B2R commissioning Programme

Open Activities
Activity ID Description At Completion Start Finish 2023 2024
Duration FebMar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

1 All Current Data - Schedule Toolkit Feb 24, 2023 Jun 30, 2023 All Current Data - Schedule Toolkit
2 B2R commissioning Programme Feb 24, 2023 Jun 30, 2023 B2R commissioning Programme
3 B2R commissioning programme Feb 24, 2023 Jun 30, 2023 B2R commissioning programme
4 1 B2R commissioning programme 107 Feb 24, 2023 Jun 30, 2023 B2R commissioning programme
5 Milestones Mar 10, 2023 Jun 30, 2023 Milestones
6 1.1 Milestones 92 Mar 10, 2023 Jun 30, 2023 Milestones
7 1.1.1 Stage 1.5 Start 0 Mar 10, 2023 Mar 10, 2023 Stage 1.5 Start
8 1.1.3 Site Wide Start 0 May 17, 2023 May 17, 2023 Site Wide Start
9 1.1.2 Stage 1.5 Finish 0 May 27, 2023 May 27, 2023 Stage 1.5 Finish
10 1.1.4 Site Wide Finish 0 May 28, 2023 May 28, 2023 Site Wide Finish
11 1.1.5 Stage 2 Start 0 May 28, 2023 May 28, 2023 Stage 2 Start
12 1.1.6 Stage 2 Finish 0 Jun 30, 2023 Jun 30, 2023 Stage 2 Finish
13 Rowdown Feb 24, 2023 May 2, 2023 Rowdown
14 1.3 Rowdown 55 Feb 24, 2023 May 2, 2023 Rowdown
15 SCADA Mar 13, 2023 May 2, 2023 SCADA
16 1.3.1 SCADA 40 Mar 13, 2023 May 2, 2023 SCADA
17 1.3.1.2 Stage 1 40 Mar 13, 2023 May 2, 2023 Stage 1
18 1.3.1.1 CCCC Completed & signed for system, Install ITP suitably complete 0 Mar 13, 2023 Mar 13, 2023 CCCC Completed & signed for system, Install ITP suitably complete and commissioning
19 Team 1 Feb 24, 2023 Apr 4, 2023 Team 1
20 1.3.2 Team 1 33 Feb 24, 2023 Apr 4, 2023 Team 1
21 1.3.2.1 Earthing (SCT 46) 10 Feb 24, 2023 Mar 11, 2023 Earthing (SCT 46)
22 MCC 01 Feb 27, 2023 Mar 21, 2023 MCC 01
23 1.3.2.2 MCC 01 19 Feb 27, 2023 Mar 21, 2023 MCC 01
24 1.3.2.2.1 Stage 1 11 Feb 27, 2023 Mar 11, 2023 Stage 1
25 1.3.2.2.2 Stage 1 & 1.5 (witnessing if required) 3 Mar 11, 2023 Mar 14, 2023 Stage 1 & 1.5 (witnessing if required)
26 1.3.2.2.3 Update of drawings, VVB Test sheets and Post Commissioning 5 Mar 14, 2023 Mar 21, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
27 HVAC & Airconditionng Feb 27, 2023 Mar 12, 2023 HVAC & Airconditionng
28 1.3.2.3 HVAC & Airconditionng 20 Feb 27, 2023 Mar 12, 2023 HVAC & Airconditionng
29 1.3.2.3.2 Stage 1 & 1.5 (witnessing if required) 1 Mar 11, 2023 Mar 11, 2023 Stage 1 & 1.5 (witnessing if required)
30 1.3.2.3.3 Update of drawings, VVB Test sheets and Post Commissioning 1 Mar 11, 2023 Mar 12, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
31 Main Tunnel Ventilation Mar 6, 2023 Mar 25, 2023 Main Tunnel Ventilation
32 1.3.2.4 Main Tunnel Ventilation 18 Mar 6, 2023 Mar 25, 2023 Main Tunnel Ventilation
33 1.3.2.4.1 Stage 1 10 Mar 6, 2023 Mar 15, 2023 Stage 1
34 1.3.2.4.2 Stage 1 & 1.5 (witnessing if required) 3 Mar 15, 2023 Mar 20, 2023 Stage 1 & 1.5 (witnessing if required)
35 1.3.2.4.3 Update of drawings, VVB Test sheets and Post Commissioning 5 Mar 20, 2023 Mar 25, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
36 MCC01 AHF Mar 22, 2023 Mar 24, 2023 MCC01 AHF
37 1.3.2.5 MCC01 AHF 3 Mar 22, 2023 Mar 24, 2023 MCC01 AHF
38 1.3.2.5.1 Stage 1 1 Mar 22, 2023 Mar 22, 2023 Stage 1
39 1.3.2.5.2 Stage 1 & 1.5 (witnessing if required) 1 Mar 23, 2023 Mar 23, 2023 Stage 1 & 1.5 (witnessing if required)
40 1.3.2.5.3 Update of drawings, VVB Test sheets and Post Commissioning 1 Mar 24, 2023 Mar 24, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
41 Fire Alarm System Mar 17, 2023 Mar 30, 2023 Fire Alarm System

