You are on page 1of 1

2.

8 Work Program for Incoming Period


For the incoming period we are expecting to continue and finish with the following works

1. Ground improvement and backfill and laying of geogrid


Ground improvement and backfill and laying of geogrid we are expecting for block A to be completed at 15th
of June 2022.

For block B&C we are expecting to complete the above-mentioned works at 25th of June 2022.

2. Cast in situ of lean concrete below foundations& Geotextile fell


Right after completing the works with ground improvement works will continue with pouring of lean
concrete. The priority it’s the block A which we expect to pour the concrete on 18th of June 2022

Figure 21 Lean Concrete on lift shafts, 30th of May Figure 22 Cubic samples taken on site, 30th of May
For block C we expect the pouring of concrete to be executed on 27th of June 2022.

Block B will be left for the time being since we want to use that space as working area until the basement of
block A is completed.

One day before pouring of concrete of above mentioned blocks the geotextile fell will be laid one day
before the pouring of concrete

3. Installation of bituminous waterproofing 3+4mm


The waterproofing insulation for Block A it’s expected to be completed on 17 th of June and for block C that
work is scheduled to start on 29th of June and be completed by 2nd of July

4. Structural Works – Strip raft foundations


On 1st of June, we will start with execution of strip and raft foundation of block E (Sporting Hall) and
archiving the completion of the foundations by the end of the month.

For block A (Basement) we are still waiting for the new foundation design.

5. Earth works – Laying of gravel under slab on grade it’s expected to start on 20 th of June and to be
completed in the first week of next month.
Archived Progress
MarchAch Total Ach Scheduled
POS Description of works
Progress Progress Progress
A) General Items 93.83 % 93.83 % 80.00 %
B) Earth Works 2.96 % 14.96 % 15.00 %
C) Structural Works 0.39 % 0.39% 0.30 %
D) Civil and Architectural Works 0.74 % 0.74 % 0.50 %
E) Water and Sanitation Works 0.00 % 0.00 % 0.00 %
F) Electrical Installations 0.00 % 0.00 % 0.00 %
G) Mechanical Installations 0.00 % 0.00 % 0.00 %
H) Outside Works and Landscape Works 0.00 % 0.00 % 0.00 %
I) Infrastructural Works 0.00 % 0.00 % 0.00 %
J) Geotechnical Works 42.80 % 42.80 % 30.00 %
2.04 % 5.47 % 5.00 %

You might also like