PT.

Acset Indonusa Tbk,


Project Asya Commercial Genova Phase 1
SCHEDULE ASYA GENOVA BL03 S.D BL09 v1.R2
ID Task Task Name Duration Start Finish Predecessors Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 Schedule Genova BL03-BL09 v1R2 L5 20231011 574 days 8/31/2022 11/11/2024
1 ASYA COMMERCIAL GENOVA (BL 03 s.d BL 09) 574 days 8/31/2022 11/11/2024
2 Kontrak 262 days 8/31/2022 8/31/2023
3 EoT 1 392 days 8/31/2022 2/29/2024
4 Final Schedule 392 days 8/31/2022 2/29/2024
5 Structure 301 days 8/31/2022 10/25/2023
13 Finishing & MEP 149 days 8/7/2023 2/29/2024
14 1st Floor (Area Interior - BL03 s.d BL09) 100 days 8/7/2023 12/22/2023 7
15 Tenant area 100 days 8/7/2023 12/22/2023
16 GWT 48 days 8/7/2023 10/11/2023
17 Wall finish 60 days 8/7/2023 10/27/2023 16SS
18 - Pasangan dinding 36 days 8/7/2023 9/25/2023 16SS
19 - Plester Dinding 30 days 8/21/2023 9/29/2023 18SS+10 days
20 - Acian Dinding 30 days 9/4/2023 10/13/2023 19SS+10 days
21 - Cat Dinding (BARE) 30 days 9/18/2023 10/27/2023 20SS+10 days
22 Ceilling (BARE) 48 days 8/21/2023 10/25/2023 19SS
23 - Pasangan Rangka & Gypsum 48 days 8/21/2023 10/25/2023 19SS
24 - Compound & Cat (BARE) 30 days 9/14/2023 10/25/2023 23FS-30 days
25 Drylay Marmer (BARE) 20 days 9/18/2023 10/13/2023 21SS
26 Floor Marmer (BARE) 20 days 10/16/2023 11/10/2023 25
27 -Instal Marmer 20 days 10/16/2023 11/10/2023 25
28 Floor HT (BARE) 46 days 10/16/2023 12/18/2023 25
29 Waterproofing Dinding & Lantai 10 days 10/16/2023 10/27/2023 25
30 - Tes Rendam 12 days 10/30/2023 11/14/2023 29
31 Install HT 24 days 11/15/2023 12/18/2023 30
32 Door & Window wall (By Orther) 10 days 10/16/2023 10/27/2023 20
33 Underground Pipe 14 days 10/16/2023 11/2/2023 20
34 Electrical 18 days 11/3/2023 11/28/2023 33
35 Plumbing 24 days 11/3/2023 12/6/2023 34SS
36 Accessories 12 days 12/7/2023 12/22/2023 35
37 Toilet 90 days 8/21/2023 12/22/2023 15SS+10 days
38 Wall finish 41 days 8/21/2023 10/16/2023 15SS+10 days
39 - Pasangan dinding 36 days 8/21/2023 10/9/2023 18SS+5 days
40 - Plester Dinding 36 days 8/28/2023 10/16/2023 39SS+5 days
41 - Pasangan HT (BARE) 24 days 9/11/2023 10/12/2023 40SS+10 days
42 Ceilling (BARE) 40 days 8/21/2023 10/13/2023 22SS
43 - Pasangan Rangka & Gypsum 36 days 8/21/2023 10/9/2023 22SS
44 - Compound & Cat (BARE) 30 days 9/4/2023 10/13/2023 43SS+10 days
45 Floor HT (BARE) 42 days 10/16/2023 12/12/2023 28SS
46 Waterproofing Dinding & Lantai 12 days 10/16/2023 10/31/2023 28SS
47 -Tes rendam 12 days 11/1/2023 11/16/2023 46
48 Install HT 18 days 11/17/2023 12/12/2023 47
49 Door (By Orther) 10 days 10/16/2023 10/27/2023 32SS

Task Inactive Milestone Start-only Path Predecessor Summary Task

Split Inactive Summary Finish-only Path Predecessor Normal Task

Project: Schedule Genova BL03-BL09 v1R2 L5 20231 Milestone Manual Task External Tasks Critical
Date: 10/19/2023 Summary Duration-only External Milestone Critical Split

