Professional Documents
Culture Documents
REVIEW OF FINANCIAL
PROGRESS OF PROJECTS
REVIEW OF FINANCIAL PROGRESS OF PROJECTS
The summary of the financial progress (with GST) in quarter-8 (April to June,
2020) and upto quarter-8 (July 2018 to June, 2020) of Integrated Unit (IU) and
Captive Power Plant (CPP-II) projects as well as for the entire project is given
below:
73807.6
Integrated Unit (IU) 0.00 0.00 0% 83046.11 89%
9
Captive Power 22306.1
0.00 0.00 0% 22726.90 98%
Plant (CPP) 5
@ Grinding Unit
0.00 0.00 0.00 0.00 0.00 0.00
(GU) at Surat
96113.8
Total 0.00 0.00 0% 105773.01 91%
4
NOTES:
1) *Actual upto quarter-8 also includes payments made during quarter-8 out of unutilized budget of
quarter 1, quarter-2, quarter-3, quarter-4 and quarter-5 and Rs. 11.16 Cr. paid by SIL prior to 1 st
disbursement out of their own sources.
2) @ As M/s. L & T have filed a petition before NGT against the Pollution Clearance granted by
Government of Gujarat to SIL for putting up a Greenfield Cement Grinding Unit (GU) at Surat
and as decided by the consortium, the physical and financial progress of Cement Grinding Unit
(GU) at Surat has not been considered here and deferred for the time being.
The summarized financial progress (without GST) upto quarter-8 (July 2018 to
June, 2020) of Integrated Unit (IU) and Captive Power Plant (CPP) projects as
well as for the entire project as percentage of total Revised Project Cost as on
30.06.2020 is given below:
SIL has submitted the revised project cost of Integrated Unit (IU) and CPP-II as
on 30.06.2020. It is observed that during quarter-8 (April to June, 2020), the
total project cost overrun (net of repeated orders) has increased by Rs. 5.51
crore i.e. cost overrun increased from Rs. 8.12 crore as on 31.03.2020 to Rs.
13.63 crore as on 30.06.2020.
#The original project cost of Integrated Unit (IU) and CPP-II projects approved by the
Lenders in June, 2018 was Rs. 103994.96 lac. After deducting the cost of 2 rotary
packers amounting to Rs. 1480.42 lac and one surface miner amounting to Rs. 631.80
lac which was not considered by SIL in the revised project cost as on 30.06.2020, the
net adjusted project cost approved by the Lenders in June, 2018 has been arrived to
Rs. 101882.74 lac.
On the basis of revised project cost of Rs. 1032.46 crore (without GST) of IU
and CPP-II projects as on 30.06.2020 as given above and actual expenses of
Rs. 842.26 crore paid upto 30.06.2020, the balance funds required to complete
the expansion projects is worked out to about Rs. 190.20 crore (without GST)
as follows:
1) The financial progresses of IU and CPP-II projects was good upto quarter-4
(April to June 2019) and thereafter it was slowed down which is evident
from the fact that the financial budget given by SIL for quarter-5 (July to
September 2019) has not been fully utilised till the end of quarter-8 i.e.
SANGHI INDUSTRIES LTD. [Pg. 8] ERCOM ENGINEERS PVT. LTD.
REVIEW OF FINANCIAL PROGRESS OF PROJECTS
30.06.2020. Even SIL has not requested for any fresh budget for quarter-9
(July to September 2020) and informed that the unutilised budget of
quarter-5 is sufficient to take care of funds requirement. Though the
physical progress of the projects upto 30.06.2020 as informed by SIL is
about 98% but the financial progress is only 82%.
5) Due to Covid-19 pandemic and as per the guidelines of RBI, the Lenders in
the last consortium meeting held on 19.08.2020 have decided to convert
the interest payable on term loans from 01.03.2020 to 31.08.2020 into
Funded Interest Term Loan (FITL). Therefore, the interest payable from
01.03.2020 to 30.06.2020 has been accrued but not paid to the Lenders
during quarter-8 (April to June, 2020). The crystallised amount of interest
payable on term loans from 01.03.2020 to 31.08.2020 which is converted
into Funded Interest Term Loan (FITL) will be informed in the next report
i.e. report for quarter-9 (July to September, 2020).
###############