ID: MSP-Project-000000 | Progress Date: Mar 10, 2023 | Print date: Mar 21, 2023 - 10:06 Page: 1 of 7
B2R commissioning Programme
Open Activities
Activity ID Description At Completion Start Finish 2023 2024
Duration FebMar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

42 1.3.2.6 Fire Alarm System 12 Mar 17, 2023 Mar 30, 2023 Fire Alarm System
43 1.3.2.6.1 Stage 1 3 Mar 17, 2023 Mar 21, 2023 Stage 1
44 1.3.2.6.2 Stage 1 & 1.5 (witnessing if required) 4 Mar 25, 2023 Mar 28, 2023 Stage 1 & 1.5 (witnessing if required)
45 1.3.2.6.3 Update of drawings, VVB Test sheets and Post Commissioning 2 Mar 29, 2023 Mar 30, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
46 Access Hatch. Man Rescue & Lifting Mar 31, 2023 Apr 3, 2023 Access Hatch. Man Rescue & Lifting
47 1.3.2.7 Access Hatch. Man Rescue & Lifting 2 Mar 31, 2023 Apr 3, 2023 Access Hatch. Man Rescue & Lifting
48 1.3.2.7.1 Stage 1 1 Mar 31, 2023 Mar 31, 2023 Stage 1
49 1.3.2.7.2 Update of drawings, VVB Test sheets and Post Commissioning 1 Apr 3, 2023 Apr 3, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
50 Dry Dropper Apr 4, 2023 Apr 4, 2023 Dry Dropper
51 1.3.2.9 Dry Dropper 1 Apr 4, 2023 Apr 4, 2023 Dry Dropper
52 1.3.2.9.1 Update of drawings, VVB Test sheets and Post Commissioning 1 Apr 4, 2023 Apr 4, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
53 Team 2 Mar 6, 2023 Apr 20, 2023 Team 2
54 1.3.3 Team 2 39 Mar 6, 2023 Apr 20, 2023 Team 2
55 Lighting, Small Power and CMS Mar 6, 2023 Mar 12, 2023 Lighting, Small Power and CMS
56 1.3.3.1 Lighting, Small Power and CMS 6 Mar 6, 2023 Mar 12, 2023 Lighting, Small Power and CMS
57 1.3.3.1.2 Update of drawings, VVB Test sheets and Post Commissioning 4 Mar 8, 2023 Mar 12, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
58 Staircase Ventilation System Mar 11, 2023 Mar 28, 2023 Staircase Ventilation System
59 1.3.3.2 Staircase Ventilation System 16 Mar 11, 2023 Mar 28, 2023 Staircase Ventilation System
60 1.3.3.2.1 Stage 1 6 Mar 11, 2023 Mar 16, 2023 Stage 1