Project Summary Manual Summary Rollup Deadline Progress

Inactive Task Manual Summary Path Predecessor Milestone Task Manual Progress

10/19/2023 1
PT. Acset Indonusa Tbk,
Project Asya Commercial Genova Phase 1
SCHEDULE ASYA GENOVA BL03 S.D BL09 v1.R2
ID Task Task Name Duration Start Finish Predecessors Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
50 - Instal Door 10 days 10/16/2023 10/27/2023 32SS
51 Underground Pipe 14 days 10/16/2023 11/2/2023 33SS
52 Electrical 18 days 11/3/2023 11/28/2023 34SS
53 Plumbing 24 days 11/3/2023 12/6/2023 35SS
54 Accecories 12 days 12/7/2023 12/22/2023 36SS
55 Pantry 85 days 8/28/2023 12/22/2023 15SS+15 days
56 Wall finish 68 days 8/28/2023 11/29/2023 15SS+15 days
57 - Pasangan dinding 48 days 8/28/2023 11/1/2023 39SS+5 days
58 - Plester Dinding 48 days 9/11/2023 11/15/2023 57SS+10 days
59 - Acian Dinding 48 days 9/25/2023 11/29/2023 58SS+10 days
60 - Pasangan HT (BARE) 30 days 10/9/2023 11/17/2023 59SS+10 days
61 Ceilling (BARE) 46 days 8/28/2023 10/30/2023 22SS
62 - Pasangan Rangka & Gypsum 36 days 8/28/2023 10/16/2023 22SS
63 - Compound & Cat 36 days 9/11/2023 10/30/2023 62SS+10 days
64 Top table 18 days 10/9/2023 11/1/2023 60SS
65 -install Granit 18 days 10/9/2023 11/1/2023 60SS
66 Underground Pipe 14 days 10/16/2023 11/2/2023 51SS
67 Electrical 18 days 11/3/2023 11/28/2023 52SS
68 Plumbing 24 days 11/3/2023 12/6/2023 53SS
69 Accessories 12 days 12/7/2023 12/22/2023 54SS
70 Staircase 49 days 9/18/2023 11/23/2023
71 - Screed (BARE) 36 days 9/18/2023 11/6/2023 15SS+30 days
72 - install HT (BARE) 36 days 10/2/2023 11/20/2023 71SS+10 days
73 - Install Ralling (BARE) 18 days 10/16/2023 11/8/2023 72SS+10 days
74 - Finish cat (BARE) 24 days 10/23/2023 11/23/2023 73SS+5 days
75 Electrical 18 days 10/2/2023 10/25/2023 71SS+10 days
76 Accessories 12 days 10/26/2023 11/10/2023 75
77 Storage 90 days 8/21/2023 12/22/2023
78 Wall finish 56 days 9/4/2023 11/20/2023
79 - Pasangan dinding 36 days 9/4/2023 10/23/2023 17SS+20 days
80 - Plester Dinding 36 days 9/18/2023 11/6/2023 79SS+10 days
81 - Acian Dinding 36 days 10/2/2023 11/20/2023 80SS+10 days
82 Ceilling (BARE) 51 days 8/21/2023 10/30/2023
83 - Pasangan Rangka & Gypsum 36 days 8/21/2023 10/9/2023 22SS
84 - Compound & Cat 36 days 9/11/2023 10/30/2023 83SS+15 days
85 HT (BARE) 46 days 10/17/2023 12/19/2023
86 - screed 36 days 10/17/2023 12/5/2023 79FS-5 days
87 - install HT 36 days 10/31/2023 12/19/2023 86SS+10 days
88 Electrical 18 days 11/3/2023 11/28/2023 67SS
89 Accessories 12 days 12/7/2023 12/22/2023 69SS
90 Door (By Orther) 10 days 10/30/2023 11/10/2023 32
91 - install door 10 days 10/30/2023 11/10/2023 32
92 Hall 36 days 11/3/2023 12/22/2023
Task Inactive Milestone Start-only Path Predecessor Summary Task

Split Inactive Summary Finish-only Path Predecessor Normal Task

Project: Schedule Genova BL03-BL09 v1R2 L5 20231 Milestone Manual Task External Tasks Critical
Date: 10/19/2023 Summary Duration-only External Milestone Critical Split

