You are on page 1of 145

JINKA TOWN ROAD PROJECT Ethiopian Roads Authority

Alternative 2

GRAND SUMMARY
Contract Name: Construction of JINKA TOWN ROAD PROJECT
Alternative 2

DIVISION Description DIVISION TOTAL AMOUNT ETB


1000 General 673,147.70
2000 Site Clearance 549,527.44
3000 Drainage 40,284,928.74
4000 Earthworks and Material Stabilization 19,618,815.63
5000 Subase, Road base and Gravel Wearing Course 10,575,064.16
6000 Surface Treatments and Bituminous Surfacings 20,559,471.49
7000 Rigid Pavement Not Applicable
8000 Structures 25,567,535.26
9000 Ancillary Works 439,634.82

(A) Total of Series 118,268,125.24


(B) Specified provisional sums included within the Series -
(C) Total of Series less Specified Provisional Sums (A-B) 118,268,125.24
(D) Estimated detailed Engineering Design cost (5% of A) 5,913,406.26
(E) Total of Series + Design Cost = (A+D) 124,181,531.51
(F) Add Value Added Tax (VAT) (15% of E) 18,627,229.73
(G) Grand Total (E+F) 142,808,761.23

Stadia Engineering Works Consultant Plc Page 1 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity Rate Amount
DIVISION 1000 GENERAL
1400 ACCOMMODATION, SERVICES, AND ATTENDANCE FOR THE
ENGINEER'S STAFF
Office Building Complete as specified including furniture.(Tables
14.01 L. Sum -
1409/1 and 1409/5)
Laboratory Building Complete as specified including furniture. (Tables
14.02 L. Sum -
1409/4 and 1409/6)
14.03 Items measured and paid for by the Lump sum
a Office Equipment as specified as per Table 1409/2 L. Sum -
b Laboratory Equipment as specifies as required and specified in Tables L. Sum -
1409/3 (a), (b), (c) and/or (d)
14.04 Services
a Fixed Costs L. Sum -
b Maintenance and Services for offices and laboratories. Month -
14.05 Vehicles for Engineer and his staff
b Vehicle Type B No. -
14.06 Provision of fuel and lubricants and the servicing, maintenance, and
repair of vehicles for the Engineer and his staff
b Fuel, service and maintain vehicle , Type B Veh-mth -
e Fuel, service and maintain vehicle in excess of 3,000 km for any vehicle in km -
any one Calendar month, vehicle Type B
14.07 Attendance upon the Engineer and his staff
a Driver for the Engineer's vehicles Man-mth -
b Chainman and Laborers Man-mth -
c Laboratory Assistants Man-mth -
d Cleaners Man-mth -
e Watchman/Security Man-mth -
14.08 Additional Offices and laboratory equipment ordered by the Engineer

a Prov. Sum -
Additional equipment ordered by the Engineer
Laboratory testing to be carried out in external laboratories as instructed by
b Prov. Sum -
the Engineer
c Percentage allowed for overhead and profit on items 14.08 (a) and (b) % -
Building, House Type, complete, as specified, including fixtures
14.09 furniture and
equipment (Tables 1409/7 and 1409/8)
a Type A housing No. -
b Type B housing No. -
c Type C housing (Blocks) No. -
d Type D housing No. -
14.10 Items measured by number
a Air conditioning units No. -
14.11 Temporary facilities of the Engineer
a Office fully fitted, furnished and equipped including all services Month -
b Laboratory fully fitted, furnished and equipped including all services Month -
c Housing Accommodation fully fitted, furnished and equipped including all
services
i Type A houses Month -
ii Type B houses Month -
d Vehicles including all operating costs
ii Type B Month -
e Survey Equipment Month -
14.12 Communication Equipment for the Engineer
b SIM card for mobile phone (work-related usage) No. -
c Airtime for work-related SIM card Month -
1500 TRAFFIC MANAGEMENT
15.01 Temporary Diversions
a Construction of diversions km -
b Maintenance of Diversion km 0.70 172,087.46 120,461.22
c Reinstatement of Diversion km -
d Traffic Management – full width km -
e Traffic Management – half-width km -
1600 Social, Health, Safety and Environmental Protection and Mitigation
Measures
16.01 Preparation of Management Plans
a Site Environmental and Social Management Plan (SESMP) L. Sum -
b Health and Safety Management Plan (HSMP) L. Sum -
Provision of Occupational Health and Safety Equipment with Worker
16.02 L. Sum -
Training
Provision of a suitably equipped and staffed Clinic in the main
16.03 construction camp; and the provision of first aid equipment, kits and L. Sum -
medical supplies, sick bay and a suitable ambulance service at all
camps on the site
16.04 Watering of the road under construction, temporary diversions, and Km 4.00 138,171.62 552,686.48
access and haul roads at settlement areas
16.05 STD and HIV/AIDS Prevention and Control Programme
Conducting Knowledge, Attitude and Practice (KAP) surveys, preparation of
action plans on STD and HIV/AIDS alleviation measures, provision of
a information and educational materials, counselling and testing services and Prov. Sum -
establishment and training of peer educators and Anti-AIDS Committees

b Percentage allowed for overhead and profit on item 16.05 (a) % -

Stadia Engineering Works Consultant Plc Page 2 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity Rate Amount
16.06 Liaison with Communities and Local Authorities
Establishment and management of a Project Liaison Committee (PLC)
a including the organization of public meetings and project related notices to Prov. Sum -
the Community
b Percentage allowed for overhead and profit on item 16.06 (a) % -
16.07 Complimentary Interventions
a Provision for the inclusion of complimentary interventions to the contract as Prov. Sum -
agreed and directed by the Client
b Percentage allowed for overhead and profit on item 16.07 (a) % -
1000 General -TOTAL (Carried forward to Summary) 673,147.70

DIVISION 2000 SITE CLEARANCE


2100 Clearing and Grubbing
21.01 Clearing and Grubbing ha 11.74 46,816.85 549,527.44
21.04 Removal and storage of selected vegetation
a Cost of removal, storage, protection and replanting in a protected and Prov. Sum
fenced-off area of selected vegetation
b Charge on provisional sum of item 21.04(a) %
Demolition, Removal, Disposal or storage of Existing structures and
2200
installations
22.06 Removal of existing concrete and masonry structures
a Plain concrete m3
b Reinforced concrete m3
c Masonry Structures - mortared m3
d Masonry Structures - dry m3
2000 SITE CLEARANCE -TOTAL (Carried forward to Summary) 549,527.44

DIVISION 3000 DRAINAGE


3100
OPEN DRAINS, CASCADES, BANKS, DYKES AND SUB-SOIL DRAINS
31.01 Excavation for Open Drains
a Excavating soft material, irrespective of depth m3 27,916.60 90.04 2,513,555.06
b Excavating Hard material to any depth m3 291.91 200.82 58,621.52
31.05 Banks and dykes m3 -
3200 Culverts and Appurtenant Structures
32.01 Excavation
a Excavating soft material, irrespective of depth m3 1,985.69 105.01 208,522.76
b Excavation in hard material irrespective of depth m3 39.71 223.14 8,860.79
32.02 Backfilling
a Using the excavated material m3 420.40 58.06 24,408.37
b Using Imported selected material m3 1,373.72 138.98 190,919.77
32.03 Concrete pipe culverts
a On class A Bedding
i 36'' diameter R.C pipe m
ii 42'' diameter R.C pipe m
iii 48'' diameter R.C pipe m
b On class B Bedding
i 36'' diameter R.C pipe m
ii 42'' diameter R.C pipe m
iii 48'' diameter R.C pipe m 201.00 3,754.49 754,653.22
32.07 Cast in situ Concrete and Form work (C-30)
a Grade C-30 concrete for culverts(box/sand), inlet and outlet structures and s m3 274.11 5,064.46 1,388,231.98
32.1 Steel reinforcement
b High tensile steel reinforcement for culverts t 27.94 33,583.39 938,462.21
32.12 Removing existing Structures
c Removing existing class 'B' stone masonry m3 25.00 181.92 4,548.00
32.14 Removing and stocking existing prefabricated culverts
b Removing and stocking existing corrugated iron sheet pipe of size 1450mm m 26.00 678.91 17,651.67
32.16 Service Ducts
a Ordinary pipes (150mm diameter steel pipes) m 425.00 288.04 122,416.57
b Split pipes (150mm diameter steel pipes) m
32.17 Duct marker blocks (Precast RC Blocks)  No. 34.00 711.70 24,197.87
32.18 Chambers for ducts No.
3300 Kerbing, Channeling, Open Chutes, Downpipes, and Lining of Open
Drains
33.01 Kerbing
a Concrete kerbing (precast or in-situ concrete)
i Class 25/20 Concrete Curbing (size .45m X .17m) m 13,018.40 400.14 5,209,197.14
ii Class 25/20 Concrete Curbing (size .20m X .25m) m 6,830.00 251.09 1,714,966.51
33.03 Chutes
Concrete Chute (Class 20/20 precast concrete trapezoidal paved
a m
waterway) including Formwork
b Masonry Stone Chute (Rectangular) m 2,623.38
33.09 Concrete lining for open drains
Cast in-situ concrete lining (Class 20/20 concrete for Rectangular open
a m3
drain) including Formwork (with U2 surface finish)

Stadia Engineering Works Consultant Plc Page 3 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity Rate Amount
33.17 Paved Drains in Urban Areas and Reinforced Drain Covers
a U-shaped drains in urban areas (as per Drawings)
Stone Masonry (Class B U-shaped Masonry – Internal size 1m depth by
i m3 1,608.20
0.8m width)
b Reinforced Concrete Drain Covers (as per Drawings)
Pedestrian crossing covers (Class 25/20 RC Concrete – size
i No. 5,940.00 998.70 5,932,286.36
1.6mX1.0mX0.15m)
Vehicle crossing covers (Class 25/20 RC Concrete – size
ii No.
1.6mX0.5mX0.20m)
Vehicle crossing covers (Class 25/20 RC Concrete – size
iii No. 660.00 1,666.95 1,100,188.58
1.6mX1.0mX0.20m)
3400 Stone Pitching, Masonry, Precast Concrete Block and Riprap
34.01 Stone Pitching
b Grouted pitching
i For outlet & inlet of culverts m2 343.07 248.45 85,235.47
ii For Road side drains m2 - 248.45
iii For Ditch on benches and paved furrow ditch m2 285.71
34.02 Riprap
a Packed riprap (Class 3) m3 108.10 360.00 38,916.00
b Dumped riprap (Class 3) m3 1,679.00 360.00 604,440.00
34.03 Stone Masonry Walls
b Cement-mortared stone walls m3 9,433.42 1,608.20 15,170,836.39
34.04 Concrete Pitching
Pre-cast concrete blocks for side walk pavement (300x300x60mm Pre-
c m2 7,066.98 590.61 4,173,812.51
colored concrete block on sand base including any jointing work)
3000 DRAINAGE -TOTAL (Carried forward to Summary) 40,284,928.74

DIVISION 4000 EARTHWORKS AND MATERIAL STABILIZATION


4100 Preparation of Roadbed
41.01 Preparation of Road bed and protection of earth works
b Removal of unsuitable material m3 74,506.24 79.80 5,945,531.88
41.02 Road bed preparation and compaction m3 17,882.69 55.76 997,122.86
41.04 Investigation at deep cuts sections
a Prov. Sum
Fixed cost
b Percentage allowed for overhead and profit on item 41.04(a) %
4200 Roadway and Borrow Excavation
42.01 Cut and borrow to fill
a Cut to fill/embankment compaction to minimum of 95% of Modified 48,499.70 129.45 6,278,498.27
m3
AASHTO density,T-180
b Borrow to fill/embankment,compaction to minimum of 95% AASHTO T-180 m3 100.00 164.44 16,444.19
c Rock fill (as specified in sub-clause 4404) m3 4,828.32 294.17 1,420,335.53
Improved subgrade compacted to 95% of modified AASHTO density (a
d compacted thickness not exceeding 200 mm and not less than m3 7,915.50 176.32 1,395,655.73
100mm)
42.03 Cut to spoil
a Common (normal) excavation to spoil m3 44,083.68 80.87 3,565,227.18
b Hard rock Excavation m3 44,083.68 211.13
43.01 Reinstatement of borrow areas
a Rock (hard) material ha
b Common (normal or soft) material ha
44.04 Side fills or Fill-flattening m3
4000 EARTHWORKS AND MATERIAL STABILIZATION- TOTAL 19,618,815.63
(Carried forward to Summary)

DIVISION 5000 SUBBASE, ROAD BASE AND GRAVEL WEARING


COURSE
5100 Sub-Bases
51.01 Sub-base layer constructed from gravel or crushed stone
a Gravel sub-base (unstabilised gravel) compacted to
95% of modified AASHTO density (a compacted thickness not
i m3 15,189.00 262.35 3,984,813.68
exceeding 200 mm and not less than 100mm)
5200 Road Bases (excluding bituminous bases)
52.01 Base layer construction
c Crushed-stone base compacted to:
ii 100% of modified AASHTO density (a compacted thickness not m3 10,092.00 653.02 6,590,250.47
exceeding 200 mm and not less than 100mm)
5000 SUBBASE, ROAD BASE AND GRAVEL WEARING COURSE 10,575,064.16
-TOTAL (Carried forward to Summary)

DIVISION 6000 SURFACE TREATMENTS AND BITUMINOUS


SURFACINGS
6100 BITUMINOUS PRIME COAT
61.01 Prime coat
a MC-30 cutback bitumen l 52,770.00 40.04 2,113,004.70
6200 Tack Coat
62.01 Tack coat
a Stable-grade bitumen emulsion (30%) l
6300 SURFACE SEALS
63.02 Double surface seal using
b 20 mm and 10 mm aggregate(150/200 penetration grade bitumen) m2
63.07 Variations in the rate of application of bituminous binder

Stadia Engineering Works Consultant Plc Page 4 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity Rate Amount
g 150/200 penetration grade bitumen l 25.52

Stadia Engineering Works Consultant Plc Page 5 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity Rate Amount
63.08 Variation in the rate of application of chippings
b 20 mm chippings m3 477.79
d 10 mm chippings m3 477.79
6400 Asphalt Road Base and Surfacing's
64.02 Asphaltic surfacing
a 50mm Asphaltic surfacing with penetration grade 85/100 bitumen m2 52,770.00 349.56 18,446,466.79
64.05 Binder variations of 50/70 penetration grade bitumen t 25,778.25
6000 SURFACE TREATMENTS AND BITUMINOUS SURFACINGS - 20,559,471.49
TOTAL (Carried forward to summary)

DIVISION 8000 STRUCTURES


8100 Foundations for Structures
81.01 Additional foundation investigations
a Prov. Sum
Fixed cost
b Percentage allowed for overhead and profit on item 81.01(a) %
81.02 Excavation of materials
a Excavating soft material, irrespective of depth m3 8,186.36 110.11 901,387.68
b Excavation of hard materials irrespective of depth m3 1,521.97 240.74 366,392.51
81.05 Backfill to excavations utilizing :
a Material from the excavation m3 -
b Imported material m3 3,642.52 245.87 895,577.33
c Hand laid rock embankment m3
81.08 Foundation fill
a Rock fill m3
c Compacted granular fill m3
8200 Falsework, Formwork, and Concrete Finishes
82.01 Formwork
a  Formwork for Class F1 surface finish m2
b  Formwork for Class F2 surface finish m2 1,840.00 851.08 1,565,982.51
8300 Steel Reinforcement for Structures
83.01 Steel reinforcement for structure
a Steel bars
i Grade 60 Reinforcement Steel t 37.50 34,757.89 1,303,420.89
ii Grade 40 Reinforcement Steel t 62.80 33,583.39 2,109,036.91
8400 Concrete for Structures
84.01 Cast in situ concrete
a Class 30/20 concrete in all Reinforced Concrete Structures m3 690.85 3,266.49 2,256,651.36
b Class 25/20 concrete in all Reinforced Concrete Structures m3
c Class 15/20 concrete in lean concrete m3 26.95 2,570.71 69,272.29
d Cyclopean concrete underneath foundation footing m3 909.88 2,570.71 2,339,023.27
8700 Bridge Bearings, Parapets, Railings, Footways, No-fines Concrete,
Water-proofing and Drainage for Structures
87.03 Elastomeric Bearing No. 16.00 11,470.53 183,528.50
87.07 Concrete parapet m 50.00 685.12 34,256.07
87.13 Expansion joints
a Expansion joint with 20mm filler m 43.00 365.89 15,733.06
87.16 a Joint sealant, 20mm deep grouted polysulphide sealant m 43.00 182.87 7,863.53
87.19 Drainage pipes and weep holes
a Drainage pipes:
i Dia. 100mm PVC pipe No.
b Weep holes
i Dia. 200mm PVC pipe m 211.20 82.96 17,520.70
87.23 Crushed Stone in drainage Strips m3 237.60 575.16 136,657.57
8900 Stone Masonry Structures
89.01 Stone masonry walls
b Cement-mortared stone masonry walls (Class "B" Stone Masonry) m3 8,050.00 1,660.28 13,365,231.09
81000 Mechanically Stabilized Earth
810.01 Supply and erection of MSE structure
Gabion wall facing as shown on the drawings (including rock fill, connection
a wires, Geotextile filter for drainage behind gabion wall facing, and other m2
accessories)
b Polymeric (Geogrid) Reinforcements m2
Drainage at interface of backfill and in-situ soil (including Longitudinal
c Perforated Drainage Pipe, Transverse Outlet Pipe and geotextile filter, as m2
shown on drawings)
810.02 Fill material in MSE structures m3 367.29
8000 STRUCTURES - TOTAL(Carried forward to summary) 25,567,535.26

DIVISION 9000 ANCILLARY WORKS


9100 Gabions and Mattresses
91.01 Foundation trench excavation and backfilling
a In solid rock (material requiring blasting) m3 - 240.74
b Excavation (common) in all other classes of material m3 - 110.11
c Backfilling m3
91.02 Surface preparation for bedding m2 - 49.17
91.03 Gabions and Mattresses -
a Gabion boxes -
Gabion boxes (galvanized, wire dia 2.7mm, box size (2x1x1) and mesh size
i m3
100x120mm, diaphragm spacing 1m)

Stadia Engineering Works Consultant Plc Page 6 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity Rate Amount

ii Gabion boxes (galvanized, wire dia 2.7mm, box size (1.5x1x1) and mesh
m3
size 100x120mm, diaphragm spacing 1m) -

Stadia Engineering Works Consultant Plc Page 7 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity Rate Amount
91.04 Filter Fabric (Terram 1000 or equivalent) m2 -
9200 DELINEATORS, MARKERS AND KILOMETRE POSTS
92.01 Delineators, markers (guide posts) and kilometer posts
b Guide Posts (reinforced concrete C- 20) No.
c Kilometer posts (reinforced concrete C- 20) No. 6.00 803.77 4,822.60
9300 Guardrails
93.01 Galvanized guard rails on steel post m 360.00 494.17 177,900.32
9400 ROAD SIGNS
Sign faces with painted background. Symbols, lettering and borders in
94.01 Engineering grade retro-reflective material with signboard constructed
from aluminum alloy of thickness 2mm
a Traffic signs
i Area not exceeding 2 m² m2 35.24 1,572.79 55,417.13
ii Area exceeding 2 m² m2
94.02 Sign Supports
a Concrete Class C 20/20 No.
b Steel No. 44.00 555.79 24,454.72
Concrete in road sign footings including excavation and backfilling
94.03 m3 2.61 2,662.35 6,948.73
(Class 15/20)
9500 Road Traffic Markings, Road Studs and Traffic Calming
95.01 Paint (thermoplastic road marking)
a White lines (broken or unbroken) (width of 100mm) km 6.60 12,506.72 82,544.32
b Yellow lines (broken or unbroken) (width of 100mm) km 6.60 12,506.72 82,544.32
c White lettering and symbols m2 40.00 125.07 5,002.69
95.02 Variation in rate of application:
a White paint l 50.54
b Yellow paint l 50.54
c Glass beads Kg 35.10
95.04 Traffic Calming
a In situ asphalt Speed Bumps (Single Bump 10m wide and 0.1m thick as per m
drawing)
b In situ asphalt Rumble Strips (classification of set of 4 strips specified) m
9600 Landscaping and Grassing
96.01 Stockpiling of Topsoil m3
96.02 Preparation of areas for grassing:
a Top-soiling m3
b Provide and apply chemical fertilizers (type) t
96.03 Grassing:
a Planting of grass cuttings ha
b Seeding ha
96.04 Replacement or replanting of trees and growth management No.
96.05 Reinstatement of construction sites
a Prov. Sum
Reinstatement of camp sites
b Prov. Sum
Reinstatement of plant sites and storage sites
c Percentage allowed for overhead and profit on item 96.05 (a) & (b) %
9900 Footways and Masonry and Concrete Safety Barriers
99.02 Safety Barrier
a Masonry m
b Precast Concrete as per drawing m
9000 ANCILLARY WORKS - TOTAL (Carried forward to summary) 439,634.82

