Nepal Electricity Authority

Bhojpur Sankhuwasabha 11/0.4kV Rural Electrification Project


Contractor: BP Construction Pvt. Ltd.
Contract Number: NEA/DCSD/PTSD/REP/078/79/PACKAGE-10(RE1)
Construction Schedule
2023 2024
S.No. Activities Start Date End Date Milestone
February March April May June July Aug September October November December January February March April May June July August
A. Contract Duration 28-Feb-23 27-Aug-24 Milestone 1
A.1 Contract Signing 12-Feb-23 12-Feb-23
A.2 Appointment of Project Manager and submission of Project Organization chart
A.3 APG Submission and Advance Payment Receiving
A.4 Finalizing Project Team, Project Documentation Format & Implementation Schedule 28-Feb-23 28-May-23

B LINE WORK 28-Feb-23 27-Aug-24

B.1 Pre-Construction Survey 28-Feb-23 17-Apr-23 Milestone 2


a Desk Study 28-Feb-23 3-Mar-23
b Field Survey 28-Feb-23 18-Mar-23
c Preparation of PCS Report and Survey Drawing 18-Mar-23 12-Apr-23
d Submission of Draft and Final PCS Report 13/04/2023 16/04/2023
e Approval of PCS 16/04/2023 17/04/2023

B.2 Procurement of Line Material 3-May-23 30-Mar-24 Milestone 4

a Purchase Order Placement of Line Material 5-Apr-23 20-Dec-23

b Poles, Stay Sets and Other Fittings 26-Apr-23 30-Mar-24


i Delivery to site 12-Sep-23 30-Mar-24

c ABC Cable and Covered Conductor 3-Dec-23 23-Mar-18


i Delivery to site 22-Feb-18 23-Mar-18

d ABC Cable Fittings, Other Hardware & Fittings 13-Oct-23 24-Apr-24


v Delivery to site 10-Mar-24 24-Apr-24

e Transformers and Other Accessories 10-Dec-23 19-Jan-24


i Delivery to site 25-Jan-23 19-Apr-24

B.3 Site Mobilization 15-Sep-23 10-Mar-24 Milestone 3

B.4 Installation Work 8-Sep-23 30-Jun-24 Milestone 5


a Pole Erection 10-Sep-23 30-Apr-24
b ABC Cable Stringing with Stay Installation 16-Mar-24 15-Jun-24
c Transformer Installation 1-Apr-24 30-Jun-18

B.5 Testing, Commissioning, Charging, Final-As Built Drawing and Handover 3-Apr-24 30-Jul-24 Milestone 6
a Final Survey Work 16-Apr-24 15-Jul-24
b Preparation of Final Report with As-Built Drawing 1-Jun-24 30-Jul-24
c Testing, Commissioning & Charging Work 15-Mar-24 15-Jul-24
d Handover to Local Distribution Center 5-May-24 20-Aug-24