Project Summary Manual Summary Rollup Deadline Progress

Inactive Task Manual Summary Path Predecessor Milestone Task Manual Progress

10/19/2023 2
PT. Acset Indonusa Tbk,
Project Asya Commercial Genova Phase 1
SCHEDULE ASYA GENOVA BL03 S.D BL09 v1.R2
ID Task Task Name Duration Start Finish Predecessors Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
93 SKTR & SKSR Installation 18 days 11/3/2023 11/28/2023 67SS
94 Electricity Meter 18 days 11/15/2023 12/8/2023 93FS-10 days
95 Main Line Water Installation 18 days 11/27/2023 12/20/2023 94FS-10 days
96 Water Meter 12 days 12/7/2023 12/22/2023 95FS-10 days
97 2nd Floor (BL03 s.d BL09) 82 days 9/26/2023 1/17/2024
98 Tenant area 76 days 9/26/2023 1/9/2024
99 Wall finish 44 days 9/26/2023 11/24/2023
100 - Pasangan dinding 30 days 9/26/2023 11/6/2023 18
101 - Plester Dinding 24 days 10/10/2023 11/10/2023 100SS+10 days
102 - Acian Dinding 24 days 10/24/2023 11/24/2023 101SS+10 days
103 Ceilling (BARE) 36 days 10/24/2023 12/12/2023
104 - Pasangan Rangka & Gypsum 24 days 10/24/2023 11/24/2023 102SS
105 - Compound & Cat 24 days 11/9/2023 12/12/2023 104SS+12 days
106 HT (BARE) 26 days 10/30/2023 12/4/2023
107 waterproofing Dinding & Lantai 12 days 10/30/2023 11/14/2023 29
108 - Tes Rendam 6 days 11/9/2023 11/16/2023 107SS+8 days
109 Install HT 12 days 11/17/2023 12/4/2023 108
110 Door & Window wall (By Orther) 12 days 12/13/2023 12/28/2023
111 - Door & Window wall (By Orther) 12 days 12/13/2023 12/28/2023 105
112 Electrical 18 days 11/29/2023 12/22/2023 34
113 Plumbing 18 days 12/7/2023 1/1/2024 35
114 Accessories 12 days 12/25/2023 1/9/2024 36
115 Toilet 66 days 10/10/2023 1/9/2024
116 Wall finish 23 days 11/7/2023 12/7/2023
117 - Pasangan dinding 18 days 11/7/2023 11/30/2023 100
118 - Plester Dinding 18 days 11/14/2023 12/7/2023 117SS+5 days
119 - Pasangan HT (BARE) 12 days 11/21/2023 12/6/2023 118SS+5 days
120 Ceilling (BARE) 30 days 10/10/2023 11/20/2023
121 - Pasangan Rangka & Gypsum 18 days 10/10/2023 11/2/2023 43
122 - Compound & Cat 18 days 10/26/2023 11/20/2023 121SS+12 days
123 Floor HT (BARE) 24 days 11/1/2023 12/4/2023
124 - Waterproofing Dinding & Lantai 18 days 11/1/2023 11/24/2023 46
125 - Tes Rendam 12 days 11/9/2023 11/24/2023 124SS+6 days
126 - Install HT 12 days 11/17/2023 12/4/2023 125SS+6 days
127 Door (By Orther) 12 days 10/30/2023 11/14/2023
128 - Instal Door 12 days 10/30/2023 11/14/2023 50
129 Coring Lantai 12 days 11/27/2023 12/12/2023 124
130 Electrical 18 days 11/29/2023 12/22/2023 52
131 Plumbing 18 days 12/7/2023 1/1/2024 53
132 Accessories 12 days 12/25/2023 1/9/2024 54
133 Pantry 67 days 10/17/2023 1/17/2024
134 Wall finish 36 days 11/2/2023 12/21/2023
135 - Pasangan dinding 24 days 11/2/2023 12/5/2023 57
Task Inactive Milestone Start-only Path Predecessor Summary Task

