You are on page 1of 3

BDI DAILY WORK ASSESMENT

PROJECT : AL-WATHBA ZONE : 2

REPORT till 13: Total joints;2198 Total Excavation 364


SI NO DATE NO OF JOINTS EXCAVATION (mm) BACKFILLING (mm) No of pipe off loaded
1 13/04/2023 7 96mm 96mm
2 14/02/2023 off off 0ff
3 15/04/2023 4 84mm 84mm
4 16/04/2023 4 108mm 108mm
5 17/04/2023 7 0 0
6 18/04/2023 5 75mm 72mm
8 19/04/2023 5 72mm 72mm
9 20/04/2023 6 96mm 96mm
10 4/21/2023 off off off
11 4/22/2023 off off off
12 4/23/2023 off off off
14 4/24/2023 10 216mm 216mm
15 4/25/2023 10 264mm 264mm
16 4/26/2023 9 180mm 180mm
17 4/27/2023 11 132mm 132mm
18 4/28/2023 off off off
19 4/29/2023 12 252mm 252mm
20 4/30/2023 9 168mm 168mm

TOTAL complete 2128mm 2128 375

.
BDI MONTHLY WORK ASSESSMENT
project: AL Wathba
Month : MAY 2023

SI NO DATE No of JOINTS EXCAVATION BACKFILLING PIPE OFFLOADING Trial pitting


1 5/1/2023
2 5/2/2023
3 5/3/2023
5/4/2023
5/5/2023
5/6/2023
5/7/2023
5/8/2023
5/9/2023
5/10/2023
5/11/2023
5/12/2023
5/13/2023
5/14/2023
5/15/2023
5/16/2023
5/17/2023
5/18/2023
5/19/2023
5/20/2023
5/21/2023

You might also like