 2023 May 2, 2023 Rowdown
78 Lloyd Park Mar 11, 2023 May 16, 2023 Lloyd Park
155 Kent Gateway May 9, 2023 May 27, 2023 Kent Gateway
184 Beddington Mar 20, 2023 Apr 30, 2023 Beddington
218 Site Wide May 17, 2023 May 28, 2023 Site Wide
223 Stage 2 May 28, 2023 Jun 30, 2023 Stage 2
224 1.8 Stage 2 28 May 28, 2023 Jun 30, 2023 Stage 2
225 1.8.6 Complete 0 Jun 30, 2023 Jun 30, 2023 Complete
226 DTS May 28, 2023 Jun 8, 2023 DTS
227 1.8.1 DTS 8 May 28, 2023 Jun 8, 2023 DTS
228 1.8.1.1 Sync Both DTS and Check Alignment 7 May 28, 2023 Jun 7, 2023 Sync Both DTS and Check Alignment
229 1.8.1.3 Fire Alarm 4 May 28, 2023 Jun 2, 2023 Fire Alarm
230 1.8.1.4 Carry out headhouse integrated testing and cause and effect 4 Jun 2, 2023 Jun 8, 2023 Carry out headhouse integrated testing and cause and effect
231 1.8.1.2 Paperwork 1 Jun 7, 2023 Jun 8, 2023 Paperwork
232 Main Tunnel Ventilation Jun 8, 2023 Jun 19, 2023 Main Tunnel Ventilation
233 1.8.2 Main Tunnel Ventilation 9 Jun 8, 2023 Jun 19, 2023 Main Tunnel Ventilation
234 1.8.2.1 Balancing & Airflow Tests 8 Jun 8, 2023 Jun 16, 2023 Balancing & Airflow Tests
235 1.8.2.2 Paperwork 1 Jun 16, 2023 Jun 19, 2023 Paperwork
236 SCADA Jun 8, 2023 Jun 30, 2023 SCADA
237 1.8.3 SCADA 20 Jun 8, 2023 Jun 30, 2023 SCADA
238 1.8.3.1 Integrated testing 8 Jun 8, 2023 Jun 16, 2023 Integrated testing
239 1.8.3.2 Trip & Alarm Audit through to SCS 10 Jun 16, 2023 Jun 28, 2023 Trip & Alarm Audit through to SCS
240 1.8.3.3 Paperwork 2 Jun 28, 2023 Jun 30, 2023 Paperwork
241 Acoustic Testing Jun 7, 2023 Jun 11, 2023 Acoustic Testing
242 1.8.4 Acoustic Testing 4 Jun 7, 2023 Jun 11, 2023 Acoustic Testing
243 1.8.4.1 BEDD 1 Jun 7, 2023 Jun 8, 2023 BEDD
244 1.8.4.2 KEGA 1 Jun 8, 2023 Jun 9, 2023 KEGA
245 1.8.4.3 LLOP 1 Jun 9, 2023 Jun 10, 2023 LLOP
246 1.8.4.4 ROWD 1 Jun 10, 2023 Jun 11, 2023 ROWD
247 Harmonic Survey (7days) May 28, 2023 Jun 22, 2023 Harmonic Survey (7days)
248 1.8.5 Harmonic Survey (7days) 20 May 28, 2023 Jun 22, 2023 Harmonic Survey (7days)
249 1.8.5.1 BEDD 5 May 28, 2023 Jun 5, 2023 BEDD
250 1.8.5.2 KEGA 5 Jun 5, 2023 Jun 10, 2023 KEGA
251 1.8.5.3 LLOP 5 Jun 10, 2023 Jun 15, 2023 LLOP
252 1.8.5.4 ROWD 5 Jun 15, 2023 Jun 22, 2023 ROWD

ID: MSP-Project-000000 | Progress Date: Mar 10, 2023 | Print date: Mar 21, 2023 - 10:05 Page: 1 of 1