Split Inactive Summary Finish-only Path Predecessor Normal Task

Project: Schedule Genova BL03-BL09 v1R2 L5 20231 Milestone Manual Task External Tasks Critical
Date: 10/19/2023 Summary Duration-only External Milestone Critical Split

Project Summary Manual Summary Rollup Deadline Progress

Inactive Task Manual Summary Path Predecessor Milestone Task Manual Progress

10/19/2023 3
PT. Acset Indonusa Tbk,
Project Asya Commercial Genova Phase 1
SCHEDULE ASYA GENOVA BL03 S.D BL09 v1.R2
ID Task Task Name Duration Start Finish Predecessors Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
136 - Plester Dinding 24 days 11/10/2023 12/13/2023 135SS+6 days
137 - Acian Dinding 18 days 11/20/2023 12/13/2023 136SS+6 days
138 - Pasangan HT (BARE) 18 days 11/28/2023 12/21/2023 137SS+6 days
139 Ceilling (BARE) 30 days 10/17/2023 11/27/2023
140 - Pasangan Rangka & Gypsum 24 days 10/17/2023 11/17/2023 62
141 - Compound & Cat 18 days 11/2/2023 11/27/2023 140SS+12 days
142 Top table 18 days 11/2/2023 11/27/2023
143 - Install top table 18 days 11/2/2023 11/27/2023 65
144 Coring Lantai 12 days 12/13/2023 12/28/2023 129
145 Electrical 24 days 11/29/2023 1/1/2024 67
146 Plumbing 18 days 12/7/2023 1/1/2024 68
147 Accessories 18 days 12/25/2023 1/17/2024 69
148 Staircase (BARE) 52 days 10/26/2023 1/5/2024
149 - Screed (BARE) 30 days 11/7/2023 12/18/2023 71
150 - install HT (BARE) 30 days 11/21/2023 1/1/2024 149SS+10 days
151 - Install Ralling (BARE) 18 days 11/28/2023 12/21/2023 150SS+5 days
152 - Finish cat (BARE) 24 days 12/5/2023 1/5/2024 151SS+5 days
153 Electrical 24 days 10/26/2023 11/28/2023 75
154 Accessories 18 days 11/13/2023 12/6/2023 76
155 3rd Floor (BL03 s.d BL09) 72 days 11/3/2023 2/12/2024
156 Tenant area 58 days 11/7/2023 1/25/2024
157 Wall finish 40 days 11/7/2023 1/1/2024
158 - Pasangan dinding 30 days 11/7/2023 12/18/2023 100
159 - Plester Dinding 30 days 11/21/2023 1/1/2024 158SS+10 days
160 - Acian Dinding 24 days 11/28/2023 12/29/2023 159SS+5 days
161 Ceilling (BARE) 36 days 11/27/2023 1/15/2024
162 - Pasangan Rangka & Gypsum 24 days 11/27/2023 12/28/2023 104
163 - Compound & Cat 24 days 12/13/2023 1/15/2024 105
164 Floor HT (BARE) 34 days 11/15/2023 1/1/2024
165 - Waterproofing Dinding & Lantai 24 days 11/15/2023 12/18/2023 107
166 - Tes Rendam 12 days 11/29/2023 12/14/2023 165SS+10 days
167 - Install HT 18 days 12/7/2023 1/1/2024 166SS+6 days
168 Door & Window wall (By Orther) 12 days 12/29/2023 1/15/2024
169 - Door & Window wall 12 days 12/29/2023 1/15/2024 111
170 Electrical 18 days 12/25/2023 1/17/2024 112
171 Plumbing 18 days 1/2/2024 1/25/2024 113
172 Accessories 12 days 1/10/2024 1/25/2024 114
173 Toilet 72 days 11/3/2023 2/12/2024
174 Wall finish 23 days 12/19/2023 1/18/2024
175 - Pasangan dinding 18 days 12/19/2023 1/11/2024 158
176 - Plester Dinding 18 days 12/26/2023 1/18/2024 175SS+5 days
177 - Pasangan HT (BARE) 12 days 1/2/2024 1/17/2024 176SS+5 days
178 Ceilling (BARE) 24 days 11/3/2023 12/6/2023
Task Inactive Milestone Start-only Path Predecessor Summary Task

