GPT INFRAPROJECTS LIMITED

Tentitive Work Program for the month of MAY-2023


Name of Work: CONSTRUCTION OF CABLE STAYED ROAD OVER BRIDGE(ROB) AT EXISTING ROB LOCATION BETWEEN EP/19/156 AN
STATION IN MUMBAI DIVISION OF CENTRAL RAILWAY

PHASE II

Concrete
Date of casting Structure Amount (L) Actual Amount (L)
Volume

5/3/2023 Pile P29/01 23 8.2 8.22874


5/3/2023 Pile P29/08 23 8.2 8.22874
5/5/2023 Pile P30/01 23.25 8.2 8.08
5/8/2023 Pile P30/08 23.25 8.2 8.08
5/10/2023 Pile P30/02 23.25 8.2 8.08
5/12/2023 Pile P30/07 23.25 8.2 8.08
5/15/2023 Pile P30/03 23.25 8.2 8.08
5/17/2023 Pile P30/06 23.25 8.2 8.08
5/19/2023 Pile P30/05 23.25 8.2 8.08
5/22/2023 Pile P30/04 23.25 8.2 8.08
5/24/2023 Pile LA2/01 23.25 8.2
5/26/2023 Pile LA2/04 23.25 8.2
5/29/2023 Pile LA2/03 23.25 8.2
5/31/2023 Pile LA2/02 23.25 8.2
5/24/2023 Pile P28/03 17 6.51 6.51
5/26/2023 Pile P28/06 17 6.51
5/29/2023 Pile P28/04 17 6.51 6.5
5/31/2023 Pile P28/05 17 6.51 6.5
5/23/2023 Excavation P30 1 0.63
5/24/2023 PCC P30 7 0.437
5/26/2023 Pile Cap P30 163 32.65
UNPLANNED LOCATION Pile P27/04 15 6 6
UNPLANNED LOCATION Pile P27/05 15 6 6
TOTAL 187 113
CTS LIMITED
the month of MAY-2023
OB LOCATION BETWEEN EP/19/156 AND EP/20/1, BETWEEN GHATKOPAR AND VIKHROLI
N OF CENTRAL RAILWAY

Actual
Planned Achieved Remarks
Completion Date

5/3/2023 4% 4%
RIG 1
5/4/2023 4% 4%
5/10/2023 4% 5%
5/8/2023 4% 4%
5/8/2023 4% 4%
5/11/2023 4% 5% RIG 1
5/12/2023 4% 5%
5/15/2023 4% 5%
5/18/2023 4% 5%
5/16/2023 4% 5%
4%
4%
RIG 1
4%
4%
5/22/2023 3% 3%
3%
RIG 2
5/15/2023 3% 4%
5/19/2023 3% 4%
0.3% -
0.2% -
18% -
5/20/2023 3% 3% UNPLANNED LOCATION
5/22/2023 3% 3% UNPLANNED LOCATION
114 100% 65%