Stadia Engineering Works Consultant Plc Page 8 of 145


WUKRO – ATSBI – KONOBA ROAD PROJECT Ethiopian Roads Authority

BILL 11 DAYWORKS

Item Number Description Unit Quantity Rate Amount


11.1 LABOR
11.1 (a) Unskilled Labour hr 5,000.00 12.6 63,093.41
11.1 (b) Skilled Labour hr 2,000.00 15.3 30,694.09
11.1 (c) Driver Heavy hr 1,500.00 39.8 59,682.95
11.1 (d) Driver Light hr 900.00 31.8 28,647.82
11.1 (e) Operator I Class hr 2,000.00 22.7 45,472.73
11.1 (f) Operator II Class hr 1,000.00 28.4 28,420.45
11.1 (g) Foreman hr 2,000.00 17.1 34,104.55
11.1 (h) Mason hr 2,000.00 22.2 44,335.91
11.1 (i) Carpenter hr 900.00 40.9 36,832.91
11.1 (j) Surveyor hr 300.00 90.9 27,283.64
Sub-total (11.1) 398,568.46
11.2 MATERIAL
11.2 (a) Portland cement on site Qtl 20.00 255.8 5,115.60
11.2 (b) Reinforcing steel on site ton 5.00 19,060.0 95,300.00
11.2 (c) Bitumen MC-30 kg 7,500.00 28.4 212,925.00
11.2 (d) Bitumen 80/100, 60/70 kg 10,000.00 19.1 190,950.00
11.2 (e) Aggregates m3 150.00 327.9 49,190.45
11.2 (f) Gabion m3 100.00 374.5 37,450.00
11.2 (g) Gabion mattress m2 50.00 374.5 18,725.00
11.2 (h) Rock fill m3 120.00 217.9 26,148.26
Sub-total (11.2) 635,804.31
11.3 EQUIPMENT
11.3 (a) Dozer (Cat D8R) hr 100.00 2,080.7 208,070.71
11.3 (b) Track Loader I (Cat 953C) hr 180.00 1,087.9 195,818.85
11.3 (c) Track Loader II (Cat 973) hr 180.00 1,782.4 320,834.81
11.3 (d) Grader (Cat 14G) hr 100.00 1,603.2 160,322.00
11.3 (e) Loader (Cat 980G) hr 100.00 1,782.4 178,241.56
11.3 (f) Back Hoe/Excavator hr 120.00 941.9 113,025.14
11.3 (g) Excavator (Cat 225) hr 100.00 1,390.8 139,075.51
11.3 (h) Steel Roller 10/12 t hr 100.00 760.4 76,035.78
11.3 (i) Pneumatic Roller 12 t hr 100.00 790.2 79,017.94
11.3 (j) Vibrating Roller 12 t hr 100.00 760.4 76,035.78
11.3 (k) Dump Truck hr 100.00 585.8 58,578.71
11.3 (l) Water Tanker 6,000 lt hr 100.00 568.6 56,860.75
11.3 (m) Air Compressor hr 100.00 396.4 39,642.84
11.3 (n) Generator 15 Kw hr 100.00 95.0 9,500.00
11.3 (o) Generator 150 Kw hr 150.00 475.0 71,250.00
11.3 (p) Concrete Vibrator hr 150.00 24.9 3,736.97
11.3 (q) Vibroplate hr 100.00 15.8 1,576.84
11.3 (r) Concrete Mixer 15 HP 0.5m3 hr 100.00 50.9 5,091.71
11.3 (s) Crusher plant hr 100.00 3,432.4 343,244.54
11.3 (t) Chip (Aggregate) Spreader hr 100.00 1,472.9 147,294.74
11.3 (u) Biumen distributor hr 100.00 1,171.4 117,137.88
11.3 (v) Power Broom hr 100.00 544.4 54,441.46
Sub-total (11.3) 2,454,834.52

SUMMARY FOR BILL NO. 11. DAYWORKS

Pay Item Description Unit Quantity Rate Amount

11.1 Labour 398,568.46

11.2 Material 635,804.31

11.3 Equipment 2,454,834.52

SUB TOTAL 3,489,207.29


Allow specified percent of sub-total for % 1,221,222.55
Contractor's overheads, profit etc 35%

TOTAL FOR BILL NO 11 : DAYWORKS 4,710,429.84

Stadia Engineering Works Consultant Plc Page 9 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No :

Activity No : a Category: Sub-Component ADP= March 21, 2017


Activity Name: Borrow Material Production Scope: Material Production 686.00 M3 Result: 34.74 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.IV 1 8.00 102.31 818.51 81.08
2 Helper II 1 8.00 23.87 190.99 18.92
3
4
Labour Sub-total 1,009.49 - 8.64
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 100.00
2
3
Equipment Sub-total 2,080.71 10,672.75 5,972.91 91.36
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 11,682.24 5,972.91

Average daily production (ADP) = 686.00 M3


Activity operational cost per crew day / ADP = 17.03 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 22.99 Birr/m3
Activity replacement cost per crew day / ADP = 8.71 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 11.75 Birr/m3
Total Activity Unit Rate = 34.74 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 10 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : b Category: Sub-Component ADP= March 21, 2017
Activity Name: Select Material Production Scope: Material Production 560.00 M3 Result: 42.56 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.IV 1 8.00 102.31 818.51 81.08
2 Helper II 1 8.00 23.87 190.99 18.92
3
4
Labour Sub-total 1,009.49 - 8.64
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 100.00
2
3
Equipment Sub-total 2,080.71 10,672.75 5,972.91 91.36
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 11,682.24 5,972.91

Average daily production (ADP) = 560.00 M3


Activity operational cost per crew day / ADP = 20.86 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 28.16 Birr/m3
Activity replacement cost per crew day / ADP = 10.67 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 14.40 Birr/m3
Total Activity Unit Rate = 42.56 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 11 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : c Category: Sub-Component ADP= March 21, 2017
Activity Name: Quarry Rock Production Scope: Material Production 480.00 M3 Result: 187.73 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Quarry Foreman 1 8.00 56.84 454.73 11.35
2 St.eq.opI 1 8.00 22.74 181.89 4.54
3 Powder Man I 1 8.00 30.69 245.55 6.13
4 Equ.op.IV 1 8.00 102.31 818.51 20.43
5 Helper I 1 8.00 18.76 150.06 3.75
6 Labor Foreman 1 8.00 17.05 136.42 3.41
7 Labour I 20 160.00 12.62 2,018.99 50.40
8
Labour Sub-total 4,006.15 - 7.87
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 37.63
2 Air Compressor 600CFM 16.00 377.78 18.65 396.43 6,044.45 298.41 21.31
3 Drill, Self Prop, Crawler Type 4500 Kg 16.00 727.88 599.01 1,326.89 11,646.14 9,584.13 41.06
4 Hand Tools
Equipment Sub-total 3,804.03 28,363.34 15,855.44 55.73
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Ammonium Nitrate Kg 60.00 180.00 10,800.00 58.31
2 Power Jell Kg 90.00 2.25 202.50 1.09
3 Electrical Detonator No 65.00 16.00 1,040.00 5.61
4 Cord m 16.00 180.00 2,880.00 15.55
5 Connecting wire m 12.00 300.00 3,600.00 19.44
6 Bits & Drills No
Material Sub-total 18,522.50 - 36.40
Total Cost per crew day 50,891.99 15,855.44

Average daily production (ADP) = 480.00 M3


Activity operational cost per crew day / ADP = 106.02 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 143.13 Birr/m3
Activity replacement cost per crew day / ADP = 33.03 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 44.59 Birr/m3
Total Activity Unit Rate = 187.73 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 12 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : d Category: Sub-Component ADP= March 21, 2017
Activity Name: Scope: Material Production 240.00 M3 Result: 442.71 Birr/m3
Rock Crushing -Surface & concrete Aggregate

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mat. Prod. Sup. 1 8.00 90.95 727.56 22.15
2 Equ.op.III 1 2.00 39.79 79.58 2.42
3 Driver III 3 20.00 36.38 727.56 22.15
4 St.eq.opI 1 8.00 22.74 181.89 5.54
5 Mechanic II 1 8.00 51.16 409.25 12.46
6 Helper I 1 8.00 18.76 150.06 4.57
7 Labour I 10 80.00 12.62 1,009.49 30.73
Labour Sub-total 3,285.40 - 5.62
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 1.99
2 Crusher Plant 51-100 TPH 8.00 2,319.77 1,112.67 27,459.56 18,558.17 8,901.40 62.35
3 Loader, Crawler 2-2.5 M3 1.00 979.60 802.82 1,782.42 979.60 802.82 3.29
4 Dump truck,6*4 (12m3) 12M3 20.00 481.75 104.04 104.04 9,635.00 2,080.75 32.37
Equipment Sub-total 30,433.90 29,764.41 12,281.19 50.88
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Stone M3 106.02 33.03 240.00 25,445.99 7,927.72 100.00
2 - -
Material Sub-total 25,445.99 7,927.72 43.50
Total Cost per crew day 58,495.81 20,208.91

Average daily production (ADP) = 240.00 M3


Activity operational cost per crew day / ADP = 243.73 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 329.04 Birr/m3
Activity replacement cost per crew day / ADP = 84.20 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 113.68 Birr/m3
Total Activity Unit Rate = 442.71 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 13 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : e Category: Sub-Component ADP= March 21, 2017
Activity Name: Rock Crushing -Base Aggregate Scope: Material Production 260.00 M3 Result: 435.35 Birr/m3

Hours per Hourly cost


Item No Type Daily cost % for operation
crew day (Indexed)
1 Mat. Prod. Sup. 1 8.00 90.95 727.56 17.19
2 Equ.op.III 3 24.00 39.79 954.93 22.56
3 Driver III 3 22.00 36.38 800.32 18.90
3 St.eq.opI 1 8.00 22.74 181.89 4.30
4 Mechanic II 1 8.00 51.16 409.25 9.67
5 Helper I 1 8.00 18.76 150.06 3.54
6 Labour I 10 80.00 12.62 1,009.49 23.85
Labour Sub-total 4,233.51 - 6.76
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 1.08 591.65 496.23 1,087.88 640.96 537.58 2.08
2 Crusher Plant 51-100 TPH 8.00 2,319.77 1,112.67 3,432.45 18,558.17 8,901.40 60.14
3 Loader, Crawler 2-2.5 M3 1.08 979.60 802.82 1,782.42 1,061.23 869.72 3.44
4 Dump truck,6*4 (12m3) 12M3 22.00 481.75 104.04 585.79 10,598.50 2,288.82 34.35
Equipment Sub-total 6,888.53 30,858.85 12,597.52 49.25
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Stone M3 106.02 33.03 260.00 27,566.49 8,588.37 100.00
2
3
Material Sub-total 27,566.49 8,588.37 43.99
Total Cost per crew day 62,658.85 21,185.89

Average daily production (ADP) = 260.00 M3


Activity operational cost per crew day / ADP = 241.00 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 325.34 Birr/m3
Activity replacement cost per crew day / ADP = 81.48 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 110.00 Birr/m3
Total Activity Unit Rate = 435.35 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 14 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : f Category: Sub-Component ADP= March 21, 2017
Activity Name: Rock Crushing -Sub Base Aggregate Scope: Material Production 280.00 M3 Result: 413.42 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mat. Prod. Sup. 1 8.00 90.95 727.56 21.38
2 Equ.op.III 1 2.33 39.79 92.84 2.73
3 Driver III 3 22.89 36.38 832.66 24.46
3 St.eq.opI 1 8.00 22.74 181.89 5.34
4 Mechanic II 1 8.00 51.16 409.25 12.02
5 Helper I 1 8.00 18.76 150.06 4.41
6 Labour I 10 80.00 12.62 1,009.49 29.66
7
Labour Sub-total 3,403.76 - 5.31
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 2.33 591.65 496.23 1,087.88 1,380.52 1,157.87 4.46
2 Crusher Plant 51-100 TPH 8.00 2,319.77 1,112.67 3,432.45 18,558.17 8,901.40 59.93
3 Dump truck,6*4 (12m3) 12M3 22.89 481.75 104.04 585.79 11,026.72 2,381.30 35.61
Equipment Sub-total 5,106.11 30,965.40 12,440.57 48.34
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Stone M3 106.02 33.03 280.00 29,686.99 9,249.01 100.00
Material Sub-total 29,686.99 9,249.01 46.35
Total Cost per crew day 64,056.16 21,689.58 100.00

Average daily production (ADP) = 280.00 M3


Activity operational cost per crew day / ADP = 228.77 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 308.84 Birr/m3
Activity replacement cost per crew day / ADP = 77.46 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 104.57 Birr/m3
Total Activity Unit Rate = 413.42 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering 30% void & waste for quarry rock hauling calculation
* 0.5Km free hauling distance for quarry rock hauling operation

Stadia Engineering Works Consultant Plc Page 15 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : g Category: Sub-Component ADP= March 21, 2017
Activity Name: Hot Mix Production (AC - 60/70) Scope: Material Production 200.00 M3 Result: 4,439.00 Birr/m3
*(Central Mix Plant)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Batch plant Sup. 1 8.00 86.40 691.19 15.98
2 Equ.op.III 1 4.00 39.79 159.15 3.68
3 Welder II 1 8.00 45.47 363.78 8.41
4 Mechanic III 1 8.00 71.62 572.96 13.25
5 Elec. III 1 8.00 71.62 572.96 13.25
6 Helper II 5 40.00 23.87 954.93 22.08
7 Labour I 10 80.00 12.62 1,009.49 23.34
Labour Sub-total 4,324.46 - 0.69
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 4,351.53 2,366.60 1,984.93 9.67
2 Asphalt Plant 130-150TPH 8.00 2,669.98 435.31 24,842.31 21,359.81 3,482.50 87.24
3 AC Welder, Diesel 300-400AMP 4.00 189.56 16.19 823.00 758.24 64.76 3.10
Equipment Sub-total 30,016.84 24,484.65 5,532.18 3.90
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Bitumen - AC-60/70 Kg 19.10 - 27,600.00 527,022.00 - 88.08
2 Chip Aggregate M3 262.13 91.80 272.00 71,298.39 24,968.25 11.92
Material Sub-total 598,320.39 24,968.25 95.41
Total Cost per crew day 627,129.50 30,500.43

Average daily production (ADP) = 200.00 M3


Activity operational cost per crew day / ADP = 3,135.65 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 4,233.12 Birr/m3
Activity replacement cost per crew day / ADP = 152.50 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 205.88 Birr/m3
Total Activity Unit Rate = 4,439.00 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 16 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : h Category: Sub-Component ADP= March 21, 2017
Activity Name: Hot Mix Production (AC - 80/100) Scope: Material Production 200.00 M3 Result: 5,605.38 Birr/m3
*(Central Mix Plant)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Batch plant Sup. 1 8.00 86.40 691.19 16.28
2 Equ.op.III 1 2.00 39.79 79.58 1.87
3 Welder II 1 8.00 45.47 363.78 8.57
4 Mechanic III 1 8.00 71.62 572.96 13.50
5 Elec. III 1 8.00 71.62 572.96 13.50
6 Helper II 5 40.00 23.87 954.93 22.50
7 Labour I 10 80.00 12.62 1,009.49 23.78
Labour Sub-total 4,244.88 - 0.53
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 2.00 591.65 496.23 2,175.77 1,183.30 992.46 11.89
2 Asphalt Plant 130-150TPH 3.00 2,669.98 435.31 9,315.87 8,009.93 1,305.94 80.49
3 AC Welder, Diesel 300-400AMP 4.00 189.56 16.19 823.00 758.24 64.76 7.62
Equipment Sub-total 12,314.63 9,951.47 2,363.16 1.24
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Bitumen - AC-80/100 Kg 26.00 - 27,600.00 717,600.00 - 90.96
2 Chip Aggregate M3 262.13 91.80 272.00 71,298.39 24,968.25 9.04
Material Sub-total 788,898.39 24,968.25 98.23
Total Cost per crew day 803,094.74 27,331.41

Average daily production (ADP) = 200.00 M3


Activity operational cost per crew day / ADP = 4,015.47 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 5,420.89 Birr/m3
Activity replacement cost per crew day / ADP = 136.66 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 184.49 Birr/m3
Total Activity Unit Rate = 5,605.38 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 17 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : i Category: Sub-Component ADP= March 21, 2017
Activity Name: Pipe Production(Dia.36) Scope: Material Production 15.00 Each Result: 1,419.03 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason II 2 16.00 32.40 518.39 16.43
2 St.eq.opI 1 8.00 22.74 181.89 5.76
3 Bar Sett.I 2 16.00 30.69 491.11 15.56
4 Helper I 3 24.00 18.76 450.18 14.27
5 Labour I 15 120.00 12.62 1,514.24 47.98
Labour Sub-total 3,155.81 - 20.52
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 4.00 42.64 8.28 50.92 170.56 33.10 65.48
2 Concrete Vibrator 5 HP 4.00 22.48 2.43 24.91 89.91 9.74 34.52
3 Pipe Molds - 120.00 - 1.20 144.00
4 Hand Tools
5
Equipment Sub-total 260.48 186.84 1.69
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.35 6,690.06 - 55.94
2 Binding wire Kg 32.00 6.25 200.00 - 1.67
3 Cement Quintal 255.78 14.58 3,729.27 - 31.18
4 Sand m3 461.54 1.62 747.69 - 6.25
5 Crushed Aggregate M3 243.73 84.20 2.43 592.27 204.62 4.95
Material Sub-total 11,959.29 204.62 77.78
Total Cost per crew day 15,375.58 391.46

Average daily production (ADP) = 15.00 Each


Activity operational cost per crew day / ADP = 1,025.04 Birr/each
Total Oper. unit cost including 35% overhead & profit = 1,383.80 Birr/each
Activity replacement cost per crew day / ADP = 26.10 Birr/each
Total Repl. unit cost including 35% overhead & profit = 35.23 Birr/each
Total Activity Unit Rate = 1,419.03 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 18 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : j Category: Sub-Component ADP= March 21, 2017
Activity Name: Pipe Production(Dia.42) Scope: Material Production 15.00 Each Result: 1,908.02 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason II 3 24.00 32.40 777.58 17.02
2 St.eq.opI 1 8.00 22.74 181.89 3.98
3 Bar Sett.I 3 24.00 30.69 736.66 16.13
4 Helper I 4 32.00 18.76 600.24 13.14
5 Labour I 23 180.00 12.62 2,271.36 49.73
Labour Sub-total 4,567.74 - 22.02
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 4.00 42.64 8.28 50.92 170.56 33.10 65.48
2 Concrete Vibrator 5 HP 4.00 22.48 2.43 24.91 89.91 9.74 34.52
3 Pipe Molds - 120.00 - 1.20 144.00
4 Hand Tools
5
Equipment Sub-total 260.48 186.84 1.26
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.47 8,948.67 - 56.21
2 Binding wire Kg 32.00 12.50 400.00 - 2.51
3 Cement Quintal 255.78 18.90 4,834.24 - 30.37
4 Sand m3 461.54 2.10 969.23 - 6.09
5 Crushed Aggregate M3 243.73 84.20 3.15 767.76 265.24 4.82
Material Sub-total 15,919.90 265.24 76.73
Total Cost per crew day 20,748.12 452.08

Average daily production (ADP) = 15.00 Each


Activity operational cost per crew day / ADP = 1,383.21 Birr/each
Total Oper. unit cost including 35% overhead & profit = 1,867.33 Birr/each
Activity replacement cost per crew day / ADP = 30.14 Birr/each
Total Repl. unit cost including 35% overhead & profit = 40.69 Birr/each
Total Activity Unit Rate = 1,908.02 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 19 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : k Category: Sub-Component ADP= March 21, 2017
Activity Name: Pipe Production(Dia.48) Scope: Material Production 15.00 Each Result: 2,704.24 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason II 4 32.00 32.40 1,036.78 16.91
2 St.eq.opI 1 8.00 22.74 181.89 2.97
3 Bar Sett.I 4 32.00 30.69 982.21 16.02
4 Helper I 6 48.00 18.76 900.36 14.69
5 Labour I 30 240.00 12.62 3,028.48 49.41
Labour Sub-total 6,129.72 - 20.76
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 5.00 42.64 8.28 50.92 213.21 41.38 70.34
2 Concrete Vibrator 5 HP 4.00 22.48 2.43 24.91 89.91 9.74 29.66
3 Pipe Molds - 120.00 - 1.20 144.00
4 Hand Tools
5
Equipment Sub-total 303.12 195.12 1.03
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.78 14,815.34 - 64.13
2 Binding wire Kg 32.00 12.50 400.00 - 1.73
3 Cement Quintal 255.78 22.68 5,801.09 - 25.11
4 Sand m3 461.54 2.52 1,163.08 - 5.03
5 Crushed Aggregate M3 243.73 84.20 3.78 921.31 318.29 3.99
Material Sub-total 23,100.81 318.29 78.22
Total Cost per crew day 29,533.66 513.41

Average daily production (ADP) = 15.00 Each


Activity operational cost per crew day / ADP = 1,968.91 Birr/each
Total Oper. unit cost including 35% overhead & profit = 2,658.03 Birr/each
Activity replacement cost per crew day / ADP = 34.23 Birr/each
Total Repl. unit cost including 35% overhead & profit = 46.21 Birr/each
Total Activity Unit Rate = 2,704.24 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 20 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : l Category: Sub-Component ADP= March 21, 2017
Activity Name: Guide Post Production Scope: Material Production 30.00 Each Result: 395.53 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carpenter I 1 8.00 40.93 327.40 30.38
2 Bar Sett.I 1 8.00 30.69 245.55 22.78
3 Labour I 5 40.00 12.62 504.75 46.84
4
Labour Sub-total 1,077.70 - 12.45
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 2.00 42.64 8.28 50.92 85.28 16.55 65.48
2 Concrete Vibrator 5 HP 2.00 22.48 2.43 24.91 44.96 4.87 34.52
3
4
Equipment Sub-total 130.24 21.42 1.51
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 0.91 420.92 5.65
2 Cement Quintal 255.78 8.21 2,099.44 28.20
3 Crushed Aggregate M3 243.73 84.20 1.37 333.43 115.19 4.48
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.22 4,231.32 56.83
5 Lumber m3 10,000.00 0.04 360.00 4.84
Material Sub-total 7,445.11 115.19 86.04
Total Cost per crew day 8,653.05 136.61

Average daily production (ADP) = 30.00 Each


Activity operational cost per crew day / ADP = 288.44 Birr/each
Total Oper. unit cost including 35% overhead & profit = 389.39 Birr/each
Activity replacement cost per crew day / ADP = 4.55 Birr/each
Total Repl. unit cost including 35% overhead & profit = 6.15 Birr/each
Total Activity Unit Rate = 395.53 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 21 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : m Category: Sub-Component ADP= March 21, 2017
Activity Name: KM Post Production Scope: Material Production 30.00 Each Result: 395.53 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carpenter I 1 8.00 40.93 327.40 30.38
2 Bar Sett.I 1 8.00 30.69 245.55 22.78
3 Labour I 5 40.00 12.62 504.75 46.84
4
Labour Sub-total 1,077.70 - 12.45
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 2.00 42.64 8.28 50.92 85.28 16.55 65.48
2 Concrete Vibrator 5 HP 2.00 22.48 2.43 24.91 44.96 4.87 34.52
3
4
Equipment Sub-total 130.24 21.42 1.51
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 0.91 420.92 5.65
2 Cement Quintal 255.78 8.21 2,099.44 28.20
3 Crushed Aggregate M3 243.73 84.20 1.37 333.43 115.19 4.48
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.22 4,231.32 56.83
5 Lumber m3 10,000.00 0.04 360.00 4.84
Material Sub-total 7,445.11 115.19 86.04
Total Cost per crew day 8,653.05 136.61

Average daily production (ADP) = 30.00 Each


Activity operational cost per crew day / ADP = 288.44 Birr/each
Total Oper. unit cost including 35% overhead & profit = 389.39 Birr/each
Activity replacement cost per crew day / ADP = 4.55 Birr/each
Total Repl. unit cost including 35% overhead & profit = 6.15 Birr/each
Total Activity Unit Rate = 395.53 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 22 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : n Category: Sub-Component ADP= March 21, 2017
Activity Name: HCB Production Scope: Material Production 160.00 Each Result: 7.28 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 5.00 17.05 85.26 31.06
2 Labour I 2 15.00 12.62 189.28 68.94
3
Labour Sub-total 274.54 - 31.83
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 HCB Machine 5.00 - - - - -
2
Equipment Sub-total - -
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 0.72 332.31 56.51
2 Cement Quintal 255.78 1.00 255.78 43.49
3
4
Material Sub-total 588.09 - 68.17
Total Cost per crew day 862.63 -

