Goginauri HPP project

Name Assigned to Start Finish % Complete

1 GOGUNAURI HEPP PROJECT 4/21/2023 10/29/2023 0

2 POWER HOUSE 4/21/2023 9/5/2023 0

3 Eartworks 4/21/2023 6/18/2023 0

Mechanical Excavation for the foundation at


4 4/21/2023 4/22/2023 0
+700,77-698,30

5 -‐aveling the terrain around the poLer house 4/22/2023 4/23/2023 0

6 Gravel wacBfilling and compaction for arround Curten kall 5/17/2023 5/19/2023 0

StaWilibing filling around the poLer plant and concreting


7 6/18/2023 6/18/2023 0
the fieldz

8 Concrete and R.C Works 4/25/2023 6/17/2023 0

9 -‐ean Concrete for at +698,40 4/25/2023 4/30/2023 0

10 FormLorB and .,war korBs for Foundation on +698z80 4/30/2023 5/5/2023 0

11 .zC korBs for Foundation on +698,80 5/5/2023 5/9/2023 0

FormLorB and .zwar korBs for Curtain Lall from +698,80


12 5/9/2023 5/13/2023 0
to 702,70

13 .zC korBs for Curtain Lall on +698,80+701,05 5/13/2023 5/17/2023 0

14 FormLorB and .zwar korBs for SlaW on +701,05 5/19/2023 5/24/2023 0

15 -‐ean Concrete for on +700,77 5/24/2023 5/26/2023 0

FormLorB and .zwar LorBs for Continuous Foundation on-


16 5/26/2023 6/1/2023 0
+701,22
.zC korBs for Continuous Foundation and SlaW on .zC
17 6/1/2023 6/7/2023 0
+701,05

