This project planner document tracks the progress of 13 project activities over 60 periods. It shows the planned start and duration for each activity, as well as the actual start, duration, and percentage complete. The commencement of the project is 25% complete in period 1. The first project meeting and design concept being approved are both fully completed according to plan. The website design is currently only 50% complete and running past its planned end date.
This project planner document tracks the progress of 13 project activities over 60 periods. It shows the planned start and duration for each activity, as well as the actual start, duration, and percentage complete. The commencement of the project is 25% complete in period 1. The first project meeting and design concept being approved are both fully completed according to plan. The website design is currently only 50% complete and running past its planned end date.
This project planner document tracks the progress of 13 project activities over 60 periods. It shows the planned start and duration for each activity, as well as the actual start, duration, and percentage complete. The commencement of the project is 25% complete in period 1. The first project meeting and design concept being approved are both fully completed according to plan. The website design is currently only 50% complete and running past its planned end date.
Select a period to highlight at right. A legend describing the charting follows. Period Highlight: 1 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)