Average daily production (ADP) = 160.00 Each


Activity operational cost per crew day / ADP = 5.39 Birr/each
Total Oper. unit cost including 35% overhead & profit = 7.28 Birr/each
Activity replacement cost per crew day / ADP = - Birr/each
Total Repl. unit cost including 35% overhead & profit = - Birr/each
Total Activity Unit Rate = 7.28 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 23 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : o Category: Sub-Component ADP= March 21, 2017
Activity Name: Sand Production Scope: Material Production 28.00 M3 Result: 385.88 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.III 1 8.00 39.79 318.31 67.96
2 Helper I 1 8.00 18.76 150.06 32.04
3
4
Labour Sub-total 468.37 - 9.07
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 100.00
2
3
4
Equipment Sub-total 941.88 4,698.07 2,836.94 90.93
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
Material Sub-total - -
Total Cost per crew day 5,166.44 2,836.94

Average daily production (ADP) = 28.00 M3


Activity operational cost per crew day / ADP = 184.52 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 249.10 Birr/m3
Activity replacement cost per crew day / ADP = 101.32 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 136.78 Birr/m3
Total Activity Unit Rate = 385.88 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 24 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : p Category: Sub-Component ADP= March 21, 2017
Activity Name: Sand Hauling Scope: Material Production 1,129.41 M3 Result: 62.39 Birr/m3
* 10.5km freehaul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.III 10 77.02 39.79 3,064.51 100.00
2
3
4
Labour Sub-total 3,064.51 - 7.47
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 12.46
2 Dump truck,6*4 (12m3) 12M3 69.02 481.75 104.04 585.79 33,250.18 7,180.61 87.54
3
4
Equipment Sub-total 1,673.67 37,983.39 11,150.47 92.53
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
Material Sub-total - -
Total Cost per crew day 41,047.90 11,150.47

Average daily production (ADP) = 1,129.41 M3


Activity operational cost per crew day / ADP = 36.34 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 49.07 Birr/m3
Activity replacement cost per crew day / ADP = 9.87 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 13.33 Birr/m3
Total Activity Unit Rate = 62.39 Birr/m3

Stadia Engineering Works Consultant Plc Page 25 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : q Category: Sub-Component ADP= March 21, 2017
Activity Name: Formwork - Minor Drainage Scope: Drainage 32.00 M2 Result: 239.73 Birr/m2

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carp. Foreman 1 8.00 64.80 518.39 20.68
2 Driver III 1 2.00 36.38 72.76 2.90
3 Carpenter II 3 24.00 54.57 1,309.61 52.25
4 Labour I 6 48.00 12.62 605.70 24.17
5
6
Labour Sub-total 2,506.46 - 45.52
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 100.00
2 Hand Tools
3
4
Equipment Sub-total 514.88 853.51 176.24 15.50
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Equaliptus Pole (Dia. 100mm, 8m long) No 100.00 8.00 800.00 - 37.27
2 Lumber m3 10,000.00 0.13 1,280.00 - 59.64
3 Nails kg 26.50 2.50 66.25 - 3.09
Material Sub-total 2,146.25 - 38.98
Total Cost per crew day 5,506.22 176.24

Average daily production (ADP) = 32.00 M2


Activity operational cost per crew day / ADP = 172.07 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 232.29 Birr/m2
Activity replacement cost per crew day / ADP = 5.51 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 7.44 Birr/m2
Total Activity Unit Rate = 239.73 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering to re-use Each Equaliptus pole & lumber 2 1/2 times

Stadia Engineering Works Consultant Plc Page 26 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : r Category: Sub-Component ADP= March 21, 2017
Activity Name: Duct Marker Blocks Production Scope: Material Production 30.00 Each Result: 223.98 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carpenter I 1 8.00 40.93 327.40 30.38
2 Bar Sett.I 1 8.00 30.69 245.55 22.78
3 Labour I 5 40.00 12.62 504.75 46.84
4
Labour Sub-total 1,077.70 - 21.96
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 2.00 42.64 8.28 50.92 85.28 16.55 65.48
2 Concrete Vibrator 5 HP 2.00 22.48 2.43 24.91 44.96 4.87 34.52
3 Pipe Molds - - 1.20
4
Equipment Sub-total 130.24 21.42 2.65
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 0.38 174.46 4.71
2 Cement Quintal 255.78 3.40 870.16 23.52
3 Crushed Aggregate M3 243.73 84.20 0.57 138.20 47.74 3.73
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.11 2,058.48 55.63
5 Lumber m3 10,000.00 0.05 459.00 12.40
Material Sub-total 3,700.30 47.74 75.39
Total Cost per crew day 4,908.24 69.16

Average daily production (ADP) = 30.00 Each


Activity operational cost per crew day / ADP = 163.61 Birr/each
Total Oper. unit cost including 35% overhead & profit = 220.87 Birr/each
Activity replacement cost per crew day / ADP = 2.31 Birr/each
Total Repl. unit cost including 35% overhead & profit = 3.11 Birr/each
Total Activity Unit Rate = 223.98 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 27 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : s Category: Sub-Component ADP= March 21, 2017
Activity Name: Scope: Drainage 12.00 M3 Result: 3,124.94 Birr/m3
Class A bedding (Class 20/20 concrete)
*(Grade 20)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8
Labour Sub-total 4,174.40 - 15.71
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 60.36
2 Concrete Vibrator 5 HP 16.00 22.48 2.43 24.91 359.66 38.95 20.35
3 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 19.30
4 Hand Tools
Equipment Sub-total 1,767.68 325.47 6.65
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 43.20 11,049.70 - 53.58
2 Formwork m2 172.07 5.51 23.57 4,055.68 129.82 19.67
3 Sand m3 461.54 7.20 3,323.08 - 16.11
4 Crushed Aggregate M3 243.73 84.20 9.00 2,193.59 757.83 10.64
Material Sub-total 20,622.04 887.65 77.63
Total Cost per crew day 26,564.12 1,213.12

Average daily production (ADP) = 12.00 M3


Activity operational cost per crew day / ADP = 2,213.68 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,988.46 Birr/m3
Activity replacement cost per crew day / ADP = 101.09 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 136.48 Birr/m3
Total Activity Unit Rate = 3,124.94 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 28 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : t Category: Sub-Component ADP= March 21, 2017
Activity Name: Rock Crushing -Chip Aggregate Scope: Material Production 200.00 M3 Result: 477.79 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mat. Prod. Sup. 1 8.00 90.95 727.56 23.00
2 Equ.op.III 1 1.67 39.79 66.31 2.10
3 Driver III 3 17.00 36.38 618.43 19.55
4 St.eq.opI 1 8.00 22.74 181.89 5.75
5 Mechanic II 1 8.00 51.16 409.25 12.94
6 Helper I 1 8.00 18.76 150.06 4.74
7 Labour I 10 80.00 12.62 1,009.49 31.92
Labour Sub-total 3,163.01 - 6.03
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 0.83 591.65 496.23 906.57 493.04 413.53 1.76
2 Crusher Plant 51-100 TPH 8.00 2,319.77 1,112.67 27,459.56 18,558.17 8,901.40 66.14
3 Loader, Crawler 2-2.5 M3 0.83 979.60 802.82 1,485.35 816.33 669.01 2.91
4 Dump truck,6*4 (12m3) 12M3 17.00 481.75 104.04 - 8,189.75 1,768.63 29.19
Equipment Sub-total 29,851.48 28,057.29 11,752.57 53.52
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Stone M3 106.02 33.03 200.00 21,204.99 6,606.44 100.00
2 - -
Material Sub-total 21,204.99 6,606.44 40.45
Total Cost per crew day 52,425.29 18,359.01

Average daily production (ADP) = 200.00 M3


Activity operational cost per crew day / ADP = 262.13 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 353.87 Birr/m3
Activity replacement cost per crew day / ADP = 91.80 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 123.92 Birr/m3
Total Activity Unit Rate = 477.79 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 29 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 15.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Scope: Traffic Management 0.77 Result: 136,323.70 Birr/Km
*5 Km free haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 4.00 73.89 295.57 8.01
2 Equ.op.IV 2 14.00 102.31 1,432.39 38.82
3 Equ.op.III 4 30.00 39.79 1,193.66 32.35
4 Equ.op.II 1 4.00 28.42 113.68 3.08
5 Helper I 1 8.00 18.76 150.06 4.07
6 Labour I 5 40.00 12.62 504.75 13.68
Labour Sub-total 3,690.11 6.76
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 4.00 1,334.09 746.61 2,080.71 5,336.37 2,986.45 12.99
2 Motor Grader 145-165 HP 6.00 808.70 794.52 1,603.22 4,852.23 4,767.09 11.81
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 8.24
4 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 9.33
5 Loader, Wheel 2-2.5 M3 5.00 591.65 496.23 1,087.88 2,958.25 2,481.16 7.20
6 Dump truck,6*4 (12m3) 12M3 43.00 481.75 104.04 585.79 20,715.24 4,473.60 50.43
7 -
Equipment Sub-total 6,686.56 41,077.46 18,124.67 75.23
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Borrow material m3 17.03 8.71 577.50 9,834.54 5,028.21 100.00
Material Sub-total 9,834.54 5,028.21 18.01
Total Cost per crew day 54,602.11 23,152.89

Average daily production (ADP) = 0.77


Activity operational cost per crew day / ADP = 70,911.83 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 95,730.97 Birr/Km
Activity replacement cost per crew day / ADP = 30,068.69 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 40,592.73 Birr/Km
Total Activity Unit Rate = 136,323.70 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *This activity includes clearing & grubbing, shaping & placing of 10 cm embankment with 7.5m width
*Considering 25% compaction factor for borrow material

Stadia Engineering Works Consultant Plc Page 30 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 15.01(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Maintenance of Diversion Scope: Traffic Management 0.70 km Result: 172,087.46 Birr/Km
*5 Km free haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 4.00 73.89 295.57 7.89
2 Equ.op.IV 1 8.00 102.31 818.51 21.84
3 Equ.op.III 6 44.00 39.79 1,750.70 46.72
4 Equ.op.II 1 8.00 28.42 227.36 6.07
5 Helper I 1 8.00 18.76 150.06 4.00
6 Labour I 5 40.00 12.62 504.75 13.47
7
Labour Sub-total 3,746.95 6.10
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Motor Grader 145-165 HP 8.00 808.70 794.52 1,603.22 6,469.63 6,356.13 15.67
2 Water truck,6*4 20000Lits 24.00 422.98 145.63 568.61 10,151.50 3,495.08 24.58
3 Roller,Vibrator,2Drums 8 ton 6.00 478.94 281.42 760.36 2,873.64 1,688.50 6.96
4 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 11.46
5 Dump truck,6*4 (8m3) 8M3 40.00 426.76 88.12 514.88 17,070.29 3,524.90 41.33
Equipment Sub-total 4,534.95 41,298.28 19,034.46 67.18
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Select Material m3 20.86 10.67 787.50 16,428.15 8,722.69 100.00
2
Material Sub-total 16,428.15 8,722.69 26.72
Total Cost per crew day 61,473.39 27,757.15

Average daily production (ADP) = 0.70 km


Activity operational cost per crew day / ADP = 87,819.12 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 118,555.82 Birr/Km
Activity replacement cost per crew day / ADP = 39,653.07 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 53,531.65 Birr/Km
Total Activity Unit Rate = 172,087.46 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Gravelling of detour with 15cm thick & 7.5m wide


*Considering 30% compaction factor for select material

Stadia Engineering Works Consultant Plc Page 31 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 15.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Scope: Traffic Management 0.77 Result: 136,323.70 Birr/Km
*5 Km free haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 4.00 73.89 295.57 8.01
2 Equ.op.IV 2 14.00 102.31 1,432.39 38.82
3 Equ.op.III 4 30.00 39.79 1,193.66 32.35
4 Equ.op.II 1 4.00 28.42 113.68 3.08
5 Helper I 1 8.00 18.76 150.06 4.07
6 Labour I 5 40.00 12.62 504.75 13.68
Labour Sub-total 3,690.11 6.76
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 4.00 1,334.09 746.61 2,080.71 5,336.37 2,986.45 12.99
2 Motor Grader 145-165 HP 6.00 808.70 794.52 1,603.22 4,852.23 4,767.09 11.81
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 8.24
4 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 9.33
5 Loader, Wheel 2-2.5 M3 5.00 591.65 496.23 1,087.88 2,958.25 2,481.16 7.20
6 Dump truck,6*4 (12m3) 12M3 43.00 481.75 104.04 585.79 20,715.24 4,473.60 50.43
7 -
Equipment Sub-total 6,686.56 41,077.46 18,124.67 75.23
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Borrow material m3 17.03 8.71 577.50 9,834.54 5,028.21 100.00
Material Sub-total 9,834.54 5,028.21 18.01
Total Cost per crew day 54,602.11 23,152.89

Average daily production (ADP) = 0.77


Activity operational cost per crew day / ADP = 70,911.83 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 95,730.97 Birr/Km
Activity replacement cost per crew day / ADP = 30,068.69 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 40,592.73 Birr/Km
Total Activity Unit Rate = 136,323.70 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 32 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 15.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Scope: Traffic Management 0.77 Result: 106,847.47 Birr/Km

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Safetyman I 1 8.00 34.10 272.84 57.47
2 Labour I 2 16.00 12.62 201.90 42.53
3
4
Labour Sub-total 474.74 100.00
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Barrier Boards 16.00 0.25 4.00
2 Traffic Cones 48.00 0.27 12.96
3 Traffic Sign 16.00 0.35 5.60
4 Traffic Hand Flag 32.00 0.18 5.76
5 High Visibility Vests 16.00 0.30 4.80
6
Equipment Sub-total - - 33.12
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Paints, Nails, etc… -
2
3
Material Sub-total - -
Total Cost per crew day 474.74 33.12

Average daily production (ADP) = 0.77 Duration= 120.00 Days


Activity operational cost per crew day / ADP = 616.54 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 832.33 Birr/Km
Activity replacement cost per crew day / ADP = 43.01 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 58.07 Birr/Km
Total Activity Unit Rate = 106,847.47 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering 1 km Work area (stretch) per day to facilitate traffic

Stadia Engineering Works Consultant Plc Page 33 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 15.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Scope: Traffic Management 0.77 Result: 104,474.28 Birr/Km

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Safetyman I 1 8.00 34.10 272.84 57.47
2 Labour I 2 16.00 12.62 201.90 42.53
3
4
Labour Sub-total 474.74 100.00
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Barrier Boards 8.00 0.25 2.00
2 Traffic Cones 24.00 0.27 6.48
3 Traffic Sign 8.00 0.35 2.80
4 Traffic Hand Flag 32.00 0.18 5.76
5 High Visibility Vests 16.00 0.30 4.80
6
Equipment Sub-total - - 21.84
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Paints, Nails, etc… -
2
3
Material Sub-total - -
Total Cost per crew day 474.74 21.84

Average daily production (ADP) = 0.77 Duration= 120.00 Days


Activity operational cost per crew day / ADP = 616.54 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 832.33 Birr/Km
Activity replacement cost per crew day / ADP = 28.36 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 38.29 Birr/Km
Total Activity Unit Rate = 104,474.28 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering 1 km Work area (stretch) per day to facilitate traffic

Stadia Engineering Works Consultant Plc Page 34 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 21.01 Category: Mechanized ADP= March 21, 2017
Activity Name: Clearing and Grubbing Scope: Site Clearance 1.10 ha Result: 46,816.85 Birr/ha

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For I 1 8.00 45.47 363.78 14.71
2 Equ.op.IV 1 8.00 102.31 818.51 33.10
3 Equ.op.III 2 8.77 39.79 348.77 14.11
4 Helper I 1 8.00 18.76 150.06 6.07
5 Driver III 3 16.21 36.38 589.52 23.84
6 Labour I 2 16.00 12.62 201.90 8.17
Labour Sub-total 2,472.54 9.46
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 45.10
2 Loader, Wheel 2-2.5 M3 8.77 591.65 496.23 1,087.88 5,186.19 4,349.78 21.91
3 Dump truck,6*4 (12m3) 12M3 16.21 481.75 104.04 585.79 7,806.93 1,685.96 32.99
Equipment Sub-total 3,754.38 23,665.87 12,008.65 90.54
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 26,138.41 12,008.65

Average daily production (ADP) = 1.10 ha


Activity operational cost per crew day / ADP = 23,762.19 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 32,078.96 Birr/ha
Activity replacement cost per crew day / ADP = 10,916.95 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 14,737.89 Birr/ha
Total Activity Unit Rate = 46,816.85 Birr/ha
Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 35 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 22.06(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Demolishing Plain concrete Scope: Site Clearance 30.00 Result: 474.94 Br / m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason I 1 8.00 22.17 177.34 18.48
2 Labour I 8 62.00 12.62 782.36 81.52
3 - -
4
Labour Sub-total 959.70 13.03
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 73.35
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 26.65
3 - - -
4 -
Equipment Sub-total 6,405.10 3,189.43 86.97
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
3
4
Material Sub-total - -
Total Cost per crew day 7,364.80 3,189.43

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 245.49 Br / m3
Total Oper. unit cost including 35% overhead & profit = 331.42 Br / m3
Activity replacement cost per crew day / ADP = 106.31 Br / m3
Total Repl. unit cost including 35% overhead & profit = 143.52 Br / m3
Total Activity Unit Rate = 474.94 Br / m3

Stadia Engineering Works Consultant Plc Page 36 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 22.06(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Demolishing Reinforced concrete Scope: Site Clearance 18.00 Result: 808.60 Br / m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason I 1 8.00 22.17 177.34 14.94
2 Labour I 10 80.00 12.62 1,009.49 85.06
3 - -
4
Labour Sub-total 1,186.84 15.63
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 73.35
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 26.65
3 - - -
4 -
Equipment Sub-total 6,405.10 3,189.43 84.37
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
3
4
Material Sub-total - -
Total Cost per crew day 7,591.94 3,189.43

Average daily production (ADP) = 18.00


Activity operational cost per crew day / ADP = 421.77 Br / m3
Total Oper. unit cost including 35% overhead & profit = 569.40 Br / m3
Activity replacement cost per crew day / ADP = 177.19 Br / m3
Total Repl. unit cost including 35% overhead & profit = 239.21 Br / m3
Total Activity Unit Rate = 808.60 Br / m3

Stadia Engineering Works Consultant Plc Page 37 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 22.06(c) Category: Mechanized ADP= March 21, 2017
Activity Name: Scope: Site Clearance 20.00 Result: 874.40 Birr/m3
Demolishing Masonry Structures - mortared

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.IV 1 8.00 102.31 818.51 44.78
2 Labour I 10 80.00 12.62 1,009.49 55.22
3 -
Labour Sub-total 1,828.00 22.57
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Crawler Type 1.76M3 8.00 784.05 606.71 1,390.76 6,272.37 4,853.67 100.00
2 Hand Tools
3
4
5
Equipment Sub-total 1,390.76 6,272.37 4,853.67 77.43
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 8,100.38 4,853.67

Average daily production (ADP) = 20.00


Activity operational cost per crew day / ADP = 405.02 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 546.78 Birr/m3
Activity replacement cost per crew day / ADP = 242.68 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 327.62 Birr/m3
Total Activity Unit Rate = 874.40 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 38 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 22.06(d) Category: Mechanized ADP= March 21, 2017
Activity Name: Demolishing Masonry Structures - dry Scope: Site Clearance 30.00 Result: 582.93 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.IV 1 8.00 102.31 818.51 44.78
2 Labour I 10 80.00 12.62 1,009.49 55.22
3 -
Labour Sub-total 1,828.00 22.57
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Crawler Type 1.76M3 8.00 784.05 606.71 1,390.76 6,272.37 4,853.67 100.00
2 Hand Tools
3
4
5
Equipment Sub-total 1,390.76 6,272.37 4,853.67 77.43
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 8,100.38 4,853.67

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 270.01 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 364.52 Birr/m3
Activity replacement cost per crew day / ADP = 161.79 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 218.42 Birr/m3
Total Activity Unit Rate = 582.93 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 39 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 31.01(a) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Open Drain Excavation (in soft) Scope: Drainage 120.00 m3 Result: 90.04 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.III 1 8.00 39.79 318.31 67.96
2 Helper I 1 8.00 18.76 150.06 32.04
3
4
Labour Sub-total 468.37 - 9.07
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 828.35 4,698.07 2,836.94 100.00
2
Equipment Sub-total 4,698.07 2,836.94 90.93
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
3
4
Material Sub-total - -
Total Cost per crew day 5,166.44 2,836.94

Average daily production (ADP) = 120.00 m3


Activity operational cost per crew day / ADP = 43.05 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 58.12 Birr/m3
Activity replacement cost per crew day / ADP = 23.64 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 31.92 Birr/m3
Total Activity Unit Rate = 90.04 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 40 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 31.01(b) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Open Drain Exc. (in Hard) (Extra-over) Scope: Drainage 100.00 m3 Result: 200.82 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For I 1 8.00 45.47 363.78 19.52
2 Equ.op.III 2 12.00 39.79 477.46 25.62
3 St.eq.opI 1 8.00 22.74 181.89 9.76
4 Labour I 4 32.00 12.62 403.80 21.67
5 Labour II 4 32.00 13.64 436.54 23.43
Labour Sub-total 1,863.47 - 16.39
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 49.42
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 17.95
3 Air Compressor 600CFM 8.00 377.78 18.65 396.43 3,022.22 149.20 31.79
4 Jack Hammer - 32.00 2.50 5.20 7.70 80.00 166.40 0.84
5 Hand Tools
Equipment Sub-total 9,507.32 3,505.04 83.61
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
3
4
Material Sub-total - -
Total Cost per crew day 11,370.79 3,505.04

