FIRST e-BANK TOWER CONDOMINIUM CORPORATION

LIST OF UNIT OWNERS AND TENANTS AFFECTED WITH RETROFTTING WORKS

NO. FLOOR UNIT UNIT OWNER/ TENANT LOCATION DATE


7 MEZZANINE UNIT 1 & UNIT 2 SOCIAL HOUSING FINANCE CORPORATION PASEO AND VALERO SIDE SEPT 07- AUG 19, 2023
5 5HT FLOOR UNIT 1 & UNIT 2 SOCIAL HOUSING FINANCE CORPORATION PASEO AND VALERO SIDE JULY 05- SEPT 03, 2023
2 9TH FLOOR UNIT 1 & UNIT 2 SOCIAL HOUSING FINANCE CORPORATION PASEO AND VALERO SIDE MARCH 23-MAY17, 2023
6 11TH FLOOR UNIT 1 & UNIT 2 GF PARTNERS & ARCHITECTS CO. PASEO AND VALERO SIDE JULY 10-SEPT 06, 2023
8 12TH FLOOR UNIT 1 & UNIT 2 COMMONWEALTH INSURANCE CO. PASEO AND VALERO SIDE SEPT 12- NOV 09, 2023
14TH FLOOR UNIT 1 TRENDS TRAVELMART INT'L CORP. PASEO SIDE APRIL 26-MAY 21, 2023
3
14TH FLOOR UNIT 2 E- HORIZON VALERO SIDE MARCH 26-APRIL 25, 2023
9 15TH FLOOR UNIT 1 & UNIT 2 SOCIAL HOUSING FINANCE CORPORATION PASEO AND VALERO SIDE NOV 10-JAN 12, 2023
16TH FLOOR UNIT 1 A GF PARTNERS & ARCHITECTS CO. PASEO SIDE
JUNE 05-JULY 04,2023
4 16TH FLOOR UNIT 1 B PARAGON CREDIT ALLIANCE PASEO SIDE
16TH FLOOR UNIT 2 COLOSSUS PROPERTIES, INC. (VACANT) VALERO SIDE MAY 22-JUNE 04, 2023
1 17TH FLOOR UNIT 1 & UNIT 2 OMYA CHEMICAL MERCHANTS, INC. PASEO AND VALERO SIDE MARCH 09-MAR 22, 2023
20th FLOOR UNIT 1 ANCHORPOINT PASEO PROPERTIES PASEO SIDE DEC 13-JAN 12, 2023
10
21ST FLOOR UNIT 2 SINGA SHIP MANAGEMENT PHILS, INC. VALERO SIDE NOV 10-DEC 12, 2023
11 22ND FLOOR UNIT 1 & UNIT 2 SHIP HOTEL CRUISE INSTITUTE OF THE PHIL. PASEO AND VALERO SIDE JAN 13-MAR 02, 2023

FIRST BATCH: 17TH, 19TH, 14TH, 16TH

SECOND BATCH: 5TH, 11TH, MEZZANINE, 12TH

THIRD BATCH: 15TH, 21ST, 22ND


1. 1. SCAFFOLDING AND STAGING WORKS – APRIL 15, 2023 8. 1. SCAFFOLDING AND STAGING WORKS – MARCH 30, 2023
2. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 16, 2023 9. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES –MARCH 31, 2023
3. 3. BOARD UP - APRIL 16, 2023 10. 3. BOARD UP - MARCH 31, 2023
4. 4. CHIPPING AND GRINDING WORKS – APRIL 17, 2023 11. 4. CHIPPING AND GRINDING WORKS – APRIL 01, 2023
5. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- APRIL 17-18, 2023 12. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- APRIL 01-02, 2023
6. 6. CFRP APPLICATION – APRIL 19 , 2023 13. 6. CFRP APPLICATION – APRIL 3, 2023
7. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 20-21 ,2023 14. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 4, 2023

50. 1. SCAFFOLDING AND STAGING WORKS – APRIL 4, 2023


15. 1. SCAFFOLDING AND STAGING WORKS – MARCH 23, 2023
51. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 5, 2023
16. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES –MARCH 24-25, 2023
52. 3. BOARD UP - APRIL 5, 2023
17. 3. BOARD UP - MARCH 25, 2023
53. 4. CHIPPING AND GRINDING WORKS – APRIL 11, 2023
18. 4. CHIPPING AND GRINDING WORKS – MARCH 26, 2023
54. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- APRIL 11-12, 2023
19. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- MARCH 27-28, 2023
55. 6. CFRP APPLICATION – APRIL 13, 2023
20. 6. CFRP APPLICATION – MARCH 29, 2023
56. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 14, 2023
21. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MARCH 30, 2023

