CONSTRUCTION PROJECT TIMELINE

PROJECT TITLE START

DHABEJI GRID TO PLDP 220KV 2500 SQMM


03/07 PROJECT
CABLE LAYING WITHOUT TERMINATION
DURATION
PROJECT MANAGER END in days

27/08/202
FARHAN NADEEM 54
3

START END DURATION


TASK NAME COMMENTS
DATE DATE in days

Trial Pit 03/07 05/07 3


22/07/202 Excavation will start after 75% completion
Excavation 06/07
3
18
of horizontal boring.
13/07/202 Includes Office container, Rest area for
Site management 08/07
3
6
Labour and Drivers, Utilities etc
20/07/202 20/07/202 1st sheath test will be done on next day of
Transportation of Cable Drums 3 3
1
drum openings.
23/07/202 25/07/202
1st Layer of Sand bedding 3 3
3
26/07/202 14/08/202 This activity includes laying of 12 Power
Cable laying 3 3
20
cables, FOC, DTS.
15/08/202 2nd sheath test will take place in between
2nd Layer of Sand bedding 3
17/8/2023 3
this activity.
18/08/202 20/08/202
Concrete Slabs 3 3
3
21/08/202 24/08/202 Laying of Warning tape will take place in
Back Filling 3 3
4
between this activity.
25/08/202 26/08/202
Compaction 3 3
2
27/08/202 27/08/202
Final sheath Test 3 3
1
CONSTRUCTION PROJECT TIMELINE TEMPLATE
PROJECT TITLE START

PROJECT
DURATION
PROJECT MANAGER END in days

START END DURATION


TASK NAME STATUS ASSIGNED TO COMMENTS
DATE DATE in days

Planning

Demo Prep

Demolition

Excavation

Concrete

Pre backfill

Framing

Roof

Plumbing

Windows

HVAC

Electrical

A/V

House wrap

Insulation

Drywall
Exterior stone

Exterior case work

Laundry/furnace room flooring

Hardwoods

Tile

Cabinets

Plumbing -hang sinks

Interior doors

Millwork

Interior painting

Stone Counters

Schedule Buffer

Decks

Interior doors- hang & hardware

Appliances

Plumbing

Electrical

Bathroom Glass

Garage Door dress up

FINAL Inspections

Wrap up

House Cleaning

Complete
09/20 10/20 11/19 12/19 01/18 02/17 03/19 04/18 05/18 06/17

Planning
Demo Prep
Demolition
Excavation
Concrete
Pre backfill
Framing
Roof
Plumbing
Windows
HVAC
Electrical
A/V
House wrap
Insulation
Drywall
Exterior stone
Exterior case work
Laundry/furnace ro
Hardwoods
Tile
Cabinets
Plumbing -hang si
Interior doors
Millwork
Interior painting
Stone Counters
Schedule Buffer
Decks
Interior doors- han
Appliances
Plumbing
Electrical
Bathroom Glass
Garage Door dress
FINAL Inspections
Exterior case work
Laundry/furnace ro
Hardwoods
Tile
Cabinets
Plumbing -hang si
Interior doors
Millwork
Interior painting
Stone Counters
Schedule Buffer
Decks
Interior doors- han
Appliances
Plumbing
Electrical
Bathroom Glass
Garage Door dress
FINAL Inspections
Wrap up
House Cleaning
Complete
Any articles, templates, or information provided by Smartsheet on the website are for reference
only. While we strive to keep the information up to date and correct, we make no representations
or warranties of any kind, express or implied, about the completeness, accuracy, reliability,
suitability, or availability with respect to the website or the information, articles, templates, or
related graphics contained on the website. Any reliance you place on such information is
therefore strictly at your own risk.

You might also like