Average daily production (ADP) = 100.00 m3


Activity operational cost per crew day / ADP = 113.71 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 153.51 Birr/m3
Activity replacement cost per crew day / ADP = 35.05 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 47.32 Birr/m3
Total Activity Unit Rate = 200.82 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 41 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 15.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Scope: Traffic Management 0.77 Result: 82,566.18 Birr/m3
* upto 2 Km free-haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 12.63
2 Equ.op.IV 3 16.01 102.31 1,637.94 35.00
3 Equ.op.II 2 10.00 28.42 284.20 6.07
4 Equ.op.III 3 16.07 39.79 639.21 13.66
5 Helper I 2 16.00 18.76 300.12 6.41
6 Labour I 10 80.00 12.62 1,009.49 21.57
7 Labour II 2 16.00 13.64 218.27 4.66
Labour Sub-total 4,680.38 16.02
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 52.73
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 27.58
3 Roller,Vibrator,2Drums 8 ton 10.00 478.94 281.42 760.36 4,789.41 2,814.17 19.52
4 Dump truck,6*4 (12m3) 12M3 0.06 481.75 104.04 585.79 28.32 6.12 0.12
5 Loader, Wheel 2-2.5 M3 0.01 591.65 496.23 1,087.88 3.80 3.18 0.02
6 Crawler Dozer 280-330 HP 0.01 1,334.09 746.61 2,080.71 11.98 6.70 0.05

Equipment Sub-total 6,686.56 24,540.44 17,872.48 83.98


Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 29,220.82 17,872.48

Average daily production (ADP) = 0.77


Activity operational cost per crew day / ADP = 37,949.12 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 51,231.31 Birr/m3
Activity replacement cost per crew day / ADP = 23,211.01 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 31,334.87 Birr/m3
Total Activity Unit Rate = 82,566.18 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 42 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.01(a) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Minor Structures Excavation (in Soft) Scope: Drainage 150.00 m3 Result: 105.01 Birr/m3
*0.5Km free-haul to waste
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 21.05
2 Equ.op.III 2 12.00 39.79 477.46 23.03
3 Helper I 1 8.00 18.76 150.06 7.24
4 Labour I 10 80.00 12.62 1,009.49 48.68
5
6
Labour Sub-total 2,073.56 - 24.46
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 73.35
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 26.65
3 Hand Tools
4
5
Equipment Sub-total 6,405.10 3,189.43 75.54
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 8,478.65 3,189.43

Average daily production (ADP) = 150.00 m3


Activity operational cost per crew day / ADP = 56.52 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 76.31 Birr/m3
Activity replacement cost per crew day / ADP = 21.26 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 28.70 Birr/m3
Total Activity Unit Rate = 105.01 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 43 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.01(b) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Scope: Drainage 90.00 m3 Result: 223.14 Birr/m3
Minor Structures Exc. (in Hard) (Extra-over)
*0.5Km free-haul to waste
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For I 1 8.00 45.47 363.78 19.52
2 Equ.op.III 2 12.00 39.79 477.46 25.62
3 St.eq.opI 1 8.00 22.74 181.89 9.76
4 Labour I 4 32.00 12.62 403.80 21.67
5 Labour II 4 32.00 13.64 436.54 23.43
Labour Sub-total 1,863.47 - 16.39
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 49.42
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 17.95
3 Air Compressor 600CFM 8.00 377.78 18.65 396.43 3,022.22 149.20 31.79
4 Jack Hammer - 32.00 2.50 5.20 7.70 80.00 166.40 0.84
5 Hand Tools
Equipment Sub-total 9,507.32 3,505.04 83.61
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
Material Sub-total - -
Total Cost per crew day 11,370.79 3,505.04

Average daily production (ADP) = 90.00 m3


Activity operational cost per crew day / ADP = 126.34 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 170.56 Birr/m3
Activity replacement cost per crew day / ADP = 38.94 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 52.58 Birr/m3
Total Activity Unit Rate = 223.14 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering 40% Loose factor for excavated material

Stadia Engineering Works Consultant Plc Page 44 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.02(a) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Scope: Drainage 70.00 m3 Result: 58.06 Birr/m3
Backfilling using the excavated material
*using the excavated material
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 6.05
2 Helper I 2 16.00 18.76 300.12 13.32
3 Labour I 18 144.00 12.62 1,817.09 80.63
4
5
Labour Sub-total 2,253.63 - 81.47
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Plate Compactor - 48.00 10.68 5.09 15.77 512.64 244.24 100.00
2 Hand Tools
3
Equipment Sub-total 15.77 512.64 244.24 18.53
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
3
Material Sub-total - -
Total Cost per crew day 2,766.27 244.24

Average daily production (ADP) = 70.00 m3


Activity operational cost per crew day / ADP = 39.52 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 53.35 Birr/m3
Activity replacement cost per crew day / ADP = 3.49 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 4.71 Birr/m3
Total Activity Unit Rate = 58.06 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 45 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.02(b) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Scope: Drainage 70.00 m3 Result: 138.98 Birr/m3
Backfilling using Imported selected material
*using imported material of 10 km free haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 5.85
2 Equ.op.III 1 2.00 39.79 79.58 3.41
3 Helper I 2 16.00 18.76 300.12 12.86
4 Labour I 18 144.00 12.62 1,817.09 77.88
5
6
Labour Sub-total 2,333.21 - 40.82
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 0.20 591.65 496.23 1,087.88 118.33 99.25 7.97
2 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 57.50
3 Plate Compactor - 48.00 10.68 5.09 15.77 512.64 244.24 34.53
4 Hand Tools
5
Equipment Sub-total 1,618.53 1,484.49 519.73 25.97
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Select Material m3 20.86 10.67 91.00 1,898.36 970.60 100.00
2
3
Material Sub-total 1,898.36 970.60 33.21
Total Cost per crew day 5,716.06 1,490.33

Average daily production (ADP) = 70.00 m3


Activity operational cost per crew day / ADP = 81.66 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 110.24 Birr/m3
Activity replacement cost per crew day / ADP = 21.29 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 28.74 Birr/m3
Total Activity Unit Rate = 138.98 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 46 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.03(a)(i) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: 36'' diameter R.C pipe installation on class A Scope: Drainage 11.00 Result: 3,160.08 Birr/m
Bedding

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 21.00
2 Mason I 2 16.00 22.17 354.69 17.06
3 Equ.op.III 1 7.00 39.79 278.52 13.40
4 Labour I 10 80.00 12.62 1,009.49 48.55
5
Labour Sub-total 2,079.24 - 9.08
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 63.41
2 Dump truck,6*4 (8m3) 8M3 3.00 426.76 88.12 514.88 1,280.27 264.37 34.30
3 Plate Compactor - 8.00 10.68 5.09 15.77 85.44 40.71 2.29
4
Equipment Sub-total 3,732.32 2,290.00 16.29
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 0.28 71.05 - 0.42
2 Sand m3 461.54 0.04 18.46 - 0.11
3 Class A Bedding m3 2,213.68 101.09 2.59 5,733.42 261.83 33.53
4 Pipes (Dia. 36) No 1,025.04 26.10 11.00 11,275.43 287.07 65.94
Material Sub-total 17,098.36 548.90 74.63
Total Cost per crew day 22,909.92 2,838.90

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 2,082.72 Birr/m
Total Oper. unit cost including 35% overhead & profit = 2,811.67 Birr/m
Activity replacement cost per crew day / ADP = 258.08 Birr/m
Total Repl. unit cost including 35% overhead & profit = 348.41 Birr/m
Total Activity Unit Rate = 3,160.08 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 18km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 47 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.03(a)(ii) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: 42'' diameter R.C pipe installation on class A Scope: Drainage 11.00 Result: 3,854.39 Birr/m
Bedding

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 18.33
2 Mason I 2 16.00 22.17 354.69 14.89
3 Equ.op.III 1 7.00 39.79 278.52 11.69
4 Labour I 13 104.00 12.62 1,312.34 55.09
5
Labour Sub-total 2,382.09 - 8.37
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 62.69
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.05
3 Plate Compactor - 8.00 10.68 5.09 15.77 85.44 40.71 2.26
4
Equipment Sub-total 3,774.99 2,298.81 13.27
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 0.35 88.81 - 0.40
2 Sand m3 461.54 0.05 23.08 - 0.10
3 Class A Bedding m3 2,213.68 101.09 3.15 6,973.08 318.44 31.27
4 Pipes (Dia. 42) No 1,383.21 30.14 11.00 15,215.28 331.53 68.23
Material Sub-total 22,300.26 649.97 78.36
Total Cost per crew day 28,457.34 2,948.78

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 2,587.03 Birr/m
Total Oper. unit cost including 35% overhead & profit = 3,492.49 Birr/m
Activity replacement cost per crew day / ADP = 268.07 Birr/m
Total Repl. unit cost including 35% overhead & profit = 361.90 Birr/m
Total Activity Unit Rate = 3,854.39 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 7.2km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 48 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.03(a)(iii) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: 48'' diameter R.C pipe installation on class A Scope: Drainage 11.00 Result: 4,806.76 Birr/m
Bedding

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 18.33
2 Mason I 2 16.00 22.17 354.69 14.89
3 Equ.op.III 1 7.00 39.79 278.52 11.69
4 Labour I 13 104.00 12.62 1,312.34 55.09
5
Labour Sub-total 2,382.09 - 6.60
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 62.69
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.05
3 Plate Compactor - 8.00 10.68 5.09 15.77 85.44 40.71 2.26
4
Equipment Sub-total 3,774.99 2,298.81 10.45
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 0.42 106.58 - 0.36
2 Sand m3 461.54 0.06 27.69 - 0.09
3 Class A Bedding m3 2,213.68 101.09 3.69 8,168.47 373.03 27.26
4 Pipes (Dia. 48) No 1,968.91 34.23 11.00 21,658.02 376.50 72.29
Material Sub-total 29,960.75 749.53 82.95
Total Cost per crew day 36,117.83 3,048.34

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 3,283.44 Birr/m
Total Oper. unit cost including 35% overhead & profit = 4,432.64 Birr/m
Activity replacement cost per crew day / ADP = 277.12 Birr/m
Total Repl. unit cost including 35% overhead & profit = 374.12 Birr/m
Total Activity Unit Rate = 4,806.76 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 7.2km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 49 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.03(b)(i) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: 36'' diameter R.C pipe installation on class B Scope: Drainage 11.00 Result: 2,450.02 Birr/m
Bedding

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 23.25
2 Mason I 2 16.00 22.17 354.69 18.89
3 Equ.op.III 1 7.00 39.79 278.52 14.84
4 Labour I 8 64.00 12.62 807.60 43.02
5
Labour Sub-total 1,877.34 - 10.88
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 63.96
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.75
3 Plate Compactor - 1.00 10.68 5.09 15.77 10.68 5.09 0.29
4
Equipment Sub-total 3,700.23 2,263.19 21.45
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 0.28 71.05 - 0.61
2 Sand m3 461.54 0.04 18.46 - 0.16
3 Select Material m3 20.86 10.67 14.92 311.25 159.14 2.67
4 Pipes (Dia. 36) No 1,025.04 26.10 11.00 11,275.43 287.07 96.57
Material Sub-total 11,676.19 446.20 67.67
Total Cost per crew day 17,253.76 2,709.40

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 1,568.52 Birr/m
Total Oper. unit cost including 35% overhead & profit = 2,117.51 Birr/m
Activity replacement cost per crew day / ADP = 246.31 Birr/m
Total Repl. unit cost including 35% overhead & profit = 332.52 Birr/m
Total Activity Unit Rate = 2,450.02 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 7.2km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 50 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.03(b)(ii) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: 42'' diameter R.C pipe installation on class B Scope: Drainage 11.00 Result: 2,639.89 Birr/m
Bedding

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 23.25
2 Mason I 2 16.00 22.17 354.69 18.89
3 Equ.op.III 1 7.00 39.79 278.52 14.84
4 Labour I 8 64.00 12.62 807.60 43.02
5
Labour Sub-total 1,877.34 - 10.02
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 63.96
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.75
3 Plate Compactor - 1.00 10.68 5.09 15.77 10.68 5.09 0.29
4
Equipment Sub-total 3,700.23 2,263.19 19.75
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 0.35 90.28 - 0.69
2 Sand m3 461.54 0.05 15.61 - 0.12
3 Select Material m3 20.86 10.67 16.77 23.19 178.87 0.18
4 Pipes (Dia. 42) No 1,383.21 30.14 11.00 13,029.94 331.53 99.02
Material Sub-total 13,159.02 510.40 70.23
Total Cost per crew day 18,736.59 2,773.59

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 1,703.33 Birr/m
Total Oper. unit cost including 35% overhead & profit = 2,299.49 Birr/m
Activity replacement cost per crew day / ADP = 252.14 Birr/m
Total Repl. unit cost including 35% overhead & profit = 340.40 Birr/m
Total Activity Unit Rate = 2,639.89 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 7.2km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 51 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.03(b)(iii) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: 48'' diameter R.C pipe installation on class B Scope: Drainage 11.00 m Result: 3,754.49 Birr/m
Bedding

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 23.25
2 Mason I 2 16.00 22.17 354.69 18.89
3 Equ.op.III 1 7.00 39.79 278.52 14.84
4 Labour I 8 64.00 12.62 807.60 43.02
5
Labour Sub-total 1,877.34 - 6.76
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 63.96
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.75
3 Plate Compactor - 1.00 10.68 5.09 15.77 10.68 5.09 0.29
4
Equipment Sub-total 3,700.23 2,263.19 13.33
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 0.42 106.58 - 0.48
2 Sand m3 461.54 0.06 27.69 - 0.12
3 Select Material m3 20.86 10.67 18.48 385.51 197.11 1.74
4 Pipes (Dia. 48) No 1,968.91 34.23 11.00 21,658.02 376.50 97.66
Material Sub-total 22,177.80 573.61 79.90
Total Cost per crew day 27,755.37 2,836.80

Average daily production (ADP) = 11.00 m


Activity operational cost per crew day / ADP = 2,523.22 Birr/m
Total Oper. unit cost including 35% overhead & profit = 3,406.34 Birr/m
Activity replacement cost per crew day / ADP = 257.89 Birr/m
Total Repl. unit cost including 35% overhead & profit = 348.15 Birr/m
Total Activity Unit Rate = 3,754.49 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 13.26km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 52 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.16(a) Category: Labour intensive ADP= March 21, 2017
Activity Name: Service Duct using ordinary pipes (150mm Scope: Drainage 20.00 m Result: 288.04 Birr/m
diameter steel pipes)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason I 1 8.00 22.17 177.34 42.32
2 Equ.op.III 1 1.00 39.79 39.79 9.50
3 Labour I 2 16.00 12.62 201.90 48.18
Labour Sub-total 419.03 - 10.03
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total 514.88 426.76 88.12 10.21
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Steel Pipes (Dia. 150mm) No 1,000.00 3.33 3,333.33 - 100.00
2
Material Sub-total 3,333.33 - 79.76
Total Cost per crew day 4,179.12 88.12

Average daily production (ADP) = 20.00 m


Activity operational cost per crew day / ADP = 208.96 Birr/m
Total Oper. unit cost including 35% overhead & profit = 282.09 Birr/m
Activity replacement cost per crew day / ADP = 4.41 Birr/m
Total Repl. unit cost including 35% overhead & profit = 5.95 Birr/m
Total Activity Unit Rate = 288.04 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 53 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.16(b) Category: Labour intensive ADP= March 21, 2017
Activity Name: Service Duct using split pipes (150mm diameter Scope: Drainage 20.00 Result: 468.04 Birr/m
steel pipes)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason I 1 8.00 22.17 177.34 42.32
2 Equ.op.III 1 1.00 39.79 39.79 9.50
3 Labour I 2 16.00 12.62 201.90 48.18
Labour Sub-total 419.03 - 6.12
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total 514.88 426.76 88.12 6.23
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Split Pipes (Dia. 150mm) No 1,800.00 3.33 6,000.00 - 100.00
2
Material Sub-total 6,000.00 - 87.65
Total Cost per crew day 6,845.79 88.12

Average daily production (ADP) = 20.00


Activity operational cost per crew day / ADP = 342.29 Birr/m
Total Oper. unit cost including 35% overhead & profit = 462.09 Birr/m
Activity replacement cost per crew day / ADP = 4.41 Birr/m
Total Repl. unit cost including 35% overhead & profit = 5.95 Birr/m
Total Activity Unit Rate = 468.04 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 54 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.17 Category: Labour intensive ADP= March 21, 2017
Activity Name: Duct marker blocks Scope: Drainage 20.00 No. Result: 711.70 Birr/each
*including class C-concrete footing
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 6.54
2 Labour I 15 120.00 12.62 1,514.24 72.63
3 Mason I 2 16.00 22.17 354.69 17.01
4 Equ.op.III 1 2.00 39.79 79.58 3.82
5
6
Labour Sub-total 2,084.92 - 21.35
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 41.90
2 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 58.10
3 Hand Tools
4
Equipment Sub-total 1,018.41 584.35 10.43
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 1.32 607.17 9.11
2 Cement Quintal 255.78 9.21 2,355.40 35.35
3 Crushed Aggregate M3 243.73 84.20 1.75 427.52 147.70 6.42
4 Duct marker blocks No 163.61 2.31 20.00 3,272.16 46.11 49.12

Material Sub-total 6,662.24 193.81 68.22


Total Cost per crew day 9,765.57 778.16

Average daily production (ADP) = 20.00 No.


Activity operational cost per crew day / ADP = 488.28 Birr/each
Total Oper. unit cost including 35% overhead & profit = 659.18 Birr/each
Activity replacement cost per crew day / ADP = 38.91 Birr/each
Total Repl. unit cost including 35% overhead & profit = 52.53 Birr/each
Total Activity Unit Rate = 711.70 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 55 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 32.18 Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Chambers for ducts Scope: Drainage 7.00 Result: 9,791.11 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 9.36
2 Driver III 1 2.50 36.38 90.95 1.95
3 St.eq.opI 1 8.00 22.74 181.89 3.90
4 Mason I 2 16.00 22.17 354.69 7.60
5 Carpenter I 2 16.00 40.93 654.81 14.04
6 Carpenter II 1 8.00 54.57 436.54 9.36
7 Labour I 20 160.00 12.62 2,018.99 43.27
8 Bar Sett.I 2 16.00 30.69 491.11 10.53
Labour Sub-total 4,665.50 - 9.50
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 60.36
2 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 19.30
3 Concrete Vibrator 5 HP 16.00 22.48 2.43 24.91 359.66 38.95 20.35
4 Hand Tools
5
Equipment Sub-total 1,767.68 325.47 3.60
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 4.49 2,073.18 4.86
2 Cement Quintal 255.78 40.43 10,340.44 24.22
3 Crushed Aggregate M3 243.73 84.20 6.74 1,642.23 567.35 3.85
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.28 5,296.77 12.41
5 Formwork m2 172.07 5.51 135.66 23,342.94 747.17 54.67
6
Material Sub-total 42,695.57 1,314.52 86.91
Total Cost per crew day 49,128.76 1,639.99

Average daily production (ADP) = 7.00


Activity operational cost per crew day / ADP = 7,018.39 Birr/each
Total Oper. unit cost including 35% overhead & profit = 9,474.83 Birr/each
Activity replacement cost per crew day / ADP = 234.28 Birr/each
Total Repl. unit cost including 35% overhead & profit = 316.28 Birr/each
Total Activity Unit Rate = 9,791.11 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 56 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 33.01(a)(i) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Class 25/20 Concrete Curbing (size .45m X . Scope: Drainage 155.00 m Result: 400.14 Birr/m
17m)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8
Labour Sub-total 4,174.40 - 9.43
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total 1,928.98 372.20 4.36
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 4.19 1,931.54 5.06
2 Cement Quintal 255.78 41.85 10,704.39 28.04
3 Crushed Aggregate M3 243.73 84.20 6.28 1,530.03 528.59 4.01
4 Formwork m2 172.07 5.51 139.50 24,003.68 768.32 62.89
5
6
Material Sub-total 38,169.65 1,296.91 86.21
Total Cost per crew day 44,273.02 1,669.10

Average daily production (ADP) = 155.00 m


Activity operational cost per crew day / ADP = 285.63 Birr/m
Total Oper. unit cost including 35% overhead & profit = 385.60 Birr/m
Activity replacement cost per crew day / ADP = 10.77 Birr/m
Total Repl. unit cost including 35% overhead & profit = 14.54 Birr/m
Total Activity Unit Rate = 400.14 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 57 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 33.01(a)(ii) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Class 25/20 Concrete Curbing (size .20m X . Scope: Drainage 240.00 m Result: 251.09 Birr/m
25m)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8
Labour Sub-total 4,174.40 - 9.71
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total 1,928.98 372.20 4.49
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 4.80 2,215.38 6.00
2 Cement Quintal 255.78 48.00 12,277.44 33.28
3 Crushed Aggregate M3 243.73 84.20 7.20 1,754.87 606.27 4.76
4 Formwork m2 172.07 5.51 120.00 20,648.33 660.92 55.96
5
6
Material Sub-total 36,896.03 1,267.19 85.81
Total Cost per crew day 42,999.41 1,639.38

Average daily production (ADP) = 240.00 m


Activity operational cost per crew day / ADP = 179.16 Birr/m
Total Oper. unit cost including 35% overhead & profit = 241.87 Birr/m
Activity replacement cost per crew day / ADP = 6.83 Birr/m
Total Repl. unit cost including 35% overhead & profit = 9.22 Birr/m
Total Activity Unit Rate = 251.09 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 58 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 33.03(a) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Concrete Chute (Class 20/20) including Scope: Drainage 100.00 Result: 493.50 Birr/m
Formwork

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8 -
Labour Sub-total 4,174.40 - 11.73
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total 1,928.98 372.20 5.42
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 4.80 2,215.38 7.52
2 Cement Quintal 255.78 43.20 11,049.70 37.49
3 Crushed Aggregate M3 243.73 84.20 7.20 1,754.87 606.27 5.95
4 Formwork m2 172.07 5.51 84.00 14,453.83 49.04
5 - -
6
Material Sub-total 29,473.79 606.27 82.84
Total Cost per crew day 35,577.16 978.46

Average daily production (ADP) = 100.00


Activity operational cost per crew day / ADP = 355.77 Birr/m
Total Oper. unit cost including 35% overhead & profit = 480.29 Birr/m
Activity replacement cost per crew day / ADP = 9.78 Birr/m
Total Repl. unit cost including 35% overhead & profit = 13.21 Birr/m
Total Activity Unit Rate = 493.50 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 59 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 33.09(a) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Concrete lining (Class 20/20) including Scope: Drainage 12.00 Result: 2,883.21 Birr/m3
Formwork

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 9.36
2 Driver III 1 2.50 36.38 90.95 1.95
3 St.eq.opI 1 8.00 22.74 181.89 3.90
4 Mason I 2 16.00 22.17 354.69 7.60
5 Carpenter I 2 16.00 40.93 654.81 14.04
6 Carpenter II 1 8.00 54.57 436.54 9.36
7 Labour I 20 160.00 12.62 2,018.99 43.27
8 Bar Sett.I 2 16.00 30.69 491.11 10.53
Labour Sub-total 4,665.50 - 18.84
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total 1,928.98 372.20 7.79
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 1.91 880.62 4.85
2 Cement Quintal 255.78 17.17 4,392.25 24.18
3 Crushed Aggregate M3 243.73 84.20 2.86 697.56 240.99 3.84
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.22 4,139.83 22.79
5 Formwork m2 172.07 5.51 46.80 8,052.85 257.76 44.34
6
Material Sub-total 18,163.11 498.75 73.36
Total Cost per crew day 24,757.60 870.95

Average daily production (ADP) = 12.00


Activity operational cost per crew day / ADP = 2,063.13 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,785.23 Birr/m3
Activity replacement cost per crew day / ADP = 72.58 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 97.98 Birr/m3
Total Activity Unit Rate = 2,883.21 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 60 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 33.17(b)(i) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Pedestrian drain covers (Class 25/20 - Scope: Drainage 30.00 No. Result: 998.70 Birr/each
1.4mX1.2mX0.15m)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carpenter I 1 8.00 40.93 327.40 10.22
2 Bar Sett.I 1 8.00 30.69 245.55 7.67
3 Labour I 5 40.00 12.62 504.75 15.76
4 Labor Foreman 1 8.00 17.05 136.42 4.26
5 Labour I 15 120.00 12.62 1,514.24 47.28
6 Mason I 2 16.00 22.17 354.69 11.08
7 Equ.op.III 1 3.00 39.79 119.37 3.73
8
Labour Sub-total 3,202.42 - 15.21
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 17.35
2 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.15
3 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 43.41
4 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 30.09
5 Hand Tools
Equipment Sub-total 1,966.12 758.16 9.34
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 3.02 1,395.69 8.79
2 Cement Quintal 255.78 27.22 6,961.31 43.82
3 Crushed Aggregate M3 243.73 84.20 4.54 1,105.57 381.95 6.96
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.32 6,071.14 38.22
5 Lumber m3 10,000.00 0.04 351.00 2.21
6
Material Sub-total 15,884.72 381.95 75.45
Total Cost per crew day 21,053.26 1,140.11

Average daily production (ADP) = 30.00 No.


