Daily Report for the Clearance Progress by K.

Kee (03 Aug 2023)

K. Kee Engineering Co.

Photo 6
Photo 3 Photo 1

Photo 2

Photo 7
Photo 4

Photo 5

Photo 1
Photo 2

Photo 3
Photo 4

Photo 5
Photo 6

Photo 7
Remarks: All of demolition works was completed.
Date Approx. Nos. of Steel Plates No. of Trucks Leaving NDA
Remain Access
12-Jun-2023 270 0
13-Jun-2023 246 4
14-Jun-2023 246 0
15-Jun-2023 235 2
16-Jun-2023 197 7
17-Jun-2023 186 2
19-Jun-2023 168 4
20-Jun-2023 151 3
21-Jun-2023 151 0
23-Jun-2023 151 0
24-Jun-2023 145 1
26-Jun-2023 140 1
27-Jun-2023 140 0
28-Jun-2023 140 0
29-Jun-2023 140 0
30-Jun-2023 140 0
Date Approx. Nos. of Steel Plates No. of Trucks Leaving the
Remain New Access
3-Jul-2023 135 1
4-Jul-2023 129 1
5-Jul-2023 129 0
6-Jul-2023 122 1
7-Jul-2023 94 4
8-Jul-2023 65 4
10-Jul-2023 65 0
11-Jul-2023 65 0
12-Jul-2023 25* 0
13-Jul-2023 25* 0
14-Jul-2023 25* 0
15-Jul-2023 25* 0
17-Jul-2023 (Typhoon T8) 25* 0
18-Jul-2023 10* 0
19-Jul-2023 10* 0
20-Jul-2023 5* 0
21-Jul-2023 5* 0
22-Jul-2023 5* 0
24-Jul-2023 0* 0
25-Jul-2023 0* 0
26-Jul-2023 0* 0
27-Jul-2023 0* 0
28-Jul-2023 0* 0
29-Jul-2023 0* 0
31-Jul 2023 0* 0

*Around 65 nos of steel plate was used by K Kee own factory without move out. All of steel
plate was cleared.