29. 1. SCAFFOLDING AND STAGING WORKS – APRIL 26, 2023


43. 1. SCAFFOLDING AND STAGING WORKS – MAY 11, 2023
30. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES –APRIL 27, 2023
44. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 11-12, 2023
31. 3. BOARD UP - APRIL 27, 2023
45. 3. BOARD UP - MAY 12, 2023
32. 4. CHIPPING AND GRINDING WORKS – APRIL28, 2023
46. 4. CHIPPING AND GRINDING WORKS – MAY 13-14, 2023
33. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- APRIL 28-29, 2023
47. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- MAY 14-15, 2023
34. 6. CFRP APPLICATION – APRIL 30, 2023
48. 6. CFRP APPLICATION – MAY 16, 2023
35. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 2 ,2023
49. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 17 ,2023

22. 1. SCAFFOLDING AND STAGING WORKS – MAY 3, 2023


36. 1. SCAFFOLDING AND STAGING WORKS APRIL 21, 2023
23. 2DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 4, 2023
37. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES –APRIL 22, 2023
24. 3. BOARD UP - MAY 4, 2023
38. 3. BOARD UP - APRIL 22, 2023
25. 4. CHIPPING AND GRINDING WORKS – MAY 5-6, 2023
39. 4. CHIPPING AND GRINDING WORKS – APRIL 23, 2023
26. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- MAY 6-8, 2023
40. 5. APPLICATION OF EPOXY MORTAR AND INJECTION-APRIL 23-24, 2023
41. 6. CFRP APPLICATION – APRIL 25, 2023 27. 6. CFRP APPLICATION – MAY 9, 2023
28. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 10-11 ,2023
42. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 26 ,2023
64. 1. SCAFFOLDING AND STAGING WORKS – APRIL 18, 2023 57. 1. SCAFFOLDING AND STAGING WORKS – APRIL 1, 2023
65. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 19, 2023 58. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 2, 2023
3. BOARD UP - APRIL 20, 2023 59. 3. BOARD UP - APRIL 2, 2023
66. 4. CHIPPING AND GRINDING WORKS – APRIL 21, 2023 60. 4. CHIPPING AND GRINDING WORKS – APRIL 3, 2023
67. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – APRIL 21-22,2023 61. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- APRIL 3-4, 2023
68. 6. CFRP APPLICATION – APRIL 23,2023 62. 6. CFRP APPLICATION – APRIL 5,2023
69. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 24-25,2023 63. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 6,2023

104. 1. SCAFFOLDING AND STAGING WORKS – APRIL 11, 2023


70. 1. SCAFFOLDING AND STAGING WORKS – MARCH 26, 2023
105. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 12, 2023
71. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES –MARCH 27, 2023
106. 3. BOARD UP - APRIL 12, 2023
3. BOARD UP - MARCH 27, 2023
107. 4. CHIPPING AND GRINDING WORKS – APRIL 13-14, 2023
72. 4. CHIPPING AND GRINDING WORKS – MARCH 28, 2023
108. 5. APPLICATION OF EPOXY MORTAR AND INJECTION- APRIL 14-15, 2023
73. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – MARCH 29-30,2023
109. 6. CFRP APPLICATION – APRIL 16,2023
74. 6. CFRP APPLICATION – MARCH 31,2023
110. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 16-18,2023
75. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES –APRIL 1,2023

83. 1. SCAFFOLDING AND STAGING WORKS – APRIL 30,2023


97. 1. SCAFFOLDING AND STAGING WORKS – MAY 15,2023
84. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 2, 2023
98. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 16, 2023
85. 3. BOARD UP - MAY 2, 2023
99. 3. BOARD UP - MAY 16, 2023
86. 4. CHIPPING AND GRINDING WORKS – MAY 3, 2023
100. 4. CHIPPING AND GRINDING WORKS – MAY 17-18, 2023
87. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – MAY 3-4,2023
101. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – MAY 18-19,2023
88. 6. CFRP APPLICATION – MAY 5,2023
102. 6. CFRP APPLICATION – MAY 20,2023
89. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 6, 2023
103. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 21,2023