61 1.3.3.2.2 Stage 1 & 1.5 (witnessing if required) 4 Mar 16, 2023 Mar 22, 2023 Stage 1 & 1.5 (witnessing if required)
62 1.3.3.2.3 Update of drawings, VVB Test sheets and Post Commissioning 6 Mar 22, 2023 Mar 28, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
63 UPS HVAC Apr 3, 2023 Apr 13, 2023 UPS HVAC
64 1.3.3.3 UPS HVAC 6 Apr 3, 2023 Apr 13, 2023 UPS HVAC
65 1.3.3.3.1 Stage 1 2 Apr 3, 2023 Apr 5, 2023 Stage 1
66 1.3.3.3.2 Stage 1 & 1.5 (witnessing if required) 2 Apr 5, 2023 Apr 11, 2023 Stage 1 & 1.5 (witnessing if required)
67 1.3.3.3.3 Update of drawings, VVB Test sheets and Post Commissioning 2 Apr 11, 2023 Apr 13, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
68 UPS System Apr 13, 2023 Apr 20, 2023 UPS System
69 1.3.3.4 UPS System 7 Apr 13, 2023 Apr 20, 2023 UPS System
70 1.3.3.4.1 Stage 1 2 Apr 13, 2023 Apr 15, 2023 Stage 1
71 1.3.3.4.2 Stage 1 & 1.5 (witnessing if required) 2 Apr 15, 2023 Apr 17, 2023 Stage 1 & 1.5 (witnessing if required)
72 1.3.3.4.3 Update of drawings, VVB Test sheets and Post Commissioning 3 Apr 17, 2023 Apr 20, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
73 DTS Mar 25, 2023 Apr 13, 2023 DTS
74 1.3.3.5 DTS 14 Mar 25, 2023 Apr 13, 2023 DTS
75 1.3.3.5.1 Stage 1 8 Mar 25, 2023 Apr 3, 2023 Stage 1
76 1.3.3.5.2 Stage 1 & 1.5 (witnessing if required) 2 Apr 3, 2023 Apr 5, 2023 Stage 1 & 1.5 (witnessing if required)
77 1.3.3.5.3 Update of drawings, VVB Test sheets and Post Commissioning 4 Apr 5, 2023 Apr 13, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
78 Lloyd Park Mar 11, 2023 May 16, 2023 Lloyd Park
79 1.4 Lloyd Park 54 Mar 11, 2023 May 16, 2023 Lloyd Park
80 Pre Commissioning Mar 11, 2023 Mar 17, 2023 Pre Commissioning
81 1.4.1 Pre Commissioning 7 Mar 11, 2023 Mar 17, 2023 Pre Commissioning
82 1.4.1.1 Pre Commissioning 3 Mar 11, 2023 Mar 13, 2023 Pre Commissioning

ID: MSP-Project-000000 | Progress Date: Mar 10, 2023 | Print date: Mar 21, 2023 - 10:06 Page: 2 of 7
B2R commissioning Programme
Open Activities
Activity ID Description At Completion Start Finish 2023 2024
Duration FebMar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