Activity operational cost per crew day / ADP = 701.78 Birr/each
Total Oper. unit cost including 35% overhead & profit = 947.40 Birr/each
Activity replacement cost per crew day / ADP = 38.00 Birr/each
Total Repl. unit cost including 35% overhead & profit = 51.30 Birr/each
Total Activity Unit Rate = 998.70 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling
* Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 61 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 33.17(b)(ii) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Pedestrian drain covers (Class 25/20 - Scope: Drainage 30.00 Result: 1,102.23 Birr/each
1.6mX1.2mX0.15m)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carpenter I 1 8.00 40.93 327.40 10.22
2 Bar Sett.I 1 8.00 30.69 245.55 7.67
3 Labour I 5 40.00 12.62 504.75 15.76
4 Labor Foreman 1 8.00 17.05 136.42 4.26
5 Labour I 15 120.00 12.62 1,514.24 47.28
6 Mason I 2 16.00 22.17 354.69 11.08
7 Equ.op.III 1 3.00 39.79 119.37 3.73
8
Labour Sub-total 3,202.42 - 13.74
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 17.35
2 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.15
3 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 43.41
4 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 30.09
5 Hand Tools
Equipment Sub-total 1,966.12 758.16 8.44
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 3.46 1,595.08 8.80
2 Cement Quintal 255.78 31.10 7,955.78 43.88
3 Crushed Aggregate M3 243.73 84.20 5.18 1,263.51 436.51 6.97
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.36 6,938.45 38.27
5 Lumber m3 10,000.00 0.04 378.00 2.08
6
Material Sub-total 18,130.82 436.51 77.82
Total Cost per crew day 23,299.36 1,194.67

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 776.65 Birr/each
Total Oper. unit cost including 35% overhead & profit = 1,048.47 Birr/each
Activity replacement cost per crew day / ADP = 39.82 Birr/each
Total Repl. unit cost including 35% overhead & profit = 53.76 Birr/each
Total Activity Unit Rate = 1,102.23 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling
* Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 62 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 33.17(b)(iii) Category: Mechanized+Labour intensive ADP= March 21, 2017
Activity Name: Vehicle drain covers (Class 25/20 Scope: Drainage 30.00 No. Result: 1,666.95 Birr/each
-1.6mX1.2mX0.20m)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carpenter I 1 8.00 40.93 327.40 10.22
2 Bar Sett.I 1 8.00 30.69 245.55 7.67
3 Labour I 5 40.00 12.62 504.75 15.76
4 Labor Foreman 1 8.00 17.05 136.42 4.26
5 Labour I 15 120.00 12.62 1,514.24 47.28
6 Mason I 2 16.00 22.17 354.69 11.08
7 Equ.op.III 1 3.00 39.79 119.37 3.73
8
Labour Sub-total 3,202.42 - 8.97
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 17.35
2 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.15
3 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 43.41
4 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 30.09
5 Hand Tools
Equipment Sub-total 1,966.12 758.16 5.51
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 4.61 2,126.77 6.97
2 Cement Quintal 255.78 41.47 10,607.71 34.74
3 Crushed Aggregate M3 243.73 84.20 6.91 1,684.68 582.02 5.52
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.82 15,611.51 51.13
5 Lumber m3 10,000.00 0.05 504.00 1.65
6
Material Sub-total 30,534.67 582.02 85.52
Total Cost per crew day 35,703.21 1,340.18

Average daily production (ADP) = 30.00 No.


Activity operational cost per crew day / ADP = 1,190.11 Birr/each
Total Oper. unit cost including 35% overhead & profit = 1,606.64 Birr/each
Activity replacement cost per crew day / ADP = 44.67 Birr/each
Total Repl. unit cost including 35% overhead & profit = 60.31 Birr/each
Total Activity Unit Rate = 1,666.95 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling
* Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 63 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 34.01(b)(i) Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Drainage 50.00 m2 Result: 248.45 Birr/m2
Stone Pitching for outlet & inlet of culverts
m2
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason II 1 8.00 32.40 259.19 9.59
2 Driver III 1 4.00 36.38 145.51 5.39
3 Mason I 4 32.00 22.17 709.37 26.25
4 Labour III 8 64.00 15.35 982.21 36.35
5 Labour I 6 48.00 12.62 605.70 22.42
6
Labour Sub-total 2,701.99 - 32.63
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 3.00 481.75 104.04 585.79 1,445.25 312.11 77.36
2 Water truck,6*4 20000Lits 1.00 422.98 145.63 568.61 422.98 145.63 22.64
3 Hand Tools
Equipment Sub-total 1,154.39 1,868.23 457.74 22.56
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 6.00 1,534.68 - 41.35
2 Sand m3 461.54 1.50 692.31 - 18.65
3 Stone M3 106.02 33.03 14.00 1,484.35 462.45 40.00
Material Sub-total 3,711.34 462.45 44.81
Total Cost per crew day 8,281.56 920.19

Average daily production (ADP) = 50.00 m2


Activity operational cost per crew day / ADP = 165.63 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 223.60 Birr/m2
Activity replacement cost per crew day / ADP = 18.40 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 24.85 Birr/m2
Total Activity Unit Rate = 248.45 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 20 km free haul of masonry stone

Stadia Engineering Works Consultant Plc Page 64 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 34.03(b) Category: Labour intensive ADP= March 21, 2017
Activity Name: Cement-mortared stone walls Scope: Drainage 8.00 m3 Result: 1,608.20 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 4.00 54.57 218.27 7.95
2 Equ.op.III 1 3.00 39.79 119.37 4.35
3 Mason I 5 40.00 22.17 886.72 32.30
4 Carpenter II 1 4.00 54.57 218.27 7.95
5 Labour II 5 40.00 13.64 545.67 19.88
6 Labour I 8 60.00 12.62 757.12 27.58
Labour Sub-total 2,745.42 - 32.37
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 2.00 481.75 104.04 585.79 963.50 208.07 61.96
2 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 38.04
3 Hand Tools
Equipment Sub-total 1,673.67 1,555.15 704.31 18.33
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 8.40 2,148.55 - 51.38
2 Sand m3 461.54 2.02 930.46 - 22.25
3 Stone M3 106.02 33.03 10.40 1,102.66 343.53 26.37
Material Sub-total 4,181.67 343.53 49.30
Total Cost per crew day 8,482.24 1,047.84

Average daily production (ADP) = 8.00 m3


Activity operational cost per crew day / ADP = 1,060.28 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 1,431.38 Birr/m3
Activity replacement cost per crew day / ADP = 130.98 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 176.82 Birr/m3
Total Activity Unit Rate = 1,608.20 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering 20 km free haul distance for masonry stone

Stadia Engineering Works Consultant Plc Page 65 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 34.04(c) Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Drainage 96.00 m2 Result: 590.61 Birr/each
Pre-cast concrete blocks for side walk pavement

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 5.33
2 Labour I 8 64.00 12.62 807.60 31.53
3 Mason I 8 64.00 22.17 1,418.75 55.38
4 Equ.op.III 1 5.00 39.79 198.94 7.77
5 -
6 -
Labour Sub-total 2,561.71 - 6.23
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 74.26
2 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 25.74
3 Hand Tools - -
4 - -
5
Equipment Sub-total 2,298.68 848.72 5.59
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 12.48 5,760.00 15.87
2 Cement Quintal 255.78 16.90 4,321.66 11.91

3 300x300x60mm Pre-colored concrete block m2 273.00 - 96.00 26,208.00 - 72.22


4 -
5 -
6
Material Sub-total 36,289.66 - 88.19
Total Cost per crew day 41,150.05 848.72

Average daily production (ADP) = 96.00 m2


Activity operational cost per crew day / ADP = 428.65 Birr/each
Total Oper. unit cost including 35% overhead & profit = 578.67 Birr/each
Activity replacement cost per crew day / ADP = 8.84 Birr/each
Total Repl. unit cost including 35% overhead & profit = 11.94 Birr/each
Total Activity Unit Rate = 590.61 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling
* Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 66 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 41.01(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Removal of unsuitable material and Scope: Earth Work 585.67 m3 Result: 79.80 Birr/m3
replacement with suitable material
* including 0.5 Km free haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 24.30
2 Equ.op.IV 1 8.00 102.31 818.51 33.64
3 Equ.op.III 3 22.97 39.79 914.08 37.57
4 Labour II 1 8.00 13.64 109.13 4.49
5
Labour Sub-total 2,432.87 9.88
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 48.08
2 Dump truck,6*4 (12m3) 12M3 18.83 481.75 104.04 585.79 9,068.94 1,958.50 40.86
3 Loader, Wheel 2-2.5 M3 4.15 591.65 496.23 1,087.88 2,454.45 2,058.60 11.06
4
5
Equipment Sub-total 3,754.38 22,196.14 9,990.01 90.12
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 24,629.01 9,990.01

Average daily production (ADP) = 585.67 m3


Activity operational cost per crew day / ADP = 42.05 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 56.77 Birr/m3
Activity replacement cost per crew day / ADP = 17.06 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 23.03 Birr/m3
Total Activity Unit Rate = 79.80 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering 40% loose factor

Stadia Engineering Works Consultant Plc Page 67 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 41.02 Category: Mechanized ADP= March 21, 2017
Activity Name: Road bed preparation and compaction Scope: Earth Work 586.00 m3 Result: 55.76 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 26.08
2 Equ.op.IV 1 8.00 102.31 818.51 36.11
3 Equ.op.III 1 8.00 39.79 318.31 14.04
4 Equ.op.II 1 6.00 28.42 170.52 7.52
5 Helper I 1 8.00 18.76 150.06 6.62
7 Labour II 2 16.00 13.64 218.27 9.63
Labour Sub-total 2,266.82 - 15.12
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Motor Grader 145-165 HP 8.00 808.70 794.52 1,603.22 6,469.63 6,356.13 50.83
2 Roller,Vibrator,2Drums 8 ton 6.00 478.94 281.42 760.36 2,873.64 1,688.50 22.58
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 26.59
4
5
Equipment Sub-total 2,932.19 12,727.11 9,209.65 84.88
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 14,993.93 9,209.65

Average daily production (ADP) = 586.00 m3


Activity operational cost per crew day / ADP = 25.59 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 34.54 Birr/m3
Activity replacement cost per crew day / ADP = 15.72 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 21.22 Birr/m3
Total Activity Unit Rate = 55.76 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *The grader scarifies 15cm of road bed material after top soil removal & place it again

Stadia Engineering Works Consultant Plc Page 68 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 42.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Cut to fill Scope: Earth Work 1,200.00 m3 Result: 129.45 Birr/m3
* upto 2 Km free-haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 7.23
2 Equ.op.IV 4 29.99 102.31 3,068.81 37.54
3 Equ.op.II 2 10.00 28.42 284.20 3.48
4 Equ.op.III 9 67.90 39.79 2,701.84 33.05
5 Helper I 2 16.00 18.76 300.12 3.67
6 Labour I 10 80.00 12.62 1,009.49 12.35
7 Labour II 2 16.00 13.64 218.27 2.67
Labour Sub-total 8,173.88 10.55
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 18.68
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 9.77
3 Roller,Vibrator,2Drums 8 ton 10.00 478.94 281.42 760.36 4,789.41 2,814.17 6.91
4 Dump truck,6*4 (12m3) 12M3 41.90 481.75 104.04 585.79 20,187.61 4,359.66 29.14
5 Loader, Wheel 2-2.5 M3 10.00 591.65 496.23 1,087.88 5,916.51 4,962.32 8.54
6 Crawler Dozer 280-330 HP 13.99 1,334.09 746.61 2,080.71 18,669.53 10,448.24 26.95

Equipment Sub-total 6,686.56 69,269.99 37,626.69 89.45


Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 77,443.88 37,626.69

Average daily production (ADP) = 1,200.00 m3


Activity operational cost per crew day / ADP = 64.54 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 87.12 Birr/m3
Activity replacement cost per crew day / ADP = 31.36 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 42.33 Birr/m3
Total Activity Unit Rate = 129.45 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 69 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 42.01(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Borrow to fill Scope: Earth Work 1,200.00 m3 Result: 164.44 Birr/m3
* upto 2 Km free-haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 5.82
2 Equ.op.IV 4 29.99 102.31 3,068.81 30.23
3 Equ.op.II 2 10.00 28.42 284.20 2.80
4 Equ.op.III 15 117.62 39.79 4,679.90 46.10
5 Helper I 2 16.00 18.76 300.12 2.96
6 Labour I 10 80.00 12.62 1,009.49 9.94
7 Labour II 2 16.00 13.64 218.27 2.15
Labour Sub-total 10,151.95 9.82
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 13.88
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 7.26
3 Roller,Vibrator,2Drums 8 ton 10.00 478.94 281.42 760.36 4,789.41 2,814.17 5.14
4 Dump truck,6*4 (12m3) 12M3 91.62 481.75 104.04 585.79 44,137.46 9,531.80 47.35
5 Loader, Wheel 2-2.5 M3 10.00 591.65 496.23 1,087.88 5,916.51 4,962.32 6.35
6 Crawler Dozer 280-330 HP 13.99 1,334.09 746.61 2,080.71 18,669.53 10,448.24 20.03

Equipment Sub-total 6,686.56 93,219.84 42,798.83 90.18


Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 103,371.79 42,798.83

Average daily production (ADP) = 1,200.00 m3


Activity operational cost per crew day / ADP = 86.14 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 116.29 Birr/m3
Activity replacement cost per crew day / ADP = 35.67 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 48.15 Birr/m3
Total Activity Unit Rate = 164.44 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 70 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 42.01(c) Category: Mechanized ADP= March 21, 2017
Activity Name: Rock fill Scope: Earth Work 685.00 m3 Result: 294.17 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 4.00 73.89 295.57 6.00
2 Equ.op.IV 1 8.00 102.31 818.51 16.63
3 Equ.op.II 1 8.00 28.42 227.36 4.62
4 Equ.op.III 8 57.10 39.79 2,271.81 46.15
5 Helper I 2 16.00 18.76 300.12 6.10
6 Labour I 10 80.00 12.62 1,009.49 20.51
Labour Sub-total 4,922.87 4.36
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 25.09
2 Water truck,6*4 20000Lits - 422.98 145.63 568.61 - -
3 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 9.01
4 Dump truck,6*4 (12m3) 12M3 52.24 481.75 104.04 585.79 25,168.94 5,435.41 59.16
5 Loader, Wheel 2-2.5 M3 4.85 591.65 496.23 1,087.88 2,870.74 2,407.76 6.75
Equipment Sub-total 5,083.34 42,543.96 16,067.41 37.71
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Rock Excavation M3 106.02 33.03 616.50 65,364.40 20,364.34 100.00
2
3
Material Sub-total 65,364.40 20,364.34 57.93
Total Cost per crew day 112,831.22 36,431.75

Average daily production (ADP) = 685.00 m3


Activity operational cost per crew day / ADP = 164.72 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 222.37 Birr/m3
Activity replacement cost per crew day / ADP = 53.19 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 71.80 Birr/m3
Total Activity Unit Rate = 294.17 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 71 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 42.01(d) Category: Mechanized ADP= March 21, 2017
Activity Name: Improved subgrade Scope: Earth Work 980.00 m3 Result: 176.32 Birr/m3
* upto 2 Km free-haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 6.46
2 Equ.op.IV 4 27.43 102.31 2,806.32 30.68
3 Equ.op.II 2 10.00 28.42 284.20 3.11
4 Equ.op.III 13 98.99 39.79 3,938.63 43.05
5 Helper I 2 16.00 18.76 300.12 3.28
6 Labour I 10 80.00 12.62 1,009.49 11.03
7 Labour II 2 16.00 13.64 218.27 2.39
Labour Sub-total 9,148.18 10.19
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 16.05
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 8.39
3 Roller,Vibrator,2Drums 8 ton 10.00 478.94 281.42 760.36 4,789.41 2,814.17 5.94
4 Dump truck,6*4 (12m3) 12M3 74.82 481.75 104.04 585.79 36,045.59 7,784.30 44.71
5 Loader, Wheel 2-2.5 M3 8.17 591.65 496.23 1,087.88 4,831.82 4,052.56 5.99
6 Crawler Dozer 280-330 HP 11.43 1,334.09 746.61 2,080.71 15,246.78 8,532.73 18.91

Equipment Sub-total 6,686.56 80,620.53 38,226.06 89.81


Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 89,768.72 38,226.06

Average daily production (ADP) = 980.00 m3


Activity operational cost per crew day / ADP = 91.60 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 123.66 Birr/m3
Activity replacement cost per crew day / ADP = 39.01 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 52.66 Birr/m3
Total Activity Unit Rate = 176.32 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 72 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 42.03(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Common (normal) excavation Scope: Earth Work 1,120.00 m3 Result: 80.87 Birr/m3
* upto 0.5 Km free-haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 14.47
2 Equ.op.IV 2 16.00 102.31 1,637.02 40.07
3 Equ.op.III 6 43.93 39.79 1,748.05 42.79
4 Labour II 1 8.00 13.64 109.13 2.67
Labour Sub-total 4,085.35 8.61
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 16.00 1,334.09 746.61 2,080.71 21,345.50 11,945.82 49.20
2 Dump truck,6*4 (12m3) 12M3 36.00 481.75 104.04 585.79 17,342.99 3,745.34 39.98
3 Loader, Wheel 2-2.5 M3 7.93 591.65 496.23 1,087.88 4,693.76 3,936.77 10.82
4
5
Equipment Sub-total 3,754.38 43,382.25 19,627.93 91.39
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 47,467.60 19,627.93

Average daily production (ADP) = 1,120.00 m3 Weighted Rate for Cut to Spoil in any Material
Activity operational cost per crew day / ADP = 42.38 Birr/m3 Soft Excavation Quantity 128,947.12
Total Oper. unit cost including 35% overhead & profit = 57.22 Birr/m3 Hard Excavation Quantity 1,667,554.71
Activity replacement cost per crew day / ADP = 17.52 Birr/m3 Total Excavation Quantity 1,796,501.83
Total Repl. unit cost including 35% overhead & profit = 23.66 Birr/m3 Weighted Rate 201.78
Total Activity Unit Rate = 80.87 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 73 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 42.03(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Rock excavation Scope: Earth Work 400.00 m3 Result: 211.13 Birr/m3
* including 0.5 Km free haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Quarry Foreman 1 8.00 56.84 454.73 9.86
2 Equ.op.IV 1 8.00 102.31 818.51 17.75
3 Equ.op.III 4 25.91 39.79 1,031.03 22.36
5 St.eq.opI 1 8.00 22.74 181.89 3.94
6 Powder Man I 1 8.00 30.69 245.55 5.32
7 Helper I 3 24.00 18.76 450.18 9.76
8 Labour II 2 16.00 13.64 218.27 4.73
9 Labour I 12 96.00 12.62 1,211.39 26.27
Labour Sub-total 4,611.55 9.50
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 37.42
2 Air Compressor 600CFM 8.00 377.78 18.65 396.43 3,022.22 149.20 10.60
3 Jack Hammer - 24.00 2.50 5.20 7.70 60.00 124.80 0.21
4 Drill, Self Prop, Crawler Type 4500 Kg 8.00 727.88 599.01 1,326.89 5,823.07 4,792.06 20.42
5 Loader, Wheel 2-2.5 M3 2.83 591.65 496.23 1,087.88 1,676.34 1,405.99 5.88
6 Dump truck,6*4 (12m3) 12M3 15.08 481.75 104.04 585.79 7,264.48 1,568.82 25.47
7 Hand Tools
Equipment Sub-total 5,485.40 28,518.87 14,013.78 58.75
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Ammonium Nitrate Kg 60.00 150.00 9,000.00 58.39
2 Power Jell Kg 90.00 1.88 168.75 1.09
3 Electrical Detonator No 65.00 13.00 845.00 5.48
4 Cord m 16.00 150.00 2,400.00 15.57
5 Connecting wire m 12.00 250.00 3,000.00 19.46
6 Bits & Drills
Material Sub-total 15,413.75 - 31.75
Total Cost per crew day 48,544.17 14,013.78

Average daily production (ADP) = 400.00 m3


Activity operational cost per crew day / ADP = 121.36 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 163.84 Birr/m3
Activity replacement cost per crew day / ADP = 35.03 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 47.30 Birr/m3
Total Activity Unit Rate = 211.13 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 74 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 43.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Reinstatement of rock (hard) material borrow Scope: Earth Work 0.350 Result: 69,004.36 Birr/ha
areas