18 FormLorB and .zwar LorBs for Curtain Lall on +702,45 6/7/2023 6/12/2023 0

19 .zC korBs for Curtain kall and SlaW on +702,65 6/9/2023 6/17/2023 0

20 Steel Structure Works 6/7/2023 6/24/2023 0

Preparation and installation of the steel structure sRstem of


21 6/7/2023 6/16/2023 0
the poLerhousez

22 .oofing termo insulation of the poLerhouse 6/17/2023 6/24/2023 0

23 Masonary Works 6/22/2023 8/17/2023 0

24 Construction of exterior and interior Lalls 6/22/2023 7/5/2023 0

25 yoors and LindoLs supplR and installation 7/15/2023 7/28/2023 0

Exported from Microsoft Project on 4/17/2023 Page 1 of 6


Goginauri HPP project
Name Assigned to Start Finish % Complete

26 Exterior Lall thermal insulation 7/25/2023 8/4/2023 0

27 Exterior Lall cladding 8/8/2023 8/17/2023 0

28 Dnterior Lalls mortar 7/22/2023 8/2/2023 0

29 Tiles Works 8/11/2023 9/2/2023 0

30 Ceramic tiles 8/11/2023 8/25/2023 0

31 HeavR-dutR cementitious polRurethane screed 8/23/2023 9/2/2023 0

32 Paints Work 8/17/2023 8/24/2023 0

33 Dnterior Lalls paint 8/17/2023 8/24/2023 0

34 Suspending Ceiling 8/17/2023 9/1/2023 0

35 Inauf sRstem gRpsum Woard suspended ceiling 8/20/2023 8/31/2023 0

Communication, -‐ighting, SecuritR and Electrical SRstems


36 8/17/2023 8/22/2023 0
Dnstallation

37 Sheetmetal korBs 8/28/2023 9/1/2023 0

38 Carpenter korBs 8/20/2023 8/31/2023 0

39 Mechanical Equipment 6/25/2023 8/22/2023 0

40 KurWine assemWlR 7/5/2023 7/11/2023 0

41 Generator assemWlR 7/12/2023 7/18/2023 0

42 Cooling kater sRstem assemWlR 7/21/2023 7/27/2023 0

43 Crane assemlR 6/25/2023 7/4/2023 0

44 HTAC SRstem AsssemlR 8/18/2023 8/22/2023 0

45 Electrical Equipment 7/19/2023 9/5/2023 0

46 CaWle traR and support LorBs 8/17/2023 8/26/2023 0

47 CaWle korBs V Cuper, ethernet, fiWer optiB( 8/27/2023 9/5/2023 0

48 PoLer Kransformer assemWlR 7/19/2023 7/25/2023 0

49 SLitchgear Panels LorBs and assemlR 7/26/2023 7/31/2023 0

50 PoLer socBets LorBs 8/1/2023 8/6/2023 0

Exported from Microsoft Project on 4/17/2023 Page 2 of 6


Goginauri HPP project
Name Assigned to Start Finish % Complete

51 CCKT installation 8/7/2023 8/11/2023 0

52 Dndustrial ethernet sLitch and ports LorBs 8/7/2023 8/10/2023 0

53 Plumbing system 6/30/2023 8/8/2023 0

54 SeLage SRstem assemWlR 6/30/2023 7/6/2023 0

55 PP. Pipes korB 7/11/2023 7/17/2023 0

56 PlastiB Septic tanB assemlR 7/14/2023 7/17/2023 0

57 Koilet e(﴾uipments installation 8/1/2023 8/4/2023 0

58 Concrete menhols 8/5/2023 8/8/2023 0

59 Drainage system 8/11/2023 8/22/2023 0

60 PTC Pipes LorBs 8/11/2023 8/17/2023 0

61 HyPE or Concrete menhols 8/20/2023 8/22/2023 0

62 Water Supply Sistem 8/6/2023 9/3/2023 0

63 PP. Pipes LorBs and armature assemlR 8/6/2023 8/10/2023 0

64 PE Pipes LorBs 8/11/2023 8/17/2023 0

65 Talves assemlR 8/18/2023 8/19/2023 0

66 kater Lell driling 8/20/2023 9/3/2023 0

67 HRdro Clorine sRstem asemWlR 8/18/2023 8/19/2023 0

68 Pressure tanB asemWlR 8/20/2023 8/25/2023 0

69 Cleaning, testing and disinfection 8/22/2023 9/3/2023 0

70 Kesting 8/22/2023 8/27/2023 0

71 yisinfection 8/28/2023 8/29/2023 0

72 Cleaning 8/30/2023 9/3/2023 0

73 CURTAIN WALL FOR ROAD SAFETY 4/23/2023 5/25/2023 0

74 Excavation Works 4/23/2023 5/3/2023 0

75 Excavation of the slope staWilitR 4/23/2023 4/29/2023 0

Exported from Microsoft Project on 4/17/2023 Page 3 of 6


Goginauri HPP project
Name Assigned to Start Finish % Complete

76 Excavation of the foundation level 4/30/2023 5/3/2023 0

77 Concrete Works 5/4/2023 5/25/2023 0

78 -‐ean Concrete 5/4/2023 5/7/2023 0

79 FormLorBs 5/5/2023 5/22/2023 0

80 .C LorBs Lith C30/37 5/6/2023 5/25/2023 0

81 .War korBs 5/5/2023 5/16/2023 0

82 Backfilling works 5/9/2023 5/15/2023 0

83 Curtain kall WacB side filling Lith gravel material 5/9/2023 5/15/2023 0

Curtain kall WacB side filling Lith fine material from the
84 5/9/2023 5/15/2023 0
excavation