83 1.4.1.3 Earthing (SCT 46) 4 Mar 13, 2023 Mar 17, 2023 Earthing (SCT 46)
84 1.4.1.2 Issue Permit 0 Mar 13, 2023 Mar 13, 2023 Issue Permit
85 SCADA Mar 16, 2023 May 15, 2023 SCADA
86 1.4.2 SCADA 47 Mar 16, 2023 May 15, 2023 SCADA
87 1.4.2.3 UKPN Energisation 0 Mar 16, 2023 Mar 16, 2023 UKPN Energisation
88 1.4.2.2 Stage 1 37 Mar 28, 2023 May 15, 2023 Stage 1
89 1.4.2.1 CCCC Completed& signed for system, Install ITP suitably complete 0 Mar 28, 2023 Mar 28, 2023 CCCC Completed& signed for system, Install ITP suitably complete and
90 Team 1 Mar 16, 2023 May 9, 2023 Team 1
91 1.4.3 Team 1 41 Mar 16, 2023 May 9, 2023 Team 1
92 MCC 01 Mar 16, 2023 Apr 6, 2023 MCC 01
93 1.4.3.1 MCC 01 18 Mar 16, 2023 Apr 6, 2023 MCC 01
94 1.4.3.1.1 Stage 1 10 Mar 16, 2023 Mar 27, 2023 Stage 1
95 1.4.3.1.2 Stage 1& 1.5 (witnessing if required) 3 Mar 27, 2023 Mar 30, 2023 Stage 1& 1.5 (witnessing if required)
96 1.4.3.1.3 Update of drawings, VVB Test sheets and Post Commissioning 5 Mar 30, 2023 Apr 6, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
97 HVAC& Airconditionng Apr 3, 2023 Apr 6, 2023 HVAC& Airconditionng
98 1.4.3.2 HVAC& Airconditionng 3 Apr 3, 2023 Apr 6, 2023 HVAC& Airconditionng
99 1.4.3.2.1 Stage 1 1 Apr 3, 2023 Apr 4, 2023 Stage 1
100 1.4.3.2.2 Stage 1& 1.5 (witnessing if required) 1 Apr 4, 2023 Apr 5, 2023 Stage 1& 1.5 (witnessing if required)
101 1.4.3.2.3 Update of drawings, VVB Test sheets and Post Commissioning 1 Apr 5, 2023 Apr 6, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
102 Main Tunnel Ventilation Apr 6, 2023 Apr 29, 2023 Main Tunnel Ventilation
103 1.4.3.3 Main Tunnel Ventilation 17 Apr 6, 2023 Apr 29, 2023 Main Tunnel Ventilation
104 1.4.3.3.1 Stage 1 9 Apr 6, 2023 Apr 19, 2023 Stage 1
105 1.4.3.3.2 Stage 1& 1.5 (witnessing if required) 3 Apr 19, 2023 Apr 24, 2023 Stage 1& 1.5 (witnessing if required)
106 1.4.3.3.3 Update of drawings, VVB Test sheets and Post Commissioning 5 Apr 24, 2023 Apr 29, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
107 MCC01 AHF Apr 24, 2023 Apr 27, 2023 MCC01 AHF
108 1.4.3.4 MCC01 AHF 3 Apr 24, 2023 Apr 27, 2023 MCC01 AHF
109 1.4.3.4.1 Stage 1 1 Apr 24, 2023 Apr 25, 2023 Stage 1
110 1.4.3.4.2 Stage 1& 1.5 (witnessing if required) 1 Apr 25, 2023 Apr 26, 2023 Stage 1& 1.5 (witnessing if required)
111 1.4.3.4.3 Update of drawings, VVB Test sheets and Post Commissioning 1 Apr 26, 2023 Apr 27, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
112 Fire Alarm System Mar 30, 2023 Apr 13, 2023 Fire Alarm System
113 1.4.3.5 Fire Alarm System 9 Mar 30, 2023 Apr 13, 2023 Fire Alarm System
114 1.4.3.5.1 Stage 1 3 Mar 30, 2023 Apr 3, 2023 Stage 1
115 1.4.3.5.2 Stage 1& 1.5 (witnessing if required) 4 Apr 4, 2023 Apr 11, 2023 Stage 1& 1.5 (witnessing if required)
116 1.4.3.5.3 Update of drawings, VVB Test sheets and Post Commissioning 2 Apr 12, 2023 Apr 13, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
117 Access Hatch. Man Rescue& Lifting Apr 29, 2023 May 2, 2023 Access Hatch. Man Rescue& Lifting
118 1.4.3.6 Access Hatch. Man Rescue& Lifting 2 Apr 29, 2023 May 2, 2023 Access Hatch. Man Rescue& Lifting
119 1.4.3.6.1 Stage 1 1 Apr 29, 2023 Apr 30, 2023 Stage 1
120 1.4.3.6.2 Update of drawings, VVB Test sheets and Post Commissioning 1 Apr 30, 2023 May 2, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
121 Intruder Security Alarm May 2, 2023 May 5, 2023 Intruder Security Alarm
122 1.4.3.7 Intruder Security Alarm 3 May 2, 2023 May 5, 2023 Intruder Security Alarm
123 1.4.3.7.1 Stage 1 1 May 2, 2023 May 3, 2023 Stage 1