Split Inactive Summary Finish-only Path Predecessor Normal Task

Project: Schedule Genova BL03-BL09 v1R2 L5 20231 Milestone Manual Task External Tasks Critical
Date: 10/19/2023 Summary Duration-only External Milestone Critical Split

Project Summary Manual Summary Rollup Deadline Progress

Inactive Task Manual Summary Path Predecessor Milestone Task Manual Progress

10/19/2023 4
PT. Acset Indonusa Tbk,
Project Asya Commercial Genova Phase 1
SCHEDULE ASYA GENOVA BL03 S.D BL09 v1.R2
ID Task Task Name Duration Start Finish Predecessors Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
179 - Pasangan Rangka & Gypsum 18 days 11/3/2023 11/28/2023 121
180 - Compound & Cat 18 days 11/13/2023 12/6/2023 179SS+6 days
181 Floor HT (BARE) 30 days 12/19/2023 1/29/2024
182 - Waterproofing Dinding & Lantai 18 days 12/19/2023 1/11/2024 165
183 - Tes Rendam 12 days 12/27/2023 1/11/2024 182SS+6 days
184 - Install HT 18 days 1/4/2024 1/29/2024 183SS+6 days
185 Door (By Orther) 12 days 11/15/2023 11/30/2023
186 - Instal Door 12 days 11/15/2023 11/30/2023 128
187 Coring Lantai 12 days 12/13/2023 12/28/2023 129
188 Electrical 18 days 1/18/2024 2/12/2024 170
189 Plumbing 12 days 1/26/2024 2/12/2024 171
190 Accecories 12 days 1/26/2024 2/12/2024 172
191 Pantry 55 days 11/20/2023 2/2/2024
192 Wall finish 36 days 12/6/2023 1/24/2024
193 - Pasangan dinding 24 days 12/6/2023 1/8/2024 135
194 - Plester Dinding 24 days 12/14/2023 1/16/2024 193SS+6 days
195 - Acian Dinding 24 days 12/22/2023 1/24/2024 194SS+6 days
196 - Pasangan HT (BARE) 18 days 1/1/2024 1/24/2024 195SS+6 days
197 Ceilling (BARE) 28 days 11/20/2023 12/27/2023
198 - Pasangan Rangka & Gypsum 18 days 11/20/2023 12/13/2023 140
199 - Compound & Cat 18 days 12/4/2023 12/27/2023 198SS+10 days
200 Top table 12 days 11/28/2023 12/13/2023
201 install top table 12 days 11/28/2023 12/13/2023 143
202 Coring Lantai 12 days 12/29/2023 1/15/2024 187
203 Electrical 18 days 1/2/2024 1/25/2024 145
204 Plumbing 18 days 1/2/2024 1/25/2024 146
205 Accessories 12 days 1/18/2024 2/2/2024 147
206 Staircase (BARE) 50 days 11/29/2023 2/6/2024
207 - Screed (BARE) 24 days 12/19/2023 1/19/2024 149
208 - install HT (BARE) 24 days 12/27/2023 1/29/2024 207SS+6 days
209 - Install Ralling (BARE) 24 days 1/4/2024 2/6/2024 208SS+6 days
210 - Finish cat (BARE) 18 days 1/12/2024 2/6/2024 209SS+6 days
211 Electrical 18 days 11/29/2023 12/22/2023 153
212 Accessories 12 days 12/7/2023 12/22/2023 154
213 Lantai atap & LMR (BL03 s.d BL09) 30 days 12/19/2023 1/29/2024
214 Wall finish 30 days 12/19/2023 1/29/2024
215 - Pasangan dinding 18 days 12/19/2023 1/11/2024 158
216 - Plester Dinding 18 days 12/27/2023 1/19/2024 215SS+6 days
217 - Acian Dinding 18 days 1/4/2024 1/29/2024 216SS+6 days
218 Waterproffing Bitumen + Screed 24 days 12/27/2023 1/29/2024
219 - Waterproofing Bitumen 18 days 12/27/2023 1/19/2024 216SS
220 - Tes Rendam Waterproofing Bitumen 12 days 1/4/2024 1/19/2024 219SS+6 days
221 - Screed 12 days 1/12/2024 1/29/2024 220SS+6 days