76. 1. SCAFFOLDING AND STAGING WORKS – MAY 7,2023


90. 1. SCAFFOLDING AND STAGING WORKS – APRIL 25,2023
77. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 8, 2023
91. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 26, 2023
78. 3. BOARD UP - MAY 8, 2023
92. 3. BOARD UP - APRIL 26, 2023
79. 4. CHIPPING AND GRINDING WORKS – MAY 9-10, 2023
93. 4. CHIPPING AND GRINDING WORKS – APRIL 27, 2023
80. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – MAY 10-12,2023
94. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – APRIL 27-28,2023
81. 6. CFRP APPLICATION – MAY 13,2023
95. 6. CFRP APPLICATION – APRIL 29,2023
82. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 14-15,2023
96. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – APRIL 30,2023
118. 1. SCAFFOLDING AND STAGING WORKS – MAY 29, 2023
119. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 30, 2023
120. 3. BOARD UP - MAY 31, 2023
121. 4. CHIPPING AND GRINDING WORKS – JUNE 01, 2023
122. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – JUNE 2, 2023
123. 6. CFRP APPLICATION – JUNE 3, 2023
124. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JUNE 4, 2023

111. 1. SCAFFOLDING AND STAGING WORKS – MAY 25, 2023


125. 1. SCAFFOLDING AND STAGING WORKS – MAY 22, 2023
112. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES -MAY 26, 2023
126. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JUNE 22, 2023
113. 3. BOARD UP - MAY 26, 2023
127. 3. BOARD UP - JUNE 22, 2023
114. 4. CHIPPING AND GRINDING WORKS – MAY 27, 2022
128. 4. CHIPPING AND GRINDING WORKS – MAY 23, 2023
115. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – MAY 28-29, 2023
129. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – MAY 24-25, 2023
116. 6. CFRP APPLICATION – MAY 30, 2023
130. 6. CFRP APPLICATION – MAY 26, 2023
117. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 31, 2023
131. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAY 27, 2023

139. 1. SCAFFOLDING AND STAGING WORKS – JUNE 5, 2023


140. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JUNE 6-7, 2023
141. 3. BOARD UP - JUNE 7, 2023
142. 4. CHIPPING AND GRINDING WORKS – JUNE 8, 2023
143. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – JUNE 9-10, 2023
144. 6. CFRP APPLICATION – JUNE 11, 2023
145. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JUNE 13-14, 2023

132. 1. SCAFFOLDING AND STAGING WORKS – JUNE 24, 2023


133. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JUNE 25, 2023
146. 1. SCAFFOLDING AND STAGING WORKS – JUNE 15, 2023 134. 3. BOARD UP - JUNE 26, 2023
147. 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JUNE 16, 2023 135. 4. CHIPPING AND GRINDING WORKS – JUNE 27-29, 2023
148. 3. BOARD UP - JUNE 16 2023 136. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – JUNE 29-30, 2023
149. 4. CHIPPING AND GRINDING WORKS – JUNE 17-18, 2023 137. 6. CFRP APPLICATION –JULY 1, 2023
150. 5. APPLICATION OF EPOXY MORTAR AND INJECTION – JUNE 18-19, 2023 138. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY2-4 2023
151. 6. CFRP APPLICATION – JUNE 20, 2023
152. 7. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JUNE 21-23 2023

16
1. SCAFFOLDING AND SHORING WORKS – JULY 5, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 6, 2023
3. BOARD UP –JULY 7, 2023
4. CHIPPING AND GRINDING WORKS – JULY 8-9,2023
5. APPLICATION OF EPOXY MORTAR –JULY 10-11,2023
6. APPLICATION OF EPOXY INJECTION – JUL7 11, 2023
1. SCAFFOLDING AND SHORING WORKS – JULY 27, 2023 7. CFRP APPLICATION – JULY 12, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 28, 2023 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 13-15, 2023
3. BOARD UP – JULY 28, 2023
4. CHIPPING AND GRINDING WORKS – JULY 29-30, 2023
5. APPLICATION OF EPOXY MORTAR – JULY 31-AUG 1, 2023
6. APPLICATION OF EPOXY INJECTION – AUGUST 1, 2023
7. CFRP APPLICATION – AUGUST 2, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUGUST 3-5, 2023, 2023