85 Other Works 5/5/2023 5/19/2023 0

86 )110mm PTC Pipe keep hole 5/5/2023 5/19/2023 0

87 )200 HyPE yren Pipe 5/6/2023 5/7/2023 0

88 PENSTOCK 4/21/2023 10/29/2023 0

89 Preperetion works 4/21/2023 7/4/2023 0

90 SurveR marBs, pipeline laRing etcz 4/21/2023 7/4/2023 0

91 Kreatment of terrain and clearing on trees 4/21/2023 6/19/2023 0

92 Ground Works 4/21/2023 7/11/2023 0

93 Preparation of operational Corridor 4/21/2023 6/29/2023 0

94 Excavation of Pipeline trench 4/21/2023 7/4/2023 0

95 Procurement ,transport and forming sand Wed for pipes 4/21/2023 6/29/2023 0

96 wacBfilling the trench Lith selected material 4/21/2023 7/9/2023 0

97 Maintenance of the landfill 6/7/2023 7/11/2023 0

98 Concrete Works 4/21/2023 7/13/2023 0

99 Ancor wlocBs LorBs 5/5/2023 6/3/2023 0

100 .iver Crossings LorBs 5/15/2023 7/13/2023 0

Exported from Microsoft Project on 4/17/2023 Page 4 of 6


Goginauri HPP project
Name Assigned to Start Finish % Complete

101 AssemWlR LorBs for spiral Lelded steel Pipes 4/21/2023 7/1/2023 0

102 Other Works 7/2/2023 7/19/2023 0

103 Pipeline Pressure and )﴿ltraviolet testing 7/2/2023 7/8/2023 0

104 Geodetic surveR of completed pipeline 7/10/2023 7/19/2023 0

105 WATER INTAKE ELECTRICAL EQUIPMENT 8/19/2023 10/8/2023 0

106 CaWle LorBs V Copper, optical caWle, etcz( 9/6/2023 9/24/2023 0

107 CaWle traR,steell, galvanibed cover etcz 8/19/2023 9/5/2023 0

108 Steel galvanibed pole for lighting, 10m and -‐uminaires 9/25/2023 10/4/2023 0

109 CCKT LorBs etcz 10/2/2023 10/8/2023 0

110 DAM STRUCTURE 7/20/2023 10/23/2023 0

111 Preparation Earthworks 7/20/2023 8/30/2023 0

112 Kreatment of Kerrain and cutting and clearing trees 7/20/2023 8/18/2023 0

113 Excavation on foundation 8/11/2023 8/30/2023 0

.ehaWilitation of the damaged section of the access road


114 7/20/2023 8/8/2023 0
after construction

115 Concrete Works of Dam Structure 7/25/2023 10/17/2023 0

-‐ean Concretes 20 cm for under the yam ,Settling wasin


116 7/25/2023 8/8/2023 0
slaW, and fish pass
Concreting of the lean concrete 20-220 cm thicB under
117 8/2/2023 8/21/2023 0
the Settling Wasin foundation slaW

118 Concretting yam Lith concrete C30/37 8/26/2023 9/9/2023 0

119 Concreting Settling Wasin Lith concrete C30/37 8/26/2023 9/14/2023 0

Concreting foundation SlaW 2,0m of thicB of the Settling


120 9/8/2023 9/22/2023 0
Wasin Lith concrete C30/37
Concreting Foundation SlaW 0,5-5,0m thicB of the gate
121 9/19/2023 9/23/2023 0
Lith concrete C30/37
Concreting Lalls 0,5m thicB of the settling Wasin Lith
122 9/8/2023 9/19/2023 0
concrete C30/37
Concreting Lalls 0,6m thicB of the setling Wasin Lith
123 9/25/2023 10/1/2023 0
concrete C30/37
Concreting Lalls 0,3m thicB of the settling Wasin Lith
124 9/11/2023 9/21/2023 0
concrete C30/37
Concreting Lalls 0,8m thicB of the settling Wasin Lith
125 9/16/2023 9/26/2023 0
concrete C30/37

Exported from Microsoft Project on 4/17/2023 Page 5 of 6


Goginauri HPP project
Name Assigned to Start Finish % Complete

Concreting Lalls 0,5 - 2,19m thicB of the settling Wasin


126 9/23/2023 10/3/2023 0
Lith concrete C30/37
Concreting roof slaW 0,3m thicB of the settling Wasin Lith
127 10/4/2023 10/17/2023 0
concrete C30/37
Concreting sroof slaW 0,5m thicB of settling Wasin Lith
128 9/27/2023 10/4/2023 0
concrete C30/37
Concreting concrete slope at the Wottom of the settling
129 9/17/2023 9/26/2023 0
Wasin Lith concrete C30/37
Concreting Lalls 0,3m thicB of the fish path Lith conrete
130 9/15/2023 9/21/2023 0
C30/37
Concreting oWstacles of the fish path Lith concrete
131 9/20/2023 10/1/2023 0
C30/37

132 RC works of DAM Structure 9/15/2023 10/19/2023 0

Preparation, transportation and installation .C grade


133 9/15/2023 10/19/2023 0
EN10080 for dam
Hydromechanical and Mechanical equipment of DAM
134 10/4/2023 10/22/2023 0
Structure

135 -‐ine of settling tanB and intaBe chamWer 10/5/2023 10/14/2023 0

136 Krasch .acB and wulBhead Gates 10/4/2023 10/17/2023 0

137 -‐evel meter 10/18/2023 10/22/2023 0

138 Tarious metal LorBs 10/20/2023 10/22/2023 0

139 Line of bottom outlet 10/19/2023 10/23/2023 0

140 wulBhead gate 10/19/2023 10/23/2023 0

141 TESTING AND FIXING 10/20/2023 10/29/2023 0

142 HRdraulic and pressure testing 10/20/2023 10/29/2023 0

Exported from Microsoft Project on 4/17/2023 Page 6 of 6