ID: MSP-Project-000000 | Progress Date: Mar 10, 2023 | Print date: Mar 21, 2023 - 10:06 Page: 3 of 7
B2R commissioning Programme
Open Activities
Activity ID Description At Completion Start Finish 2023 2024
Duration FebMar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

124 1.4.3.7.2 Stage 1& 1.5 (witnessing if required) 1 May 3, 2023 May 4, 2023 Stage 1& 1.5 (witnessing if required)
125 1.4.3.7.3 Update of drawings, VVB Test sheets and Post Commissioning 1 May 4, 2023 May 5, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
126 Dry Dropper May 5, 2023 May 9, 2023 Dry Dropper
127 1.4.3.8 Dry Dropper 1 May 5, 2023 May 9, 2023 Dry Dropper
128 1.4.3.8.1 Update of drawings, VVB Test sheets and Post Commissioning 1 May 5, 2023 May 9, 2023 Update of drawings, VVB Test sheets and Post Commissioning
129 Team 2 Mar 23, 2023 May 16, 2023 Team 2
130 1.4.4 Team 2 44 Mar 23, 2023 May 16, 2023 Team 2
131 Lighting, Small Power and CMS Mar 23, 2023 Apr 3, 2023 Lighting, Small Power and CMS
132 1.4.4.1 Lighting, Small Power and CMS 10 Mar 23, 2023 Apr 3, 2023 Lighting, Small Power and CMS
133 1.4.4.1.1 Stage 1 8 Mar 23, 2023 Mar 30, 2023 Stage 1
134 1.4.4.1.2 Update of drawings, VVB Test sheets and Post Commissioning 2 Mar 30, 2023 Apr 3, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection (TP106)
135 Staircase Ventilation System Mar 30, 2023 Apr 21, 2023 Staircase Ventilation System
136 1.4.4.2 Staircase Ventilation System 16 Mar 30, 2023 Apr 21, 2023 Staircase Ventilation System
137 1.4.4.2.1 Stage 1 6 Mar 30, 2023 Apr 11, 2023 Stage 1
138 1.4.4.2.2 Stage 1& 1.5 (witnessing if required) 4 Apr 11, 2023 Apr 15, 2023 Stage 1& 1.5 (witnessing if required)
139 1.4.4.2.3 Update of drawings, VVB Test sheets and Post Commissioning 6 Apr 15, 2023 Apr 21, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
140 UPS HVAC Apr 19, 2023 Apr 27, 2023 UPS HVAC
141 1.4.4.3 UPS HVAC 6 Apr 19, 2023 Apr 27, 2023 UPS HVAC
142 1.4.4.3.1 Stage 1 2 Apr 19, 2023 Apr 21, 2023 Stage 1
143 1.4.4.3.2 Stage 1& 1.5 (witnessing if required) 2 Apr 21, 2023 Apr 25, 2023 Stage 1& 1.5 (witnessing if required)
144 1.4.4.3.3 Update of drawings, VVB Test sheets and Post Commissioning 2 Apr 25, 2023 Apr 27, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
145 UPS System Apr 27, 2023 May 5, 2023 UPS System
146 1.4.4.4 UPS System 7 Apr 27, 2023 May 5, 2023 UPS System
147 1.4.4.4.1 Stage 1 2 Apr 27, 2023 Apr 29, 2023 Stage 1
148 1.4.4.4.2 Stage 1& 1.5 (witnessing if required) 2 Apr 29, 2023 May 2, 2023 Stage 1& 1.5 (witnessing if required)
149 1.4.4.4.3 Update of drawings, VVB Test sheets and Post Commissioning 3 May 2, 2023 May 5, 2023 Update of drawings, VVB Test sheets and Post Commissioning inspection
150 Pumped Drainage May 3, 2023 May 16, 2023 Pumped Drainage
151 1.4.4.5 Pumped Drainage 11 May 3, 2023 May 16, 2023 Pumped Drainage
152 1.4.4.5.1 Stage 1 5 May 3, 2023 May 11, 2023 Stage 1
153 1.4.4.5.2 Stage 1& 1.5 (witnessing if required) 2 May 11, 2023 May 13, 2023 Stage 1& 1.5 (witnessing if required)
154 1.4.4.5.3 Update of drawings, VVB Test sheets and Post Commissioning 4 May 13, 2023 May 16, 2023 Update of drawings, VVB Test sheets and Post Commissioning
155 Kent Gateway May 9, 2023 May 27, 2023 Kent Gateway
156 1.5 Kent Gateway 17 May 9, 2023 May 27, 2023 Kent Gateway
157 Pumps May 9, 2023 May 13, 2023 Pumps
158 1.5.1 Pumps 5 May 9, 2023 May 13, 2023 Pumps
159 1.5.1.1 Stage 1.5 1 May 9, 2023 May 9, 2023 Stage 1.5
160 1.5.1.2 Papework 4 May 9, 2023 May 13, 2023 Papework
161 Fire Alarm May 13, 2023 May 16, 2023 Fire Alarm
162 1.5.2 Fire Alarm 3 May 13, 2023 May 16, 2023 Fire Alarm
163 1.5.2.1 Stage 1.5 2 May 13, 2023 May 15, 2023 Stage 1.5
164 1.5.2.2 Paperwork 1 May 15, 2023 May 16, 2023 Paperwork