1. SCAFFOLDING AND SHORING WORKS – JULY 16, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 17, 2023
3. BOARD UP – JULY 18,2023
1. SCAFFOLDING AND SHORING WORKS – AUG 16, 2023 4. CHIPPING AND GRINDING WORKS – JULY 19-20, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 17, 2023 5. APPLICATION OF EPOXY MORTAR – JULY 21-22, 2023
3. BOARD UP – AUGUST 17, 2023 6. APPLICATION OF EPOXY INJECTION – JULY 22, 2023
4. CHIPPING AND GRINDING WORKS – AUG 18-19, 2023 7. CFRP APPLICATION – JULY 23, 2023
5. APPLICATION OF EPOXY MORTAR – AUGUST 20-21, 2023 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 24-26, 2023
6. APPLICATION OF EPOXY INJECTION – AUG 21, 2023
7. CFRP APPLICATION – AUG 22, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 23-24, 2023

1. SCAFFOLDING AND SHORING WORKS – AUGUST 6, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 7, 2023
3. BOARD UP – AUG 7, 2023
4. CHIPPING AND GRINDING WORKS – AUG 8-9, 2023 1. SCAFFOLDING AND SHORING WORKS – AUG 25, 2023
5. APPLICATION OF EPOXY MORTAR –AUG 10-11, 2023 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 26, 2023
6. APPLICATION OF EPOXY INJECTION – AUGUST 11, 2023 3. BOARD UP – AUG 26, 2023
7. CFRP APPLICATION – AUG 12, 2023 4. CHIPPING AND GRINDING WORKS – AUG 27-28, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 13-15, 2023 5. APPLICATION OF EPOXY MORTAR – AUG 29-30, 2023
6. APPLICATION OF EPOXY INJECTION AUG 30, 2023
7. CFRP APPLICATION – AUG 31, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEPT 1-3, 2023
1. SCAFFOLDING AND SHORING WORKS – JULY 10, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 11, 2023
3. BOARD UP –JULY 11, 2023
4. CHIPPING AND GRINDING WORKS – JULY 12-13,2023
5. APPLICATION OF EPOXY MORTAR –JULY 13-14,2023
6. APPLICATION OF EPOXY INJECTION – JUL7 15, 2023
1. SCAFFOLDING AND SHORING WORKS – JULY 27, 2023 7. CFRP APPLICATION – JULY 16, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 28, 2023 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 17, 2023
3. BOARD UP – JULY 28, 2023
4. CHIPPING AND GRINDING WORKS – JULY 29-30, 2023
5. APPLICATION OF EPOXY MORTAR – JULY 31-AUG 1, 2023
6. APPLICATION OF EPOXY INJECTION – AUGUST 1, 2023
7. CFRP APPLICATION – AUGUST 2, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUGUST 3-5, 2023, 2023

1. SCAFFOLDING AND SHORING WORKS – JULY 18, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 19, 2023
1. SCAFFOLDING AND SHORING WORKS – AUG 28, 2023 3. BOARD UP – JULY 19,2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 29, 2023 4. CHIPPING AND GRINDING WORKS – JULY 20-21, 2023
3. BOARD UP – AUG 30, 2023 5. APPLICATION OF EPOXY MORTAR – JULY 22-23, 2023
4. CHIPPING AND GRINDING WORKS – AUG 31-SEP1, 2023 6. APPLICATION OF EPOXY INJECTION – JULY 23, 2023
5. APPLICATION OF EPOXY MORTAR – SEP 2-3, 2023 7. CFRP APPLICATION – JULY 23, 2023
6. APPLICATION OF EPOXY INJECTION AUG 3, 2023 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JULY 24-26, 2023
7. CFRP APPLICATION – SEP 4, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEPT 5-6, 2023