Task Inactive Milestone Start-only Path Predecessor Summary Task

Split Inactive Summary Finish-only Path Predecessor Normal Task

Project: Schedule Genova BL03-BL09 v1R2 L5 20231 Milestone Manual Task External Tasks Critical
Date: 10/19/2023 Summary Duration-only External Milestone Critical Split

Project Summary Manual Summary Rollup Deadline Progress

Inactive Task Manual Summary Path Predecessor Milestone Task Manual Progress

10/19/2023 5
PT. Acset Indonusa Tbk,
Project Asya Commercial Genova Phase 1
SCHEDULE ASYA GENOVA BL03 S.D BL09 v1.R2
ID Task Task Name Duration Start Finish Predecessors Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Mode Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
222 - Tes Rendam Screed 6 days 1/22/2024 1/29/2024 221SS+6 days
223 LIFT 85 days 10/26/2023 2/21/2024
224 Mechanical Installation 60 days 10/26/2023 1/17/2024 75
225 Machine Installation 60 days 11/23/2023 2/14/2024 224SS+20 days
226 Wiring Electrical 40 days 12/14/2023 2/7/2024 225SS+15 days
227 Testing & Commisioning (SLO) 30 days 1/11/2024 2/21/2024 226SS+20 days
228 Façade 85 days 10/2/2023 1/26/2024
229 Wall Finish (1st Floor s.d Roof) 44 days 10/2/2023 11/30/2023
230 - Install Schaffolding Akses 8 days 10/2/2023 10/11/2023 8SS+10 days
231 - Plesteran Dinding Façade 24 days 10/12/2023 11/14/2023 230SS+8 days
232 - Acian Dinding Façade 24 days 10/30/2023 11/30/2023 231SS+12 days
233 Install GRC 46 days 11/13/2023 1/15/2024
234 - Rangka GRC 36 days 11/13/2023 1/1/2024 232SS+10 days
235 - GRC & Sealent 36 days 11/27/2023 1/15/2024 234SS+10 days
236 Pengecatan Façade 34 days 12/5/2023 1/19/2024
237 - Cat Dasar 24 days 12/5/2023 1/5/2024 235SS+6 days
238 - Cat Texture 24 days 12/13/2023 1/15/2024 237SS+6 days
239 - Checklist Eksternal 14 days 1/2/2024 1/19/2024 238FS-10 days
240 - Checklist Estate 7 days 1/10/2024 1/18/2024 239SS+6 days
241 Dismantle Scaffolding Akses 6 days 1/19/2024 1/26/2024 240
242 Canopy Façade 109 days 10/2/2023 2/29/2024
243 Kanopi Selasar dan Kanopi Separator 109 days 10/2/2023 2/29/2024
244 - Install Baja Kanopi 24 days 10/2/2023 11/2/2023 230SS
245 - Instal ACP Kanopi 24 days 1/29/2024 2/29/2024 241
246 - Install MEP 18 days 2/6/2024 2/29/2024 245SS+6 days
247 - Tes Rendam dan Final Cheklist 6 days 2/22/2024 2/29/2024 246FS-6 days
248 Checklist Internal Unit (ACSET-Sub&Vendor) 30 days 12/25/2023 2/2/2024 14
249 Final Checklist Eksternal Unit (ACSET-AML) 30 days 1/3/2024 2/13/2024 248SS+7 days
250 Final Checklist Unit (AML-Estate) 30 days 1/12/2024 2/22/2024 249SS+7 days
251 BAST 1 (FHO-1) 30 days 1/23/2024 3/4/2024 250SS+7 days
252 Masa Pemeliharaan 180 days 3/5/2024 11/11/2024 251
253 BAST 2 (FHO-2) 30 days 10/1/2024 11/11/2024 252FS-30 days

Task Inactive Milestone Start-only Path Predecessor Summary Task

Split Inactive Summary Finish-only Path Predecessor Normal Task

Project: Schedule Genova BL03-BL09 v1R2 L5 20231 Milestone Manual Task External Tasks Critical
Date: 10/19/2023 Summary Duration-only External Milestone Critical Split

Project Summary Manual Summary Rollup Deadline Progress

Inactive Task Manual Summary Path Predecessor Milestone Task Manual Progress

10/19/2023 6