ID: MSP-Project-000000 | Progress Date: Mar 10, 2023 | Print date: Mar 21, 2023 - 10:06 Page: 4 of 7
B2R commissioning Programme
Open Activities
Activity ID Description At Completion Start Finish 2023 2024
Duration FebMar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

165 SCADA May 16, 2023 May 18, 2023 SCADA


166 1.5.3 SCADA 2 May 16, 2023 May 18, 2023 SCADA
167 1.5.3.1 Stage 1.5 2 May 16, 2023 May 18, 2023 Stage 1.5
168 Staircase Ventilation May 18, 2023 May 19, 2023 Staircase Ventilation
169 1.5.4 Staircase Ventilation 1 May 18, 2023 May 19, 2023 Staircase Ventilation
170 1.5.4.1 Flow and static pressure testing 1 May 18, 2023 May 19, 2023 Flow and static pressure testing
171 Telephone FIBTEL May 19, 2023 May 19, 2023 Telephone FIBTEL
172 1.5.5 Telephone FIBTEL 1 May 19, 2023 May 19, 2023 Telephone FIBTEL
173 1.5.5.1 Stage 1.5 1 May 19, 2023 May 19, 2023 Stage 1.5
174 Intruder Alarm May 19, 2023 May 22, 2023 Intruder Alarm
175 1.5.6 Intruder Alarm 1 May 19, 2023 May 22, 2023 Intruder Alarm
176 1.5.6.1 Stage 1 1 May 19, 2023 May 19, 2023 Stage 1
177 1.5.6.2 Stage 1.5 1 May 22, 2023 May 22, 2023 Stage 1.5
178 Man rescue & Hatches May 22, 2023 May 22, 2023 Man rescue & Hatches
179 1.5.7 Man rescue & Hatches 1 May 22, 2023 May 22, 2023 Man rescue & Hatches
180 1.5.7.1 Paperwork 1 May 22, 2023 May 22, 2023 Paperwork
181 Yellow & Orange Lines May 15, 2023 May 27, 2023 Yellow & Orange Lines
182 1.5.8 Yellow & Orange Lines 10 May 15, 2023 May 27, 2023 Yellow & Orange Lines
183 1.5.8.1 Interface Drawings, SLDS 10 May 15, 2023 May 27, 2023 Interface Drawings, SLDS
184 Beddington Mar 20, 2023 Apr 30, 2023 Beddington
185 1.6 Beddington 34 Mar 20, 2023 Apr 30, 2023 Beddington
186 Staircase Ventilation Mar 20, 2023 Apr 30, 2023 Staircase Ventilation
187 1.6.1 Staircase Ventilation 34 Mar 20, 2023 Apr 30, 2023 Staircase Ventilation
188 1.6.1.1 Install 5 Mar 20, 2023 Mar 24, 2023 Install
189 1.6.1.2 Pre-Com 1 Apr 20, 2023 Apr 21, 2023 Pre-Com
190 1.6.1.3 Stage 1 2 Apr 21, 2023 Apr 25, 2023 Stage 1
191 1.6.1.4 Stage 1.5 5 Apr 25, 2023 Apr 30, 2023 Stage 1.5
192 DTS Apr 5, 2023 Apr 13, 2023 DTS
193 1.6.2 DTS 5 Apr 5, 2023 Apr 13, 2023 DTS
194 1.6.2.1 Stage 1.5 5 Apr 5, 2023 Apr 13, 2023 Stage 1.5
195 Fire Alarm Apr 5, 2023 Apr 11, 2023 Fire Alarm
196 1.6.3 Fire Alarm 3 Apr 5, 2023 Apr 11, 2023 Fire Alarm
197 1.6.3.1 Stage 1.5 3 Apr 5, 2023 Apr 11, 2023 Stage 1.5
198 SCADA Apr 12, 2023 Apr 13, 2023 SCADA
199 1.6.4 SCADA 2 Apr 12, 2023 Apr 13, 2023 SCADA
200 1.6.4.1 Stage 1.5 2 Apr 12, 2023 Apr 13, 2023 Stage 1.5
201 Small Power & Lighting Apr 12, 2023 Apr 14, 2023 Small Power & Lighting
202 1.6.5 Small Power & Lighting 3 Apr 12, 2023 Apr 14, 2023 Small Power & Lighting
203 1.6.5.1 Paperwork (NICEIC Certs) 3 Apr 12, 2023 Apr 14, 2023 Paperwork (NICEIC Certs)
204 Man rescue & Hatches Apr 12, 2023 Apr 12, 2023 Man rescue & Hatches
205 1.6.6 Man rescue & Hatches 1 Apr 12, 2023 Apr 12, 2023 Man rescue & Hatches