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 1.00 73.89 73.89 5.94
2 Equ.op.IV 1 8.00 102.31 818.51 65.78
3 Helper I 1 8.00 18.76 150.06 12.06
4 Labour I 2 16.00 12.62 201.90 16.23
5 -
6 -
Labour Sub-total 1,244.36 10.44
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 100.00
2 - -
3 - -
4 - -
5 - -
Equipment Sub-total 2,080.71 10,672.75 5,972.91 89.56
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 - -
2
3
Material Sub-total - -
Total Cost per crew day 11,917.11 5,972.91

Average daily production (ADP) = 0.35


Activity operational cost per crew day / ADP = 34,048.89 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 45,965.99 Birr/ha
Activity replacement cost per crew day / ADP = 17,065.45 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 23,038.36 Birr/ha
Total Activity Unit Rate = 69,004.36 Birr/ha

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 75 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 43.01(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Reinstatement of common (normal or soft) Scope: Earth Work 0.500 Result: 47,757.92 Birr/ha
material borrow areas

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 1.00 73.89 73.89 7.09
2 Equ.op.IV 1 8.00 102.31 818.51 78.52
3 Helper I 1 8.00 18.76 150.06 14.39
4 -
5 -
6 -
Labour Sub-total 1,042.46 8.90
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 100.00
2 - -
3 - -
4 - -
5 - -
Equipment Sub-total 2,080.71 10,672.75 5,972.91 91.10
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 - -
2
3
Material Sub-total - -
Total Cost per crew day 11,715.21 5,972.91

Average daily production (ADP) = 0.50


Activity operational cost per crew day / ADP = 23,430.42 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 31,631.07 Birr/ha
Activity replacement cost per crew day / ADP = 11,945.82 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 16,126.85 Birr/ha
Total Activity Unit Rate = 47,757.92 Birr/ha

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 76 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 44.04 Category: Mechanized ADP= March 21, 2017
Activity Name: Side fills or Fill-flattening Scope: Earth Work 1,200.00 Result: 61.32 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 15.32
2 Equ.op.IV 3 24.00 102.31 2,455.53 63.63
3 Equ.op.II 1 5.00 28.42 142.10 3.68
4 Equ.op.III 1 8.00 39.79 318.31 8.25
5 Helper I 1 8.00 18.76 150.06 3.89
6 Labour I 2 16.00 12.62 201.90 5.23
7 -
Labour Sub-total 3,859.04 11.61
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 44.03
2 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 11.51
3 Roller,Vibrator,2Drums 8 ton 5.00 478.94 281.42 760.36 2,394.70 1,407.09 8.15
4 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 36.31
5 - -
6 - -

Equipment Sub-total 5,012.89 29,390.55 21,257.27 88.39


Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 33,249.60 21,257.27

Average daily production (ADP) = 1,200.00


Activity operational cost per crew day / ADP = 27.71 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 37.41 Birr/m3
Activity replacement cost per crew day / ADP = 17.71 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 23.91 Birr/m3
Total Activity Unit Rate = 61.32 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 77 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 51.01(a)(i) Category: Mechanized ADP= March 21, 2017
Activity Name: Gravel Sub-base Scope: Pavement 480.00 m3 Result: 262.35 Birr/m3
* 8 km free-haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 9.54
2 Equ.op.IV 2 16.00 102.31 1,637.02 26.43
3 Equ.op.III 7 55.31 39.79 2,200.88 35.54
4 Equ.op.II 2 16.00 28.42 454.73 7.34
5 Helper I 2 16.00 18.76 300.12 4.85
6 Labour I 10 80.00 12.62 1,009.49 16.30
Labour Sub-total 6,193.39 - 9.84
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 35.31 481.75 104.04 585.79 17,012.65 3,674.00 36.39
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 14.48
3 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 27.68
4 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 5.06
5 Roller,Vibrator,2Drums 8 ton 16.00 478.94 281.42 760.36 7,663.05 4,502.67 16.39
6
Equipment Sub-total 4,605.85 46,749.24 25,203.91 74.26
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Select Material m3 20.86 10.67 480.00 10,013.35 5,119.64 100.00
Material Sub-total 10,013.35 5,119.64 15.91
Total Cost per crew day 62,955.98 30,323.54

Average daily production (ADP) = 480.00 m3


Activity operational cost per crew day / ADP = 131.16 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 177.06 Birr/m3
Activity replacement cost per crew day / ADP = 63.17 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 85.28 Birr/m3
Total Activity Unit Rate = 262.35 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *considering 100% Natural gravel

Stadia Engineering Works Consultant Plc Page 78 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 52.01(c)(ii) Category: Mechanized ADP= March 21, 2017
Activity Name: Crushed -stone base Scope: Pavement 800.00 m3 Result: 653.02 Birr/m3
* freehaul-18km
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 6.78
2 Equ.op.IV 2 16.00 102.31 1,637.02 18.79
3 Equ.op.III 17 129.29 39.79 5,144.10 59.03
4 Equ.op.II 2 16.00 28.42 454.73 5.22
5 Helper II 2 16.00 23.87 381.97 4.38
6 Labour I 5 40.00 12.62 504.75 5.79
Labour Sub-total 8,713.71 - 3.05
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 107.62 481.75 104.04 585.79 51,845.46 11,196.40 61.78
2 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 15.42
3 Loader, Wheel 2-2.5 M3 13.67 591.65 496.23 1,087.88 8,085.90 6,781.83 9.64
4 Roller,Vibrator,2Drums 8 ton 16.00 478.94 281.42 760.36 7,663.05 4,502.67 9.13
5 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 4.03
Equipment Sub-total 4,605.85 83,917.51 36,358.18 29.40
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Crushed Aggregate (Base Course) m3 241.00 81.48 800.00 192,796.47 65,187.34 100.00
Material Sub-total 192,796.47 65,187.34 67.55
Total Cost per crew day 285,427.69 101,545.52

Average daily production (ADP) = 800.00 m3


Activity operational cost per crew day / ADP = 356.78 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 481.66 Birr/m3
Activity replacement cost per crew day / ADP = 126.93 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 171.36 Birr/m3
Total Activity Unit Rate = 653.02 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Loader hours include 8 hours for base coarse material mixing

Stadia Engineering Works Consultant Plc Page 79 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 61.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Prime Coat (MC-30 cutback bitumen ) Scope: Pavement 8,570.00 l Result: 40.04 Birr/l

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 233.64 14.14
2 Driver III 2 16.00 36.38 272.58 16.49
3 St.eq.opI 2 16.00 22.74 203.36 12.30
4 Helper II 3 24.00 23.87 337.49 20.42
5 Labour I 6 48.00 12.62 605.70 36.65
6
7
Labour Sub-total 1,652.77 - 0.66
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Water truck,6*4 20000Lits 4.00 422.98 145.63 568.61 980.90 581.42 13.51
2 Asphalt Distributor 6000 Lit 8.00 752.49 418.89 1,171.38 4,699.69 783.04 64.73
3 Asphalt Kettle, Trailer Mounted 1500-2000Lit 8.00 499.25 114.83 614.07 332.11 306.40 4.57
4 Street Sweeper, Self Prop 1-2m 6.00 425.74 118.67 544.41 1,247.57 304.96 17.18
5
Equipment Sub-total 2,898.47 7,260.27 1,975.81 2.88
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Bitumen - MC-30 Kg 28.39 8,570.00 243,302.30 - 100.00
2
Material Sub-total 243,302.30 - 96.47
Total Cost per crew day 252,215.34 1,975.81

Average daily production (ADP) = 8,570.00 l


Activity operational cost per crew day / ADP = 29.43 Birr/l
Total Oper. unit cost including 35% overhead & profit = 39.73 Birr/l
Activity replacement cost per crew day / ADP = 0.23 Birr/l
Total Repl. unit cost including 35% overhead & profit = 0.31 Birr/l
Total Activity Unit Rate = 40.04 Birr/l

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Average Specific gravity of MC-30 is 0.95

Stadia Engineering Works Consultant Plc Page 80 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 62.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Tack Coat (Stable-grade bitumen emulsion Scope: Pavement 4,000.00 Result: 45.96 Birr/l
(30%))

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 10.82
2 Labour I 6 48.00 12.62 605.70 48.05
3 Driver III 1 8.00 36.38 291.03 23.09
4 St.eq.opII 1 8.00 28.42 227.36 18.04
5 -
Labour Sub-total 1,260.50 0.96
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Street Sweeper, Self Prop 1-2m 8.00 425.74 118.67 544.41 3,405.95 949.37 25.38
2 Asphalt Kettle, Trailer Mounted 1500-2000Lit 8.00 499.25 114.83 614.07 3,993.96 918.62 29.76
3 Asphalt Distributor 6000 Lit 8.00 752.49 418.89 1,171.38 6,019.95 3,351.08 44.86
4
Equipment Sub-total 13,419.86 5,219.06 10.25
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Bitumen - AC RC-70 Kg 29.07 4,000.00 116,280.00 100.00
2
3
Material Sub-total 116,280.00 - 88.79
Total Cost per crew day 130,960.36 5,219.06

Average daily production (ADP) = 4,000.00


Activity operational cost per crew day / ADP = 32.74 Birr/l
Total Oper. unit cost including 35% overhead & profit = 44.20 Birr/l
Activity replacement cost per crew day / ADP = 1.30 Birr/l
Total Repl. unit cost including 35% overhead & profit = 1.76 Birr/l
Total Activity Unit Rate = 45.96 Birr/l

Stadia Engineering Works Consultant Plc Page 81 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 63.02(b)* Category: ADP= March 21, 2017
Activity Name: Double Surface Seal (150/200 penetration grade Scope: Pavement 4,000.00 m2 Result: 75.02 Br / m2
bitumen) 1st layer

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 4.51
2 Labour I 10 80.00 12.62 1,009.49 33.38
3 Driver III 5 36.00 36.38 1,309.61 43.31
4 St.eq.opII 1 4.00 28.42 113.68 3.76
5 Equ.op.II 2 16.00 28.42 454.73 15.04
6
Labour Sub-total 3,023.94 1.47
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 24.00 426.76 88.12 514.88 10,242.18 2,114.94 30.62
2 Roller,Pneumatic 10 ton 12.00 553.82 236.35 790.18 6,645.90 2,836.26 19.87
3 Asphalt Kettle, Trailer Mounted 1500-2000Lit 4.00 499.25 114.83 614.07 1,996.98 459.31 5.97
4 Spreader, Aggregate 5-7m 8.00 1,067.62 405.33 1,472.95 8,540.95 3,242.63 25.54
5 Asphalt Distributor 6000 Lit 8.00 752.49 418.89 1,171.38 6,019.95 3,351.08 18.00
6 Hand Tools 8.00
Equipment Sub-total 33,445.95 12,004.22 16.25
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Chip Aggregate M3 262.13 91.80 49.14 12,881.64 4,511.07 7.61
2 Bitumen - MC-3000 Kg 26.60 5,880.00 156,408.00 - 92.39
3
Material Sub-total 169,289.64 4,511.07 82.28
Total Cost per crew day 205,759.53 16,515.29

Average daily production (ADP) = 4,000.00 m2


Activity operational cost per crew day / ADP = 51.44 Br / m2
Total Oper. unit cost including 35% overhead & profit = 69.44 Br / m2
Activity replacement cost per crew day / ADP = 4.13 Br / m2
Total Repl. unit cost including 35% overhead & profit = 5.57 Br / m2
Total Activity Unit Rate = 75.02 Br / m2

Stadia Engineering Works Consultant Plc Page 82 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 63.02(b) Category: ADP= March 21, 2017
Activity Name: Double Surface Seal (150/200 penetration grade Scope: Pavement 4,000.00 Result: 135.58 Br / m2
bitumen)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 4.51
2 Labour I 10 80.00 12.62 1,009.49 33.38
3 Driver III 5 36.00 36.38 1,309.61 43.31
4 St.eq.opII 1 4.00 28.42 113.68 3.76
5 Equ.op.II 2 16.00 28.42 454.73 15.04
6
Labour Sub-total 3,023.94 1.83
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 24.00 426.76 88.12 514.88 10,242.18 2,114.94 30.62
2 Roller,Pneumatic 10 ton 12.00 553.82 236.35 790.18 6,645.90 2,836.26 19.87
3 Asphalt Kettle, Trailer Mounted 1500-2000Lit 4.00 499.25 114.83 614.07 1,996.98 459.31 5.97
4 Spreader, Aggregate 5-7m 8.00 1,067.62 405.33 1,472.95 8,540.95 3,242.63 25.54
5 Asphalt Distributor 6000 Lit 8.00 752.49 418.89 1,171.38 6,019.95 3,351.08 18.00
6 Hand Tools 8.00
Equipment Sub-total 33,445.95 12,004.22 20.23
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Chip Aggregate M3 262.13 91.80 22.86 5,991.46 2,098.17 4.65
2 Bitumen - MC-3000 Kg 26.60 4,620.00 122,892.00 - 95.35
3
Material Sub-total 128,883.46 2,098.17 77.94
Total Cost per crew day 165,353.35 14,102.39

Average daily production (ADP) = 4,000.00 1st layer 75.02 Br / m2


Activity operational cost per crew day / ADP = 41.34 Br / m2 2nd layer 60.57 Br / m2
Total Oper. unit cost including 35% overhead & profit = 55.81 Br / m2
Activity replacement cost per crew day / ADP = 3.53 Br / m2
Total Repl. unit cost including 35% overhead & profit = 4.76 Br / m2
Total Activity Unit Rate = 135.58 Br / m2

Stadia Engineering Works Consultant Plc Page 83 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 64.02(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Asphaltic Concrete (50 mm thick, 80/100 Scope: Pavement 3,500.00 m2 Result: 349.56 Birr/m2
bitumen)
* 18 Freehaul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 7.59
2 Equ.op.III 15 118.00 39.79 4,695.06 60.27
3 Equ.op.II 4 26.00 28.42 738.93 9.49
4 St.eq.opI 1 8.00 22.74 181.89 2.34
5 Helper II 3 24.00 23.87 572.96 7.36
6 Labour I 10 80.00 12.62 1,009.49 12.96
Labour Sub-total 7,789.48 - 0.91
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 106.00 481.75 104.04 585.79 51,065.48 11,027.96 69.20
2 Roller,Vibrator,2Drums 8 ton 18.00 478.94 281.42 760.36 8,620.93 5,065.51 11.68
3 Roller,Pneumatic 10 ton 8.00 553.82 236.35 790.18 4,430.60 1,890.84 6.00
4 Asphalt Paver, Crawler 2.5-8m 8.00 779.21 789.34 1,568.55 6,233.71 6,314.68 8.45
5 Street Sweeper, Self Prop 1-2m 4.00 425.74 118.67 544.41 1,702.98 474.68 2.31
6 Water truck,6*4 20000Lits 4.00 422.98 145.63 568.61 1,691.92 582.51 2.29
7 Asphalt Cutter - 4.00 10.80 14.04 24.84 43.20 56.15 0.06
Equipment Sub-total 4,842.73 73,788.81 25,412.33 8.63
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Asphalt Hot Mix M3 4,015.47 136.66 192.50 772,978.69 26,306.48 100.00
Material Sub-total 772,978.69 26,306.48 90.45
Total Cost per crew day 854,556.98 51,718.81

Average daily production (ADP) = 3,500.00 m2 Asphalt Thickness 50.00 mm


Activity operational cost per crew day / ADP = 244.16 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 329.61 Birr/m2
Activity replacement cost per crew day / ADP = 14.78 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 19.95 Birr/m2
Total Activity Unit Rate = 349.56 Birr/m2
Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 84 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 81.02(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Major Structures Excavation (in Soft) Scope: Structure 185.00 m3 Result: 110.11 Birr/m3
*0.5Km free-haul to waste
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 16.78
2 Equ.op.III 2 13.95 39.79 554.91 21.33
3 Helper I 4 32.00 18.76 600.24 23.08
4 Labour I 10 80.00 12.62 1,009.49 38.81
5
Labour Sub-total 2,601.18 - 22.54
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 52.54
2 Dump truck,6*4 (12m3) 12M3 5.95 481.75 104.04 585.79 2,864.69 618.65 32.04
3 Water Pump 230 Lit/min 24.00 57.43 3.80 61.23 1,378.28 91.12 15.42
4 Hand Tools
5
6
Equipment Sub-total 8,941.04 3,546.72 77.46
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
Material Sub-total - -
Total Cost per crew day 11,542.22 3,546.72

Average daily production (ADP) = 185.00 m3


Activity operational cost per crew day / ADP = 62.39 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 84.23 Birr/m3
Activity replacement cost per crew day / ADP = 19.17 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 25.88 Birr/m3
Total Activity Unit Rate = 110.11 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering 40% Loose factor for excavated material


*Unit rate for hard excavation in structure can be taken directly from rock excavation

Stadia Engineering Works Consultant Plc Page 85 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 81.02(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Major Structures Excavation (in Hard) Scope: Structure 80.00 m3 Result: 240.74 Birr/m3
*0.5Km free-haul to waste
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For I 1 8.00 45.47 363.78 20.14
2 Equ.op.III 2 10.57 39.79 420.62 23.28
3 St.eq.opI 1 8.00 22.74 181.89 10.07
4 Labour I 4 32.00 12.62 403.80 22.35
5 Labour II 4 32.00 13.64 436.54 24.16
Labour Sub-total 1,806.63 - 16.66
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 51.98
2 Dump truck,6*4 (12m3) 12M3 2.57 481.75 104.04 585.79 1,238.79 267.52 13.70
3 Air Compressor 600CFM 8.00 377.78 18.65 396.43 3,022.22 149.20 33.44
4 Jack Hammer - 32.00 2.50 5.20 7.70 80.00 166.40 0.89
5 Hand Tools
Equipment Sub-total 9,039.08 3,420.07 83.34
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
Material Sub-total - -
Total Cost per crew day 10,845.71 3,420.07

Average daily production (ADP) = 80.00 m3


Activity operational cost per crew day / ADP = 135.57 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 183.02 Birr/m3
Activity replacement cost per crew day / ADP = 42.75 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 57.71 Birr/m3
Total Activity Unit Rate = 240.74 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering 40% Loose factor for excavated material

Stadia Engineering Works Consultant Plc Page 86 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 81.05(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Backfill using excavated material Scope: Structure 200.00 Result: 140.56 Birr/m3
*using the excavated material
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For I 1 8.00 45.47 363.78 24.43
2 Equ.op.II 2 16.00 28.42 454.73 30.54
3 Equ.op.III 1 8.00 39.79 318.31 21.38
4 Helper I 1 8.00 18.76 150.06 10.08
5 Labour I 2 16.00 12.62 201.90 13.56
6
Labour Sub-total 1,488.78 - 11.08
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 28.32
2 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 32.07
3 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 39.61
4
Equipment Sub-total 2,416.85 11,948.57 7,386.22 88.92
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
Material Sub-total - -
Total Cost per crew day 13,437.34 7,386.22

Average daily production (ADP) = 200.00


Activity operational cost per crew day / ADP = 67.19 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 90.70 Birr/m3
Activity replacement cost per crew day / ADP = 36.93 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 49.86 Birr/m3
Total Activity Unit Rate = 140.56 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 87 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 81.05(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Backfill using imported material Scope: Structure 200.00 m3 Result: 245.87 Birr/m3
*using imported material of 10 km free haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For I 1 8.00 45.47 363.78 16.80
2 Equ.op.II 1 8.00 28.42 227.36 10.50
3 Equ.op.III 4 30.71 39.79 1,222.08 56.44
4 Helper I 1 8.00 18.76 150.06 6.93
5 Labour I 2 16.00 12.62 201.90 9.32
6
Labour Sub-total 2,165.18 - 8.53
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 17.77
2 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 20.13
3 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 24.86
4 Dump truck,6*4 (12m3) 12M3 14.71 481.75 104.04 585.79 7,088.60 1,530.83 37.24
5
Equipment Sub-total 3,002.63 19,037.17 8,917.05 75.02
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Select Material m3 20.86 10.67 200.00 4,172.23 2,133.18 100.00
2
Material Sub-total 4,172.23 2,133.18 16.44
Total Cost per crew day 25,374.58 11,050.23

Average daily production (ADP) = 200.00 m3


Activity operational cost per crew day / ADP = 126.87 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 171.28 Birr/m3
Activity replacement cost per crew day / ADP = 55.25 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 74.59 Birr/m3
Total Activity Unit Rate = 245.87 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Using rental loader


*30% compaction factor for select material

Stadia Engineering Works Consultant Plc Page 88 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 81.05(c) Category: Mechanized ADP= March 21, 2017
Activity Name: Hand laid rock embankment Scope: Structure 40.00 Result: 391.01 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 5.87
2 Equ.op.III 1 4.27 39.79 169.89 7.31
3 Labour I 20 160.00 12.62 2,018.99 86.83
4
5
Labour Sub-total 2,325.30 - 25.49
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 3.27 481.75 104.04 585.79 1,575.25 340.19 61.66
2 Loader, Crawler 2-2.5 M3 1.00 979.60 802.82 1,782.42 979.60 802.82 38.34
3 -
Equipment Sub-total 2,368.20 2,554.84 1,143.00 28.01
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Stone M3 106.02 33.03 40.00 4,241.00 1,321.29 100.00
2 -
3 -
Material Sub-total 4,241.00 1,321.29 46.50
Total Cost per crew day 9,121.14 2,464.29

Average daily production (ADP) = 40.00


Activity operational cost per crew day / ADP = 228.03 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 307.84 Birr/m3
Activity replacement cost per crew day / ADP = 61.61 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 83.17 Birr/m3
Total Activity Unit Rate = 391.01 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 89 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 81.08(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Rock foundation fill Scope: Structure 30.00 Result: 435.76 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 5.95
2 Equ.op.III 1 3.45 39.79 137.37 5.99
3 Labour I 20 160.00 12.62 2,018.99 88.06
4
5
Labour Sub-total 2,292.77 - 30.03
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 2.45 481.75 104.04 585.79 1,181.43 255.14 54.67
2 Loader, Crawler 2-2.5 M3 1.00 979.60 802.82 1,782.42 979.60 802.82 45.33
3 -
Equipment Sub-total 2,368.20 2,161.03 1,057.96 28.31
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Stone M3 106.02 33.03 30.00 3,180.75 990.97 100.00
2 -
3 -
Material Sub-total 3,180.75 990.97 41.66
Total Cost per crew day 7,634.55 2,048.92