1. SCAFFOLDING AND SHORING WORKS – AUGUST 6, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 7, 2023
3. BOARD UP – AUG 7, 2023
4. CHIPPING AND GRINDING WORKS – AUG 8-9, 2023
5. APPLICATION OF EPOXY MORTAR –AUG 10-11, 2023 1. SCAFFOLDING AND SHORING WORKS – AUG 17, 2023
6. APPLICATION OF EPOXY INJECTION – AUGUST 11, 2023 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 18, 2023
7. CFRP APPLICATION – AUG 12, 2023 3. BOARD UP – AUGUST 19, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 13-16, 2023 4. CHIPPING AND GRINDING WORKS – AUG 20-21, 2023
5. APPLICATION OF EPOXY MORTAR – AUGUST 22-23, 2023
6. APPLICATION OF EPOXY INJECTION – AUG 23, 2023
7. CFRP APPLICATION – AUG 24, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 25-27, 2023
1. SCAFFOLDING AND SHORING WORKS – SEPT 7-13, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEPT 29-AUG1, 2023
3. BOARD UP – AUG 2, 2023
4. CHIPPING AND GRINDING WORKS – AUG 3-5, 2023
1. SCAFFOLDING AND SHORING WORKS – SEP 7-13, 2023, 2023
5. APPLICATION OF EPOXY MORTAR – AUG 6-8, 2024
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEP 13-15, 2023
6. APPLICATION OF EPOXY INJECTION – AUG 9-10, 2024
3. BOARD UP – SEP 16, 2023
7. CFRP APPLICATION – AUG 11-12, 2024
4. CHIPPING AND GRINDING WORKS – SEP 17-18, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – AUG 13-19, 2024
5. APPLICATION OF EPOXY MORTAR – SEP 19-20, 2023
6. APPLICATION OF EPOXY INJECTION – SEP 21, 2023
7. CFRP APPLICATION – SEP 22-23, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEP 24-28, 2023
1. SCAFFOLDING AND SHORING WORKS – SEP 12, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEP 13, 2023
1. SCAFFOLDING AND SHORING WORKS – OCTOBER 2, 2023
3. BOARD UP – SEP 14, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – OCTOBER 3, 2023
4. CHIPPING AND GRINDING WORKS – SEPT 15-16, 2023
3. BOARD UP – OCTOBER 3, 2023
5. APPLICATION OF EPOXY MORTAR – SEP 17-18, 2023
4. CHIPPING AND GRINDING WORKS – OCTOBER 4, 2023
6. APPLICATION OF EPOXY INJECTION SEP 19, 2023
5. APPLICATION OF EPOXY MORTAR – OCTOBER 5-6, 2023
7. CFRP APPLICATION – SEP 20, 2023
6. APPLICATION OF EPOXY INJECTION – OCTOBER 6, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEP 21-22, 2023
7. CFRP APPLICATION –OCTOBER 7, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – OCTOBER 8-9,2023

1. SCAFFOLDING AND SHORING WORKS – SEPT 22, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEP 23, 2023
3. BOARD UP – SEPT 23, 2023
4. CHIPPING AND GRINDING WORKS – SEPT 24-25, 2023
5. APPLICATION OF EPOXY MORTAR – SEP 26-27, 2023
6. APPLICATION OF EPOXY INJECTION – SEP 28, 2023
1. SCAFFOLDING AND SHORING WORKS – OCTOBER 21, 2023 7. CFRP APPLICATION – SEPT 29, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – OCTOBER 22, 2023 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – SEPT 30-OCT 2, 2023
3. BOARD UP – OCTOBER 22, 2023
4. CHIPPING AND GRINDING WORKS – OCTOBER 23-24, 2023
5. APPLICATION OF EPOXY MORTAR – OCTOBER 24-25, 2023
6. APPLICATION OF EPOXY INJECTION – OCTOBER 26, 2023
7. CFRP APPLICATION –OCTOBER 27, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – OCTOBER 28-30,2023