ID: MSP-Project-000000 | Progress Date: Mar 10, 2023 | Print date: Mar 21, 2023 - 10:06 Page: 5 of 7
B2R commissioning Programme
Open Activities
Activity ID Description At Completion Start Finish 2023 2024
Duration FebMar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

206 1.6.6.1 Paperwork 1 Apr 12, 2023 Apr 12, 2023 Paperwork
207 Telephone FIBTEL Apr 13, 2023 Apr 13, 2023 Telephone FIBTEL
208 1.6.7 Telephone FIBTEL 1 Apr 13, 2023 Apr 13, 2023 Telephone FIBTEL
209 1.6.7.1 Stage 1.5 1 Apr 13, 2023 Apr 13, 2023 Stage 1.5
210 Pumps Apr 14, 2023 Apr 19, 2023 Pumps
211 1.6.8 Pumps 6 Apr 14, 2023 Apr 19, 2023 Pumps
212 1.6.8.1 Stage 1 1 Apr 14, 2023 Apr 14, 2023 Stage 1
213 1.6.8.2 Stage 1.5 1 Apr 14, 2023 Apr 15, 2023 Stage 1.5
214 1.6.8.3 Paperwork 4 Apr 15, 2023 Apr 19, 2023 Paperwork
215 Sign Off's Apr 15, 2023 Apr 26, 2023 Sign Off's
216 1.6.9 Sign Off's 10 Apr 15, 2023 Apr 26, 2023 Sign Off's
217 1.6.9.1 Yellow & Orange Lines, Interface Drawings, SLD's 10 Apr 15, 2023 Apr 26, 2023 Yellow & Orange Lines, Interface Drawings, SLD's
218 Site Wide May 17, 2023 May 28, 2023 Site Wide
219 1.7 Site Wide 10 May 17, 2023 May 28, 2023 Site Wide
220 1.7.1 Radio Install 1 May 17, 2023 May 17, 2023 Radio Install
221 1.7.2 Stage 1 4 May 18, 2023 May 23, 2023 Stage 1
222 1.7.3 Stage 1.5 5 May 24, 2023 May 28, 2023 Stage 1.5
223 Stage 2 May 28, 2023 Jun 30, 2023 Stage 2
224 1.8 Stage 2 28 May 28, 2023 Jun 30, 2023 Stage 2
225 1.8.6 Complete 0 Jun 30, 2023 Jun 30, 2023 Complete
226 DTS May 28, 2023 Jun 8, 2023 DTS
227 1.8.1 DTS 8 May 28, 2023 Jun 8, 2023 DTS
228 1.8.1.1 Sync Both DTS and Check Alignment 7 May 28, 2023 Jun 7, 2023 Sync Both DTS and Check Alignment
229 1.8.1.3 Fire Alarm 4 May 28, 2023 Jun 2, 2023 Fire Alarm
230 1.8.1.4 Carry out headhouse integrated testing and cause and effect 4 Jun 2, 2023 Jun 8, 2023 Carry out headhouse integrated testing and cause and effect