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 254.49 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 343.55 Birr/m3
Activity replacement cost per crew day / ADP = 68.30 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 92.20 Birr/m3
Total Activity Unit Rate = 435.76 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 90 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 81.08(c) Category: Mechanized ADP= March 21, 2017
Activity Name: Compacted granular foundation fill Scope: Structure 180.00 Result: 261.55 Birr/m3
*using imported material of 10 km free haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For I 1 8.00 45.47 363.78 17.27
2 Equ.op.II 1 8.00 28.42 227.36 10.79
3 Equ.op.III 4 29.24 39.79 1,163.53 55.23
4 Helper I 1 8.00 18.76 150.06 7.12
5 Labour I 2 16.00 12.62 201.90 9.58
6
Labour Sub-total 2,106.64 - 8.71
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 18.46
2 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 20.90
3 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 25.82
4 Dump truck,6*4 (12m3) 12M3 13.24 481.75 104.04 585.79 6,379.74 1,377.75 34.81
5
Equipment Sub-total 3,002.63 18,328.31 8,763.97 75.77
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Select Material m3 20.86 10.67 180.00 3,755.01 1,919.86 100.00
2
Material Sub-total 3,755.01 1,919.86 15.52
Total Cost per crew day 24,189.95 10,683.83

Average daily production (ADP) = 180.00


Activity operational cost per crew day / ADP = 134.39 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 181.42 Birr/m3
Activity replacement cost per crew day / ADP = 59.35 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 80.13 Birr/m3
Total Activity Unit Rate = 261.55 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Using rental loader


*30% compaction factor for select material

Stadia Engineering Works Consultant Plc Page 91 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 82.01(a ) Category: Mechanized ADP= March 21, 2017
Activity Name: Formwork for Class F1 surface finish Scope: Structure 32.00 Result: 973.49 Birr/m2

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carp. Foreman 1 8.00 64.80 518.39 4.80
2 Driver III 1 2.00 36.38 72.76 0.67
3 Carpenter II 16 128.00 54.57 6,984.61 64.64
4 Labour I 32 256.00 12.62 3,230.38 29.89
5
6
Labour Sub-total 10,806.14 - 47.19
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 100.00
2 Hand Tools
3
4
Equipment Sub-total 514.88 853.51 176.24 3.73
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Equaliptus Pole (Dia. 100mm, 8m long) No 100.00 70.00 7,000.00 - 62.28
2 Lumber m3 10,000.00 0.32 3,200.00 - 28.47
3 Ply wood No 60.00 16.00 960.00 - 8.54
4 Nails kg 26.50 3.00 79.50 - 0.71
Material Sub-total 11,239.50 - 49.08
Total Cost per crew day 22,899.15 176.24

Average daily production (ADP) = 32.00


Activity operational cost per crew day / ADP = 715.60 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 966.06 Birr/m2
Activity replacement cost per crew day / ADP = 5.51 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 7.44 Birr/m2
Total Activity Unit Rate = 973.49 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering to re-use Each Equaliptus pole 1.5 & lumber 1 time

Stadia Engineering Works Consultant Plc Page 92 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 82.01(b ) Category: Mechanized ADP= March 21, 2017
Activity Name: Formwork for Class F2 surface finish Scope: Structure 36.00 m2 Result: 851.08 Birr/m2

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carp. Foreman 1 8.00 64.80 518.39 4.80
2 Driver III 1 2.00 36.38 72.76 0.67
3 Carpenter II 16 128.00 54.57 6,984.61 64.64
4 Labour I 32 256.00 12.62 3,230.38 29.89
5
6
Labour Sub-total 10,806.14 - 47.99
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 100.00
2 Hand Tools
3
4
Equipment Sub-total 514.88 853.51 176.24 3.79
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Equaliptus Pole (Dia. 100mm, 8m long) No 100.00 70.00 7,000.00 - 64.46
2 Lumber m3 10,000.00 0.36 3,600.00 - 33.15
3 Ply wood No 60.00 3.00 180.00 - 1.66
4 Nails kg 26.50 3.00 79.50 - 0.73
Material Sub-total 10,859.50 - 48.22
Total Cost per crew day 22,519.15 176.24

Average daily production (ADP) = 36.00 m2


Activity operational cost per crew day / ADP = 625.53 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 844.47 Birr/m2
Activity replacement cost per crew day / ADP = 4.90 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 6.61 Birr/m2
Total Activity Unit Rate = 851.08 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering to re-use Each Equaliptus pole 1.5 & lumber 1 time

Stadia Engineering Works Consultant Plc Page 93 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 83.01(a)(i) Category: Mechanized ADP= March 21, 2017
Activity Name: Grade 60 Reinforcement Steel Scope: Structure 0.51 t Result: 34,757.89 Birr/t
*(Grade-60)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Bar Sett.II 1 8.00 40.93 327.40 13.09
2 Bar Sett.I 4 32.00 30.69 982.21 39.27
3 St.eq.opI 1 8.00 22.74 181.89 7.27
4 Labour I 10 80.00 12.62 1,009.49 40.36
5
6
Labour Sub-total 2,501.00 - 18.95
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Steel-cutter 8.00 - -
2 Barbending Jig 8.00 - -
3
4
Equipment Sub-total - -
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Binding wire Kg 32.00 15.00 480.00 - 4.49
2 Reinforcement Bar (Mild, Grade-60) t 19,930.00 0.51 10,214.13 - 95.51
3
4
Material Sub-total 10,694.13 - 81.05
Total Cost per crew day 13,195.13 -

Average daily production (ADP) = 0.51 t


Activity operational cost per crew day / ADP = 25,746.59 Birr/t
Total Oper. unit cost including 35% overhead & profit = 34,757.89 Birr/t
Activity replacement cost per crew day / ADP = - Birr/t
Total Repl. unit cost including 35% overhead & profit = - Birr/t
Total Activity Unit Rate = 34,757.89 Birr/t

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 94 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 83.01(a)(ii) Category: Mechanized ADP= March 21, 2017
Activity Name: Grade 40 Reinforcement Steel Scope: Structure 0.51 t Result: 33,583.39 Birr/t
*(Grade-40)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Bar Sett.II 1 8.00 40.93 327.40 13.09
2 Bar Sett.I 4 32.00 30.69 982.21 39.27
3 St.eq.opI 1 8.00 22.74 181.89 7.27
4 Labour I 10 80.00 12.62 1,009.49 40.36
5
6
Labour Sub-total 2,501.00 - 19.62
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Steel-cutter 8.00 - -
2 Barbending Jig 8.00 - -
3
4
Equipment Sub-total - -
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Binding wire Kg 32.00 15.00 480.00 - 4.68
2 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.51 9,768.25 - 95.32
3
4
Material Sub-total 10,248.25 - 80.38
Total Cost per crew day 12,749.25 -

Average daily production (ADP) = 0.51 t


Activity operational cost per crew day / ADP = 24,876.59 Birr/t
Total Oper. unit cost including 35% overhead & profit = 33,583.39 Birr/t
Activity replacement cost per crew day / ADP = - Birr/t
Total Repl. unit cost including 35% overhead & profit = - Birr/t
Total Activity Unit Rate = 33,583.39 Birr/t

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 95 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 84.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Class 30/20 concrete in RC Structure Scope: Structure 32.00 m3 Result: 3,266.49 Birr/m3
*(Grade 30)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 3.85
2 Driver III 3 17.00 36.38 618.43 5.45
3 St.eq.opI 2 16.00 22.74 363.78 3.21
4 Mason I 8 64.00 22.17 1,418.75 12.50
5 Carpenter I 8 64.00 40.93 2,619.23 23.08
6 Carp. Foreman 1 8.00 64.80 518.39 4.57
7 Bar Sett.II 1 8.00 40.93 327.40 2.88
8 Labour I 50 400.00 12.62 5,047.47 44.47
Labour Sub-total 11,349.99 - 15.76
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 6.00 426.76 88.12 514.88 2,560.54 528.73 28.07
2 Loader, Wheel 2-2.5 M3 3.00 591.65 496.23 1,087.88 1,774.95 1,488.69 19.46
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 37.10
4 Concrete Vibrator 5 HP 32.00 22.48 2.43 24.91 719.32 77.90 7.89
5 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 7.48
6 Hand Tools
Equipment Sub-total 2,247.20 9,120.90 3,392.78 12.67
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 144.00 36,832.32 - 71.46
2 Sand m3 461.54 19.20 8,861.54 - 17.19
3 Crushed Aggregate M3 243.73 84.20 24.00 5,849.58 2,020.89 11.35
Material Sub-total 51,543.44 2,020.89 71.57
Total Cost per crew day 72,014.34 5,413.67

Average daily production (ADP) = 32.00 m3


Activity operational cost per crew day / ADP = 2,250.45 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 3,038.10 Birr/m3
Activity replacement cost per crew day / ADP = 169.18 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 228.39 Birr/m3
Total Activity Unit Rate = 3,266.49 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 96 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 84.01(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Class 25/20 concrete in RC Structure Scope: Structure 32.00 Result: 3,093.84 Birr/m3
*(Grade 25)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 3.85
2 Driver III 3 17.00 36.38 618.43 5.45
3 St.eq.opI 2 16.00 22.74 363.78 3.21
4 Mason I 8 64.00 22.17 1,418.75 12.50
5 Carpenter I 8 64.00 40.93 2,619.23 23.08
6 Carp. Foreman 1 8.00 64.80 518.39 4.57
7 Bar Sett.II 1 8.00 40.93 327.40 2.88
8 Labour I 50 400.00 12.62 5,047.47 44.47
Labour Sub-total 11,349.99 - 16.71
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 6.00 426.76 88.12 514.88 2,560.54 528.73 28.07
2 Loader, Wheel 2-2.5 M3 3.00 591.65 496.23 1,087.88 1,774.95 1,488.69 19.46
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 37.10
4 Concrete Vibrator 5 HP 32.00 22.48 2.43 24.91 719.32 77.90 7.89
5 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 7.48
6 Hand Tools
Equipment Sub-total 2,247.20 9,120.90 3,392.78 13.43
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 128.00 32,739.84 - 69.00
2 Sand m3 461.54 19.20 8,861.54 - 18.68
3 Crushed Aggregate M3 243.73 84.20 24.00 5,849.58 2,020.89 12.33
Material Sub-total 47,450.96 2,020.89 69.86
Total Cost per crew day 67,921.86 5,413.67

Average daily production (ADP) = 32.00


Activity operational cost per crew day / ADP = 2,122.56 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,865.45 Birr/m3
Activity replacement cost per crew day / ADP = 169.18 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 228.39 Birr/m3
Total Activity Unit Rate = 3,093.84 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 97 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 84.01(c) Category: Mechanized ADP= March 21, 2017
Activity Name: Class 15/20 concrete in lean concrete Scope: Structure 32.00 m3 Result: 2,570.71 Birr/m3
*(Grade 15)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 6.12
2 Driver III 3 17.00 36.38 618.43 8.67
3 St.eq.opI 2 16.00 22.74 363.78 5.10
4 Mason I 3 24.00 22.17 532.03 7.46
5 Carpenter I 5 40.00 40.93 1,637.02 22.94
6 Carp. Foreman 1 8.00 64.80 518.39 7.27
7 Labour I 30 240.00 12.62 3,028.48 42.45
Labour Sub-total 7,134.67 - 12.85
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 6.00 426.76 88.12 514.88 2,560.54 528.73 28.07
2 Loader, Wheel 2-2.5 M3 3.00 591.65 496.23 1,087.88 1,774.95 1,488.69 19.46
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 37.10
4 Concrete Vibrator 5 HP 32.00 22.48 2.43 24.91 719.32 77.90 7.89
5 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 7.48
6 Hand Tools
Equipment Sub-total 2,247.20 9,120.90 3,392.78 16.43
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 96.00 24,554.88 - 62.53
2 Sand m3 461.54 19.20 8,861.54 - 22.57
3 Crushed Aggregate M3 243.73 84.20 24.00 5,849.58 2,020.89 14.90
Material Sub-total 39,266.00 2,020.89 70.72
Total Cost per crew day 55,521.58 5,413.67

Average daily production (ADP) = 32.00 m3


Activity operational cost per crew day / ADP = 1,735.05 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,342.32 Birr/m3
Activity replacement cost per crew day / ADP = 169.18 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 228.39 Birr/m3
Total Activity Unit Rate = 2,570.71 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 98 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 87.03 Category: Mechanized ADP= March 21, 2017
Activity Name: Elastomeric Bearing Scope: Structure 2.00 No. Result: 11,470.53 Birr/each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Welder II 1 8.00 45.47 363.78 100.00
2
Labour Sub-total 363.78 - 2.16
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 AC Welder, Diesel 300-400AMP 8.00 189.56 16.19 205.75 1,516.49 129.51 100.00
2
Equipment Sub-total 205.75 1,516.49 129.51 8.99
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.

1 Elastomeric Bearing (400mm*300mm*69mm) No 7,452.00 2.00 14,904.00 - 99.47


2 Electrode, #4 Kg 79.60 1.00 79.60 - 0.53
Material Sub-total 14,983.60 - 88.85
Total Cost per crew day 16,863.87 129.51

Average daily production (ADP) = 2.00 No.


Activity operational cost per crew day / ADP = 8,431.93 Birr/each
Total Oper. unit cost including 35% overhead & profit = 11,383.11 Birr/each
Activity replacement cost per crew day / ADP = 64.76 Birr/each
Total Repl. unit cost including 35% overhead & profit = 87.42 Birr/each
Total Activity Unit Rate = 11,470.53 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Cost includes cutting, grinding, drilling & boltting of steel plate

Stadia Engineering Works Consultant Plc Page 99 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 87.07 Category: Mechanized ADP= March 21, 2017
Activity Name: Concrete parapet Scope: Structure 66.00 m Result: 685.12 Birr/m

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8
Labour Sub-total 4,174.40 - 12.95
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total 1,928.98 372.20 5.98
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 3.09 1,425.60 5.46
2 Cement Quintal 255.78 30.89 7,900.53 30.24
3 Crushed Aggregate M3 243.73 84.20 4.63 1,129.26 390.13 4.32
4 Formwork m2 172.07 5.51 91.08 15,672.08 501.64 59.98
5
6
Material Sub-total 26,127.48 891.77 81.06
Total Cost per crew day 32,230.86 1,263.97

Average daily production (ADP) = 66.00 m


Activity operational cost per crew day / ADP = 488.35 Birr/m
Total Oper. unit cost including 35% overhead & profit = 659.27 Birr/m
Activity replacement cost per crew day / ADP = 19.15 Birr/m
Total Repl. unit cost including 35% overhead & profit = 25.85 Birr/m
Total Activity Unit Rate = 685.12 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 100 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 87.13(a) Category: Mechanized ADP= March 21, 2017
Activity Name: Expansion joint with 20mm filler Scope: Structure 8.10 m Result: 365.89 Birr/m
*including 20mm compressible joint filler board
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.III 1 1.00 39.79 39.79 5.11
2 Carpenter II 1 8.00 54.57 436.54 56.03
3 Labour I 3 24.00 12.62 302.85 38.87
4
Labour Sub-total 779.18 - 36.98
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
3
4
Equipment Sub-total 514.88 426.76 88.12 20.25
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Chipwood No 420.00 2.00 840.00 - 93.20
2 Bitumen - AC-60/70 Kg 19.10 - 3.21 61.26 - 6.80
3
Material Sub-total 901.26 - 42.77
Total Cost per crew day 2,107.19 88.12

Average daily production (ADP) = 8.10 m


Activity operational cost per crew day / ADP = 260.15 Birr/m
Total Oper. unit cost including 35% overhead & profit = 351.20 Birr/m
Activity replacement cost per crew day / ADP = 10.88 Birr/m
Total Repl. unit cost including 35% overhead & profit = 14.69 Birr/m
Total Activity Unit Rate = 365.89 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 101 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 87.19(a)(i) Category: Mechanized ADP= March 21, 2017
Activity Name: Dia. 100mm PVC drainage pipes Scope: Structure 16.00 Result: 96.07 Birr/Each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason I 1 8.00 22.17 177.34 81.68
2 Equ.op.III 1 1.00 39.79 39.79 18.32
3
Labour Sub-total 217.13 - 20.67
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total 514.88 426.76 88.12 40.63
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 PVC Pipe, 110mm No 184.80 2.20 406.56 - 100.00
2
Material Sub-total 406.56 - 38.70
Total Cost per crew day 1,050.45 88.12

Average daily production (ADP) = 16.00


Activity operational cost per crew day / ADP = 65.65 Birr/Each
Total Oper. unit cost including 35% overhead & profit = 88.63 Birr/Each
Activity replacement cost per crew day / ADP = 5.51 Birr/Each
Total Repl. unit cost including 35% overhead & profit = 7.44 Birr/Each
Total Activity Unit Rate = 96.07 Birr/Each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 102 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 87.19(b)(i) Category: Mechanized ADP= March 21, 2017
Activity Name: Dia. 200mm PVC pipe weep holes Scope: Structure 48.00 m Result: 82.96 Birr/m

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason I 1 8.00 22.17 177.34 81.68
2 Equ.op.III 1 1.00 39.79 39.79 18.32
3
Labour Sub-total 217.13 - 7.59
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total 514.88 426.76 88.12 14.91
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 PVC Pipe, 110mm No 184.80 12.00 2,217.60 - 100.00
2
Material Sub-total 2,217.60 - 77.50
Total Cost per crew day 2,861.49 88.12

Average daily production (ADP) = 48.00 m


Activity operational cost per crew day / ADP = 59.61 Birr/m
Total Oper. unit cost including 35% overhead & profit = 80.48 Birr/m
Activity replacement cost per crew day / ADP = 1.84 Birr/m
Total Repl. unit cost including 35% overhead & profit = 2.48 Birr/m
Total Activity Unit Rate = 82.96 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 103 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 87.23 Category: Mechanized ADP= March 21, 2017
Activity Name: Crushed Stone in drainage Strips Scope: Structure 8.00 m3 Result: 575.16 Birr/m3
*(sheeting material)
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labour I 4 32.00 12.62 403.80 91.03
2 Equ.op.III 1 1.00 39.79 39.79 8.97
3
Labour Sub-total 443.59 - 16.43
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
3
Equipment Sub-total 514.88 426.76 88.12 15.80
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Crushed Aggregate m3 228.77 77.46 8.00 1,830.18 619.70 100.00
2
Material Sub-total 1,830.18 619.70 67.77
Total Cost per crew day 2,700.52 707.82

Average daily production (ADP) = 8.00 m3


Activity operational cost per crew day / ADP = 337.56 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 455.71 Birr/m3
Activity replacement cost per crew day / ADP = 88.48 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 119.45 Birr/m3
Total Activity Unit Rate = 575.16 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 20 km free haul

Stadia Engineering Works Consultant Plc Page 104 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 89.01(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Class "B" Stone Masonry Scope: Structure 25.00 m3 Result: 1,660.28 Birr/m3
*with 10km free-haul
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 8.00 54.57 436.54 3.77
2 Equ.op.III 1 5.00 39.79 198.94 1.72
3 St.eq.opI 1 8.00 22.74 181.89 1.57
4 Mason I 20 160.00 22.17 3,546.87 30.59
5 Carpenter II 1 8.00 54.57 436.54 3.77
6 Helper I 2 16.00 18.76 300.12 2.59
7 Labour I 40 320.00 12.62 4,037.98 34.83
8 Labour III 20 160.00 15.35 2,455.53 21.18
Labour Sub-total 11,594.41 - 41.09
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 4.00 481.75 104.04 585.79 1,927.00 416.15 47.07
2 Loader, Crawler 2-2.5 M3 1.00 979.60 802.82 1,782.42 979.60 802.82 23.93
3 Water truck,6*4 20000Lits 2.00 422.98 145.63 568.61 845.96 291.26 20.66
4 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 8.33
5 Hand Tools
Equipment Sub-total 2,987.73 4,093.69 1,576.43 14.51
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 26.25 6,714.23 - 53.58
2 Sand m3 461.54 6.00 2,769.23 - 22.10
3 Stone M3 106.02 33.03 28.75 3,048.22 949.68 24.32
Material Sub-total 12,531.67 949.68 44.41
Total Cost per crew day 28,219.77 2,526.11

Average daily production (ADP) = 25.00 m3


Activity operational cost per crew day / ADP = 1,128.79 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 1,523.87 Birr/m3
Activity replacement cost per crew day / ADP = 101.04 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 136.41 Birr/m3
Total Activity Unit Rate = 1,660.28 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 105 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 810.01(a) Category: Mechanized ADP= March 21, 2017
Activity Name: MSE Gabion wall facing Scope: Structure 6.00 Result: 2,432.81 Birr/m2

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.75
2 Equ.op.III 1 1.00 39.79 39.79 3.43
3 Mason I 1 8.00 22.17 177.34 15.27
4 Labour I 8 64.00 12.62 807.60 69.55
Labour Sub-total 1,161.15 - 11.03
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
Equipment Sub-total 426.76 88.12 4.05
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 PVC-coated Gabion boxes,3*3*1*1m No 3,881.76 2.00 7,763.52 86.86
2 Binding wire Kg 32.00 1.50 48.00 0.54
3 Geotextile M2 81.77 - 6.00 490.60 - 5.49
4 Stone M3 106.02 33.03 6.00 636.15 198.19 7.12
Material Sub-total 8,938.27 198.19 84.91
Total Cost per crew day 10,526.18 286.32

Average daily production (ADP) = 6.00


Activity operational cost per crew day / ADP = 1,754.36 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 2,368.39 Birr/m2
Activity replacement cost per crew day / ADP = 47.72 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 64.42 Birr/m2
Total Activity Unit Rate = 2,432.81 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 106 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 810.01(b) Category: Mechanized ADP= March 21, 2017
Activity Name: Polymeric (Geogrid) Reinforcements Scope: Structure 200.00 Result: 284.41 Birr/m2

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 13.87
2 Labour I 8 64.00 12.62 807.60 82.09
3 Equ.op.III 1 1.00 39.79 39.79 4.04
Labour Sub-total 983.80 - 2.34
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
Equipment Sub-total 426.76 88.12 1.01
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Geogrid M2 203.18 200.00 40,635.54 100.00
2
Material Sub-total 40,635.54 - 96.65
Total Cost per crew day 42,046.10 88.12

Average daily production (ADP) = 200.00


Activity operational cost per crew day / ADP = 210.23 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 283.81 Birr/m2
Activity replacement cost per crew day / ADP = 0.44 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 0.59 Birr/m2
Total Activity Unit Rate = 284.41 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 107 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 810.01(c) Category: Mechanized ADP= March 21, 2017
Activity Name: Scope: Structure 110.00 Result: 447.51 Birr/m2
Drainage at interface of backfill and in-situ soil