1. SCAFFOLDING AND SHORING WORKS –OCT 10, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – OCT 11-12, 2023 1. SCAFFOLDING AND SHORING WORKS – OCTOBER 31, 2023
3. BOARD UP – OCT 13, 2023 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – NOV 1 2023
4. CHIPPING AND GRINDING WORKS – OCT 14-15, 2023 3. BOARD UP – NOV 2, 2023
5. APPLICATION OF EPOXY MORTAR – OCT 16-17, 2023 4. CHIPPING AND GRINDING WORKS – NOV 3, 2023
6. APPLICATION OF EPOXY INJECTION – OCT 17, 2023 5. APPLICATION OF EPOXY MORTAR – NOV 4, 2023
7. CFRP APPLICATION –OCT 18, 2023 6. APPLICATION OF EPOXY INJECTION – NOV5, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – OCTOBER 19-20, 2023 7. CFRP APPLICATION –NOV 6, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – NOV 7-9, 2023
1. SCAFFOLDING AND SHORING WORKS – DEC 2, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 3, 2023
1. SCAFFOLDING AND SHORING WORKS – NOV 10, 2023
3. BOARD UP – DEC 4, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – NOV 11-12, 2023
4. CHIPPING AND GRINDING WORKS – DEC 5-6, 2023
3. BOARD U- NOV 12, 2023
5. APPLICATION OF EPOXY MORTAR –DEC 6-7, 2023
4. CHIPPING AND GRINDING WORKS – NOV 13-14, 2023
6. APPLICATION OF EPOXY INJECTION – DEC 8, 2023
5. APPLICATION OF EPOXY MORTAR –NOV 14-15, 2023
7. CFRP APPLICATION – DEC 9, 2023
6. APPLICATION OF EPOXY INJECTION – NOV 16, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 10-12, 2023
7. CFRP APPLICATION – NOV17, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – NOV 18-20, 2023

1. SCAFFOLDING AND SHORING WORKS – NOV 21, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – NOV 22, 2023
3. BOARD UP – NOV 23, 2023
4. CHIPPING AND GRINDING WORKS – NOV 24-25, 2023
5. APPLICATION OF EPOXY MORTAR –NOV 26-27, 2023
6. APPLICATION OF EPOXY INJECTION – NOV 28, 2023
1. SCAFFOLDING AND SHORING WORKS – JAN 2, 2024 7. CFRP APPLICATION – NOV 29, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JAN 3, 2024 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 1-2, 2023
3. BOARD UP – JAN 3, 2024
4. CHIPPING AND GRINDING WORKS – JAN 5-6, 2024
5. APPLICATION OF EPOXY MORTAR –JAN 6-7, 2024
6. APPLICATION OF EPOXY INJECTION – JAN 8, 2024
7. CFRP APPLICATION – JAN 9, 2024
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JAN 10-12, 2024

1. SCAFFOLDING AND SHORING WORKS -DEC 22, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 23, 2023
1. SCAFFOLDING AND SHORING WORKS -DEC 13, 2023 3. BOARD UP –DEC 23, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 14, 2023 4. CHIPPING AND GRINDING WORKS –DEC 23-24, 2023
3. BOARD UP –DEC 14, 2023 5. APPLICATION OF EPOXY MORTAR –DEC 27, 2023
4. CHIPPING AND GRINDING WORKS –DCE 15-16, 2023 6. APPLICATION OF EPOXY INJECTION – DEC 28, 2023
5. APPLICATION OF EPOXY MORTAR –DEC 16-17, 2023 7. CFRP APPLICATION – DEC 29, 2023
6. APPLICATION OF EPOXY INJECTION – DEC 17, 2023 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES -DEC 30, 2023
7. CFRP APPLICATION – DEC 18, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 20-21, 2023
1. SCAFFOLDING AND SHORING WORKS – DEC 2, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 3, 2023
1. SCAFFOLDING AND SHORING WORKS – NOV 10, 2023
3. BOARD UP – DEC 4, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – NOV 11-12, 2023
4. CHIPPING AND GRINDING WORKS – DEC 5-6, 2023
3. BOARD U- NOV 12, 2023
5. APPLICATION OF EPOXY MORTAR –DEC 6-7, 2023
4. CHIPPING AND GRINDING WORKS – NOV 13-14, 2023
6. APPLICATION OF EPOXY INJECTION – DEC 8, 2023
5. APPLICATION OF EPOXY MORTAR –NOV 14-15, 2023
7. CFRP APPLICATION – DEC 9, 2023
6. APPLICATION OF EPOXY INJECTION – NOV 16, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 10-12, 2023
7. CFRP APPLICATION – NOV17, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – NOV 18-20, 2023