231 1.8.1.2 Paperwork 1 Jun 7, 2023 Jun 8, 2023 Paperwork
232 Main Tunnel Ventilation Jun 8, 2023 Jun 19, 2023 Main Tunnel Ventilation
233 1.8.2 Main Tunnel Ventilation 9 Jun 8, 2023 Jun 19, 2023 Main Tunnel Ventilation
234 1.8.2.1 Balancing & Airflow Tests 8 Jun 8, 2023 Jun 16, 2023 Balancing & Airflow Tests
235 1.8.2.2 Paperwork 1 Jun 16, 2023 Jun 19, 2023 Paperwork
236 SCADA Jun 8, 2023 Jun 30, 2023 SCADA
237 1.8.3 SCADA 20 Jun 8, 2023 Jun 30, 2023 SCADA
238 1.8.3.1 Integrated testing 8 Jun 8, 2023 Jun 16, 2023 Integrated testing
239 1.8.3.2 Trip & Alarm Audit through to SCS 10 Jun 16, 2023 Jun 28, 2023 Trip & Alarm Audit through to SCS
240 1.8.3.3 Paperwork 2 Jun 28, 2023 Jun 30, 2023 Paperwork
241 Acoustic Testing Jun 7, 2023 Jun 11, 2023 Acoustic Testing
242 1.8.4 Acoustic Testing 4 Jun 7, 2023 Jun 11, 2023 Acoustic Testing
243 1.8.4.1 BEDD 1 Jun 7, 2023 Jun 8, 2023 BEDD
244 1.8.4.2 KEGA 1 Jun 8, 2023 Jun 9, 2023 KEGA
245 1.8.4.3 LLOP 1 Jun 9, 2023 Jun 10, 2023 LLOP
246 1.8.4.4 ROWD 1 Jun 10, 2023 Jun 11, 2023 ROWD

ID: MSP-Project-000000 | Progress Date: Mar 10, 2023 | Print date: Mar 21, 2023 - 10:06 Page: 6 of 7
B2R commissioning Programme
Open Activities
Activity ID Description At Completion Start Finish 2023 2024
Duration FebMar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

247 Harmonic Survey (7days) May 28, 2023 Jun 22, 2023 Harmonic Survey (7days)
248 1.8.5 Harmonic Survey (7days) 20 May 28, 2023 Jun 22, 2023 Harmonic Survey (7days)
249 1.8.5.1 BEDD 5 May 28, 2023 Jun 5, 2023 BEDD
250 1.8.5.2 KEGA 5 Jun 5, 2023 Jun 10, 2023 KEGA
251 1.8.5.3 LLOP 5 Jun 10, 2023 Jun 15, 2023 LLOP
252 1.8.5.4 ROWD 5 Jun 15, 2023 Jun 22, 2023 ROWD

ID: MSP-Project-000000 | Progress Date: Mar 10, 2023 | Print date: Mar 21, 2023 - 10:06 Page: 7 of 7