For block B&C we are expecting to complete the above-mentioned works at 25th of June 2022.
Figure 21 Lean Concrete on lift shafts, 30th of May Figure 22 Cubic samples taken on site, 30th of May
For block C we expect the pouring of concrete to be executed on 27th of June 2022.
Block B will be left for the time being since we want to use that space as working area until the basement of
block A is completed.
One day before pouring of concrete of above mentioned blocks the geotextile fell will be laid one day
before the pouring of concrete
For block A (Basement) we are still waiting for the new foundation design.
5. Earth works – Laying of gravel under slab on grade it’s expected to start on 20 th of June and to be
completed in the first week of next month.
Archived Progress
MarchAch Total Ach Scheduled
POS Description of works
Progress Progress Progress
A) General Items 93.83 % 93.83 % 80.00 %
B) Earth Works 2.96 % 14.96 % 15.00 %
C) Structural Works 0.39 % 0.39% 0.30 %
D) Civil and Architectural Works 0.74 % 0.74 % 0.50 %
E) Water and Sanitation Works 0.00 % 0.00 % 0.00 %
F) Electrical Installations 0.00 % 0.00 % 0.00 %
G) Mechanical Installations 0.00 % 0.00 % 0.00 %
H) Outside Works and Landscape Works 0.00 % 0.00 % 0.00 %
I) Infrastructural Works 0.00 % 0.00 % 0.00 %
J) Geotechnical Works 42.80 % 42.80 % 30.00 %
2.04 % 5.47 % 5.00 %