SCHEDULE FOR FABRICATION AND INSTALLATION OF GRIZZLY AT POC

Activity ID Activity Name Original Start Finish Schedule % Qtr 1, 2023 Qtr 2, 2023 3, 2023
Duration Complete
Jan Feb Mar Apr May Jun Jul
83 21-Feb-23 15-May-23 0% 15-May-23, POC FABRICATION AN
POC FABRICATION
FAB AND INSTALLATION OF GRIZZLY AT POC
POC.1 GENERAL
GE MILESTONES 83 21-Feb-23 15-May-23 0% 15-May-23, POC.1 GENERAL MILE
A1001 project award 0 21-Feb-23* 0% project award, 21-Feb-23*
A1010 Commencement of Fabrication 0 28-Mar-23 0% Commencement of Fabrication, 28-Mar-23
A1020 Fabrication Completion 0 07-May-23 0% Fabrication Completion,
A1030 Commencement of Site Activities 0 11-May-23 0% Commencement of Site Activities, 11-M
A1040 Construction Completion 0 14-May-23 0% Construction Completion,
A1050 Taking Over 0 15-May-23 0% Taking Over,

POC.2 MATERIAL
MA PROCUREMENT 33 21-Feb-23 26-Mar-23 0% 26-Mar-23, POC.2 MATERIAL PROCUREMENT

POC.2.1 M
MATERIAL PO ISSUANCE 7 21-Feb-23 28-Feb-23 0% 28-Feb-23, POC.2.1 MATERIAL PO ISSUANCE
A1060 Structural material 7 21-Feb-23 28-Feb-23 0% Structural material
POC.2.6 M
MATERIAL DELIVERY 26 28-Feb-23 26-Mar-23 0% 26-Mar-23, POC.2.6 MATERIAL DELIVERY
A1070 Structural material 26 28-Feb-23 26-Mar-23 0% Structural material

POC.3 FABRICATION
FA 42 26-Mar-23 07-May-23 0% 07-May-23, POC.3 FABRICATION

POC.3.1 FA
FABRICATION OF GRIZZLY 42 26-Mar-23 07-May-23 0% 07-May-23, POC.3.1 FABRICATION OF G
A1080 Material and equiment arrangement 2 26-Mar-23 28-Mar-23 0% Material and equiment arrangement
A1090 Marking and cutting of plate as per required dimensions 14 28-Mar-23 11-Apr-23 0% Marking and cutting of plate as per required dimensions
A1100 fitup and welding 22 11-Apr-23 03-May-23 0% fitup and welding
A1110 NDT for weld joints 3 03-May-23 06-May-23 0% NDT for weld joints
A1120 Dispatching of grizzly to site for installaton 1 06-May-23 07-May-23 0% Dispatching of grizzly to site for installaton

POC.4 INSTALLATION
INS 7 07-May-23 14-May-23 0% 14-May-23, POC.4 INSTALLATION

POC.4.1 GENERAL
G 4 07-May-23 11-May-23 0% 11-May-23, POC.4.1 GENERAL
A1130 Shifting of grizzly to POC 1 07-May-23 08-May-23 0% Shifting of grizzly to POC
A1140 Assembly of newly fabricated grizzly 1 07-May-23 08-May-23 0% Assembly of newly fabricated grizzly
A1150 mobilization of crane (MWSPC Scope) 1 08-May-23 09-May-23 0% mobilization of crane (MWSPC Scope)
A1160 Equipment shut down 1 09-May-23 10-May-23 0% Equipment shut down
A1170 Scaffolding erection 1 10-May-23 11-May-23 0% Scaffolding erection
POC.4.2 IN
INSTALLATION OF GRIZZLY 3 11-May-23 14-May-23 0% 14-May-23, POC.4.2 INSTALLATION
A1180 Dismantiling of existing grizzly 1 11-May-23 12-May-23 0% Dismantiling of existing grizzly
A1190 Inspection of hopper support 1 11-May-23 12-May-23 0% Inspection of hopper support
A1200 Support strengthening 1 12-May-23 13-May-23 0% Support strengthening
A1210 installation of new fabricated grizzly 1 12-May-23 13-May-23 0% installation of new fabricated grizzly
A1220 Bot torquing and inspection 1 13-May-23 14-May-23 0% Bot torquing and inspection

POC.5 COMMISSIONING
CO AND START-UP 1 14-May-23 15-May-23 0% 15-May-23, POC.5 COMMISSIONIN
A1230 scaffolding dismantiling 1 14-May-23 15-May-23 0% scaffolding dismantiling
A1240 Start up 1 14-May-23 15-May-23 0% Start up

Actual Level of Effort Remaining Work Milestone Page 1 of 1 GULF ASIA LLC