1. SCAFFOLDING AND SHORING WORKS – NOV 21, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – NOV 22, 2023
3. BOARD UP – NOV 23, 2023
4. CHIPPING AND GRINDING WORKS – NOV 24-25, 2023
5. APPLICATION OF EPOXY MORTAR –NOV 26-27, 2023
6. APPLICATION OF EPOXY INJECTION – NOV 28, 2023
1. SCAFFOLDING AND SHORING WORKS – JAN 2, 2024 7. CFRP APPLICATION – NOV 29, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JAN 3, 2024 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 1-2, 2023
3. BOARD UP – JAN 3, 2024
4. CHIPPING AND GRINDING WORKS – JAN 5-6, 2024
5. APPLICATION OF EPOXY MORTAR –JAN 6-7, 2024
6. APPLICATION OF EPOXY INJECTION – JAN 8, 2024
7. CFRP APPLICATION – JAN 9, 2024
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JAN 10-12, 2024

1. SCAFFOLDING AND SHORING WORKS -DEC 22, 2023


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 23, 2023
1. SCAFFOLDING AND SHORING WORKS -DEC 13, 2023 3. BOARD UP –DEC 23, 2023
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 14, 2023 4. CHIPPING AND GRINDING WORKS –DEC 23-24, 2023
3. BOARD UP –DEC 14, 2023 5. APPLICATION OF EPOXY MORTAR –DEC 27, 2023
4. CHIPPING AND GRINDING WORKS –DCE 15-16, 2023 6. APPLICATION OF EPOXY INJECTION – DEC 28, 2023
5. APPLICATION OF EPOXY MORTAR –DEC 16-17, 2023 7. CFRP APPLICATION – DEC 29, 2023
6. APPLICATION OF EPOXY INJECTION – DEC 17, 2023 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES -DEC 30, 2023
7. CFRP APPLICATION – DEC 18, 2023
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – DEC 20-21, 2023
1. SCAFFOLDING AND SHORING WORKS -JAN 23-25, 2024
1. SCAFFOLDING AND SHORING WORKS – FEB 2-4, 2024 2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JAN 26, 2024
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – FEB 5, 2024 3. BOARD UP -JAN 26, 2024
3. BOARD UP - FEB 5, 2024 4. CHIPPING AND GRINDING WORKS –JAN 27-28, 2024
4. CHIPPING AND GRINDING WORKS – FEB 6-7, 2024 5. APPLICATION OF EPOXY MORTAR – JAN 28-29, 2024
5. APPLICATION OF EPOXY MORTAR – FEB 7-8, 2024 6. APPLICATION OF EPOXY INJECTION – JAN 29, 2024
6. APPLICATION OF EPOXY INJECTION – FEB 8, 2024 7. CFRP APPLICATION – JAN 30, 2024
7. CFRP APPLICATION – FEB 9, 2024 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JAN 31-FEB1, 2024
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – FEB 10-11, 2024

1. SCAFFOLDING AND SHORING WORKS –JAN 13-15, 2024


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – JAN 16, 2024
3. BOARD UP - JAN 16, 2024
4. CHIPPING AND GRINDING WORKS – JAN 17-18, 2024
5. APPLICATION OF EPOXY MORTAR – JAN 18-19, 2024
6. APPLICATION OF EPOXY INJECTION – JAN 19, 2024
7. CFRP APPLICATION – JAN 20, 2024
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – JAN 21-22, 2024

1. SCAFFOLDING AND SHORING WORKS – FEB 22-24, 2024


2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – FEB 25, 2024
1. SCAFFOLDING AND SHORING WORKS – FEB 12-14, 2024 3. BOARD UP - FEB 25, 2024
2. DISMANTLING OF CIVIL WORKS/ARCHITECTURAL FINISHES – FEB 15, 2024 4. CHIPPING AND GRINDING WORKS – FEB 26-27, 2024
3. BOARD UP - FEB 15, 2024 5. APPLICATION OF EPOXY MORTAR – FEB 27-28, 2024
4. CHIPPING AND GRINDING WORKS – FEB 16-17, 2024 6. APPLICATION OF EPOXY INJECTION – FEB 28, 2024
5. APPLICATION OF EPOXY MORTAR – FEB 17-18, 2024 7. CFRP APPLICATION – FEB 29
6. APPLICATION OF EPOXY INJECTION – FEB 18, 2024 8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – MAR 01-02, 2023
7. CFRP APPLICATION – FEB 19, 2024
8. RESTORATION OF CIVIL WORKS/ARCHITECTURAL FINISHES – FEB 20-21, 2024