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.61
2 Equ.op.III 1 5.32 39.79 211.80 18.03
3 Helper I 1 1.00 18.76 18.76 1.60
4 Labour I 8 64.00 12.62 807.60 68.76
5
6
Labour Sub-total 1,174.57 - 3.86
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Loader, Wheel 2-2.5 M3 0.47 591.65 496.23 1,087.88 276.60 231.99 9.35
2 Dump truck,6*4 (12m3) 12M3 4.86 481.75 104.04 585.79 2,339.24 505.18 79.09
3 Plate Compactor - 32.00 10.68 5.09 15.77 341.76 162.83 11.56
4 Hand Tools
5
Equipment Sub-total 1,689.44 2,957.60 899.99 9.71
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sub-base aggregate m3 228.77 77.46 66.00 15,098.95 5,112.54 57.37
2 PVC Pipe, 110mm No 184.80 9.17 1,694.00 6.44
3 Perforated PVC Pipe, 150mm No 369.60 18.33 6,776.00 25.75
4 Impermeable Membrane M2 25.00 110.00 2,750.00 10.45
Material Sub-total 26,318.95 5,112.54 86.43
Total Cost per crew day 30,451.12 6,012.53

Average daily production (ADP) = 110.00


Activity operational cost per crew day / ADP = 276.83 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 373.72 Birr/m2
Activity replacement cost per crew day / ADP = 54.66 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 73.79 Birr/m2
Total Activity Unit Rate = 447.51 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 108 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 91.03(a)(i) Category: Labour intensive ADP= March 21, 2017
Activity Name: Gabion boxes (2x1x1) Scope: Ancillary Works 8.00 Result: 944.80 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.75
2 Equ.op.III 1 1.00 39.79 39.79 3.43
3 Mason I 1 8.00 22.17 177.34 15.27
4 Labour I 8 64.00 12.62 807.60 69.55
Labour Sub-total 1,161.15 - 22.13
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
Equipment Sub-total 426.76 88.12 8.13
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Gabion boxes, 2m*1m*1m No 686.58 4.00 2,746.33 75.07
2 Binding wire Kg 32.00 2.00 64.00 1.75
3 Stone M3 106.02 33.03 8.00 848.20 264.26 23.18
Material Sub-total 3,658.53 264.26 69.73
Total Cost per crew day 5,246.44 352.38

Average daily production (ADP) = 8.00


Activity operational cost per crew day / ADP = 655.80 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 885.34 Birr/m3
Activity replacement cost per crew day / ADP = 44.05 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 59.46 Birr/m3
Total Activity Unit Rate = 944.80 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 109 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 91.03(a)(ii) Category: Labour intensive ADP= March 21, 2017
Activity Name: Gabion boxes (1.5x1x1) Scope: Ancillary Works 8.00 Result: 986.93 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.75
2 Equ.op.III 1 1.00 39.79 39.79 3.43
3 Mason I 1 8.00 22.17 177.34 15.27
4 Labour I 8 64.00 12.62 807.60 69.55
5
Labour Sub-total 1,161.15 - 21.13
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
3
4
Equipment Sub-total 426.76 88.12 7.76
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Gabion boxes, 1.5m*1m*1m No 561.75 5.33 2,996.00 76.66
2 Binding wire Kg 32.00 2.00 64.00 1.64
3 Stone M3 106.02 33.03 8.00 848.20 264.26 21.70
4
Material Sub-total 3,908.20 264.26 71.11
Total Cost per crew day 5,496.10 352.38

Average daily production (ADP) = 8.00


Activity operational cost per crew day / ADP = 687.01 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 927.47 Birr/m3
Activity replacement cost per crew day / ADP = 44.05 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 59.46 Birr/m3
Total Activity Unit Rate = 986.93 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 110 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 91.04 Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Ancillary Works 50.00 Result: 110.38 Birr/m2
Filter Fabric (Terram 1000 or equivalent)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 40.32
2 Labour I 2 16.00 12.62 201.90 59.68
3
Labour Sub-total 338.32 - 8.28
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1
Equipment Sub-total - -
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Geo-Textile filter fabric M2 75.00 50.00 3,750.00 100.00
2
Material Sub-total 3,750.00 - 91.72
Total Cost per crew day 4,088.32 -

Average daily production (ADP) = 50.00


Activity operational cost per crew day / ADP = 81.77 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 110.38 Birr/m2
Activity replacement cost per crew day / ADP = - Birr/m2
Total Repl. unit cost including 35% overhead & profit = - Birr/m2
Total Activity Unit Rate = 110.38 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 111 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 92.01(b) Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Ancillary Works 50.00 Result: 811.09 Birr/each
Guide Posts (reinforced concrete C- 20)
*including class C-concrete footing
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 5.60
2 Labour I 15 120.00 12.62 1,514.24 62.13
3 Mason I 2 16.00 22.17 354.69 14.55
4 Driver II 1 8.00 34.10 272.84 11.19
5 Equ.op.III 1 4.00 39.79 159.15 6.53
6
Labour Sub-total 2,437.34 - 8.38
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 100.00
2 Pick Up,Double cab,4*4,Diesel - - 191.31 178.96 370.27 - -
3 Hand Tools
4
Equipment Sub-total 1,707.03 352.49 5.87
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 3.29 1,517.91 6.09
2 Cement Quintal 255.78 23.02 5,888.49 23.62
3 Crushed Aggregate M3 243.73 84.20 4.54 1,105.73 382.00 4.43
4 Guide Posts No 288.44 4.55 50.00 14,421.76 227.69 57.84
5 Reflector No 20.00 100.00 2,000.00 - 8.02
Material Sub-total 24,933.89 609.69 85.75
Total Cost per crew day 29,078.26 962.18

Average daily production (ADP) = 50.00


Activity operational cost per crew day / ADP = 581.57 Birr/each
Total Oper. unit cost including 35% overhead & profit = 785.11 Birr/each
Activity replacement cost per crew day / ADP = 19.24 Birr/each
Total Repl. unit cost including 35% overhead & profit = 25.98 Birr/each
Total Activity Unit Rate = 811.09 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 112 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 92.01(c) Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Ancillary Works 20.00 No. Result: 803.77 Birr/each
Kilometer posts (reinforced concrete C- 20)
*including class c-concrete footing
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 6.71
2 Labour I 11 88.00 12.62 1,110.44 54.61
3 Mason I 2 16.00 22.17 354.69 17.44
4 Driver II 1 8.00 34.10 272.84 13.42
5 Equ.op.III 1 4.00 39.79 159.15 7.83
6
Labour Sub-total 2,033.54 - 17.74
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 100.00
2 Pick Up,Double cab,4*4,Diesel - - 191.31 178.96 370.27 - -
3 Hand Tools
4
Equipment Sub-total 1,707.03 352.49 14.89
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 0.76 350.11 4.53
2 Cement Quintal 255.78 5.31 1,358.19 17.59
3 Crushed Aggregate M3 243.73 84.20 1.01 246.52 3.19
4 Km Post No 288.44 4.55 20.00 5,768.70 91.07 74.69
Material Sub-total 7,723.52 91.07 67.37
Total Cost per crew day 11,464.09 443.56

Average daily production (ADP) = 20.00 No.


Activity operational cost per crew day / ADP = 573.20 Birr/each
Total Oper. unit cost including 35% overhead & profit = 773.83 Birr/each
Activity replacement cost per crew day / ADP = 22.18 Birr/each
Total Repl. unit cost including 35% overhead & profit = 29.94 Birr/each
Total Activity Unit Rate = 803.77 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 113 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 93.01 Category: Labour intensive ADP= March 21, 2017
Activity Name: Galvanized guard rails on steel post Scope: Ancillary Works 20.00 m Result: 494.17 Birr/m

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Welder I 1 8.00 20.46 163.70 40.38
2 Labour I 2 16.00 12.62 201.90 49.80
3 Equ.op.III 1 1.00 39.79 39.79 9.81
Labour Sub-total 405.39 - 5.60
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
Equipment Sub-total 426.76 88.12 5.90
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Guardrail m 320.04 20.00 6,400.73 - 100.00
2
Material Sub-total 6,400.73 - 88.49
Total Cost per crew day 7,232.88 88.12

Average daily production (ADP) = 20.00 m


Activity operational cost per crew day / ADP = 361.64 Birr/m
Total Oper. unit cost including 35% overhead & profit = 488.22 Birr/m
Activity replacement cost per crew day / ADP = 4.41 Birr/m
Total Repl. unit cost including 35% overhead & profit = 5.95 Birr/m
Total Activity Unit Rate = 494.17 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 114 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 94.01(a)(i) Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Ancillary Works 10.00 m2 Result: 1,572.79 Birr/m2
Traffic signs (Area not exceeding 2 m²)
*thickness 2mm and Area not exceeding 2sq m.
Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Welder I 1 8.00 20.46 163.70 40.38
2 Labour I 2 16.00 12.62 201.90 49.80
3 Equ.op.III 1 1.00 39.79 39.79 9.81
Labour Sub-total 405.39 - 3.51
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
Equipment Sub-total 426.76 88.12 3.69
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sign faces made by Alluminium alloy M2 1,073.00 10.00 10,730.00 - 100.00
2
Material Sub-total 10,730.00 - 92.80
Total Cost per crew day 11,562.15 88.12

Average daily production (ADP) = 10.00 m2


Activity operational cost per crew day / ADP = 1,156.21 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 1,560.89 Birr/m2
Activity replacement cost per crew day / ADP = 8.81 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 11.90 Birr/m2
Total Activity Unit Rate = 1,572.79 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *1 m2 aluminium plate used for three signs

Stadia Engineering Works Consultant Plc Page 115 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 94.01(a)(ii) Category: Labour intensive ADP= March 21, 2017
Activity Name: Traffic signs (Area exceeding 2 m²) Scope: Ancillary Works 8.00 Result: 1,603.85 Birr/m2

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Welder I 1 8.00 20.46 163.70 40.38
2 Labour I 2 16.00 12.62 201.90 49.80
3 Equ.op.III 1 1.00 39.79 39.79 9.81
Labour Sub-total 405.39 - 4.31
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
Equipment Sub-total 426.76 88.12 4.53
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sign faces made by Alluminium alloy M2 1,073.00 8.00 8,584.00 - 100.00
2
Material Sub-total 8,584.00 - 91.16
Total Cost per crew day 9,416.15 88.12

Average daily production (ADP) = 8.00


Activity operational cost per crew day / ADP = 1,177.02 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 1,588.97 Birr/m2
Activity replacement cost per crew day / ADP = 11.02 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 14.87 Birr/m2
Total Activity Unit Rate = 1,603.85 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 116 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 94.02(a) Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Ancillary Works 20.00 Result: 730.71 Birr/each
Sign Supports (Concrete Class C 20/20)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carpenter I 1 8.00 40.93 327.40 29.30
2 Bar Sett.I 1 8.00 30.69 245.55 21.97
3 Labour I 5 40.00 12.62 504.75 45.17
4 Equ.op.III 1 1.00 39.79 39.79 3.56
Labour Sub-total 1,117.49 - 10.46
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 1.00 42.64 8.28 50.92 42.64 8.28 8.67
2 Concrete Vibrator 5 HP 1.00 22.48 2.43 24.91 22.48 2.43 4.57
3 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 86.76
Equipment Sub-total 491.88 98.83 4.60
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 0.32 147.69 1.63
2 Cement Quintal 255.78 2.88 736.65 8.12
3 Crushed Aggregate M3 243.73 84.20 0.48 116.99 40.42 1.29
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.21 4,075.33 44.90
5 Lumber m3 10,000.00 0.40 4,000.00 44.07
Material Sub-total 9,076.66 40.42 84.94
Total Cost per crew day 10,686.03 139.25

Average daily production (ADP) = 20.00


Activity operational cost per crew day / ADP = 534.30 Birr/each
Total Oper. unit cost including 35% overhead & profit = 721.31 Birr/each
Activity replacement cost per crew day / ADP = 6.96 Birr/each
Total Repl. unit cost including 35% overhead & profit = 9.40 Birr/each
Total Activity Unit Rate = 730.71 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 117 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 94.02(b) Category: Labour intensive ADP= March 21, 2017
Activity Name: Sign Supports (Steel) Scope: Ancillary Works 20.00 No. Result: 555.79 Birr/Each

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason I 1 8.00 22.17 177.34 42.32
2 Equ.op.III 1 1.00 39.79 39.79 9.50
3 Labour I 2 16.00 12.62 201.90 48.18
Labour Sub-total 419.03 - 5.14
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total 514.88 426.76 88.12 5.24
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Steel Pipes (Dia. 75mm) No 600.00 12.17 7,300.00 - 100.00
2
Material Sub-total 7,300.00 - 89.62
Total Cost per crew day 8,145.79 88.12

Average daily production (ADP) = 20.00 No.


Activity operational cost per crew day / ADP = 407.29 Birr/Each
Total Oper. unit cost including 35% overhead & profit = 549.84 Birr/Each
Activity replacement cost per crew day / ADP = 4.41 Birr/Each
Total Repl. unit cost including 35% overhead & profit = 5.95 Birr/Each
Total Activity Unit Rate = 555.79 Birr/Each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 118 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 94.03 Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Ancillary Works 4.80 m3 Result: 2,662.35 Birr/m3
Concrete in road sign footings including exc.
and backfilling (Class 15/20)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 6.24
2 Labour I 16 128.00 12.62 1,615.19 73.89
3 Mason I 2 16.00 22.17 354.69 16.23
4 Driver II 0 - 34.10 -
5 Equ.op.III 1 2.00 39.79 79.58 3.64
6
Labour Sub-total 2,185.87 - 24.16
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 100.00
2 Pick Up,Double cab,4*4,Diesel - - 191.31 178.96 370.27 - -
3 Hand Tools
4
Equipment Sub-total 853.51 176.24 9.43
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 1.92 886.15 14.75
2 Cement Quintal 255.78 17.28 4,419.88 73.57
3 Crushed Aggregate M3 243.73 84.20 2.88 701.95 242.51 11.68
4
Material Sub-total 6,007.98 242.51 66.41
Total Cost per crew day 9,047.37 418.75

Average daily production (ADP) = 4.80 m3


Activity operational cost per crew day / ADP = 1,884.87 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,544.57 Birr/m3
Activity replacement cost per crew day / ADP = 87.24 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 117.77 Birr/m3
Total Activity Unit Rate = 2,662.35 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 119 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 95.01(a) Category: Labour intensive ADP= March 21, 2017
Activity Name: White lines (broken or unbroken) (width of Scope: Ancillary Works 5.00 km Result: 12,506.72 Birr/Km
100mm)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.II 1 8.00 28.42 227.36 31.06
2 Labour I 5 40.00 12.62 504.75 68.94
3
Labour Sub-total 732.11 - 1.64
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Road Marking Machine - 8.00 501.46 223.15 724.61 4,011.70 1,785.22 100.00
2 Hand Tools
3
4
Equipment Sub-total 4,011.70 1,785.22 9.01
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Thermoplastic paint l 37.44 1,000.00 37,439.14 94.09
2 Glass beads Kg 26.00 90.50 2,353.00 5.91
3
Material Sub-total 39,792.14 - 89.35
Total Cost per crew day 44,535.95 1,785.22

Average daily production (ADP) = 5.00 km


Activity operational cost per crew day / ADP = 8,907.19 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 12,024.71 Birr/Km
Activity replacement cost per crew day / ADP = 357.04 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 482.01 Birr/Km
Total Activity Unit Rate = 12,506.72 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 120 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 95.01(b) Category: Labour intensive ADP= March 21, 2017
Activity Name: Yellow lines (broken or unbroken) (width of Scope: Ancillary Works 5.00 km Result: 12,506.72 Birr/Km
100mm)

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Equ.op.II 1 8.00 28.42 227.36 31.06
2 Labour I 5 40.00 12.62 504.75 68.94
3
Labour Sub-total 732.11 - 1.64
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Road Marking Machine - 8.00 501.46 223.15 724.61 4,011.70 1,785.22 100.00
2 Hand Tools
3
4
Equipment Sub-total 4,011.70 1,785.22 9.01
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Thermoplastic paint l 37.44 1,000.00 37,439.14 94.09
2 Glass beads Kg 26.00 90.50 2,353.00 5.91
3
Material Sub-total 39,792.14 - 89.35
Total Cost per crew day 44,535.95 1,785.22

Average daily production (ADP) = 5.00 km


Activity operational cost per crew day / ADP = 8,907.19 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 12,024.71 Birr/Km
Activity replacement cost per crew day / ADP = 357.04 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 482.01 Birr/Km
Total Activity Unit Rate = 12,506.72 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 121 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 95.04(a) Category: ADP= March 21, 2017
Activity Name: In situ asphalt Speed Bumps Scope: Ancillary Works 40.00 Result: 3,829.40 Br / m

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 10.37
2 Labour I 5 40.00 12.62 504.75 38.38
3 Equ.op.III 1 3.00 39.79 119.37 9.08
4 St.eq.opII 1 4.00 28.42 113.68 8.64
5 Equ.op.II 1 4.00 28.42 113.68 8.64
6 Carpenter I 1 8.00 40.93 327.40 24.89
Labour Sub-total 1,315.30 1.23
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 3.00 426.76 88.12 514.88 1,280.27 264.37 26.13
2 Roller,Vibrator,2Drums 8 ton 4.00 478.94 281.42 760.36 1,915.76 1,125.67 39.11
3 Street Sweeper, Self Prop 1-2m 4.00 425.74 118.67 544.41 1,702.98 474.68 34.76
4 Hand Tools
5
6 8.00
Equipment Sub-total 4,899.01 1,864.72 4.59
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Asphalt Hot Mix M3 3,135.65 152.50 32.00 100,340.72 4,880.07 99.84
2 Lumber m3 10,000.00 0.006 64.00 - 0.06
3 Equaliptus Pole (Dia. 100mm, 8m long) No 100.00 1.000 100.00 - 0.10
Material Sub-total 100,504.72 4,880.07 94.18
Total Cost per crew day 106,719.03 6,744.79

Average daily production (ADP) = 40.00


Activity operational cost per crew day / ADP = 2,667.98 Br / m
Total Oper. unit cost including 35% overhead & profit = 3,601.77 Br / m
Activity replacement cost per crew day / ADP = 168.62 Br / m
Total Repl. unit cost including 35% overhead & profit = 227.64 Br / m
Total Activity Unit Rate = 3,829.40 Br / m

Stadia Engineering Works Consultant Plc Page 122 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 95.04(b) Category: ADP= March 21, 2017
Activity Name: In situ asphalt Rumble Strips Scope: Ancillary Works 12.00 Result: 907.86 Br / m

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 10.70
2 Labour I 5 40.00 12.62 504.75 39.57
3 Equ.op.III 1 2.00 39.79 79.58 6.24
4 St.eq.opII 1 4.00 28.42 113.68 8.91
5 Equ.op.II 1 4.00 28.42 113.68 8.91
6 Carpenter I 1 8.00 40.93 327.40 25.67
Labour Sub-total 1,275.51 20.34
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 19.08
2 Roller,Vibrator,2Drums 8 ton 4.00 478.94 281.42 760.36 1,915.76 1,125.67 42.84
3 Street Sweeper, Self Prop 1-2m 4.00 425.74 118.67 544.41 1,702.98 474.68 38.08
4 Hand Tools
5
6 8.00
Equipment Sub-total 4,472.25 1,776.60 71.31
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Asphalt Hot Mix M3 3,135.65 152.50 0.14 451.53 21.96 86.25
2 Lumber m3 10,000.00 0.007 72.00 - 13.75
3
Material Sub-total 523.53 21.96 8.35
Total Cost per crew day 6,271.30 1,798.56

Average daily production (ADP) = 12.00


Activity operational cost per crew day / ADP = 522.61 Br / m
Total Oper. unit cost including 35% overhead & profit = 705.52 Br / m
Activity replacement cost per crew day / ADP = 149.88 Br / m
Total Repl. unit cost including 35% overhead & profit = 202.34 Br / m
Total Activity Unit Rate = 907.86 Br / m

Stadia Engineering Works Consultant Plc Page 123 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 96.01 Category: Labour intensive ADP= March 21, 2017
Activity Name: Stockpiling of Topsoil Scope: Ancillary Works 1,120.00 Result: 66.80 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Const.For II 1 8.00 73.89 591.15 17.69
2 Equ.op.IV 2 16.00 102.31 1,637.02 48.97
3 Equ.op.III 4 25.27 39.79 1,005.33 30.08
4 Labour II 1 8.00 13.64 109.13 3.26
Labour Sub-total 3,342.62 8.86
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Crawler Dozer 280-330 HP 16.00 1,334.09 746.61 2,080.71 21,345.50 11,945.82 62.07
2 Dump truck,6*4 (12m3) 12M3 17.33 481.75 104.04 585.79 8,350.33 1,803.31 24.28
3 Loader, Wheel 2-2.5 M3 7.93 591.65 496.23 1,087.88 4,693.76 3,936.77 13.65
4
5
Equipment Sub-total 3,754.38 34,389.59 17,685.90 91.14
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 37,732.22 17,685.90

Average daily production (ADP) = 1,120.00


Activity operational cost per crew day / ADP = 33.69 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 45.48 Birr/m3
Activity replacement cost per crew day / ADP = 15.79 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 21.32 Birr/m3
Total Activity Unit Rate = 66.80 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 124 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 96.02(a) Category: Labour intensive ADP= March 21, 2017
Activity Name: Top-soiling Scope: Ancillary Works 60.00 Result: 49.64 Birr/m3

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.37
2 Equ.op.III 1 1.35 39.79 53.86 4.49
3 Labour I 10 80.00 12.62 1,009.49 84.14
4
Labour Sub-total 1,199.77 63.19
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 0.93 481.75 104.04 585.79 447.34 96.61 64.02
2 Loader, Wheel 2-2.5 M3 0.43 591.65 496.23 1,087.88 251.45 210.90 35.98
3
4
5
Equipment Sub-total 1,673.67 698.79 307.50 36.81
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1
2
Material Sub-total - -
Total Cost per crew day 1,898.56 307.50

Average daily production (ADP) = 60.00


Activity operational cost per crew day / ADP = 31.64 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 42.72 Birr/m3
Activity replacement cost per crew day / ADP = 5.13 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 6.92 Birr/m3
Total Activity Unit Rate = 49.64 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 125 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 96.02(b) Category: Labour intensive ADP= March 21, 2017
Activity Name: Provide and apply chemical fertilizers Scope: Ancillary Works 1.88 Result: 17,154.42 Birr/t

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.51
2 Equ.op.III 1 1.00 39.79 39.79 3.36
3 Labour I 10 80.00 12.62 1,009.49 85.14
4
Labour Sub-total 1,185.70 5.00
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand tools
3
4
5
Equipment Sub-total 514.88 426.76 88.12 1.80
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Urea t 11,800.00 1.875 22,125.00 - 100.00
2
Material Sub-total 22,125.00 - 93.21
Total Cost per crew day 23,737.46 88.12

Average daily production (ADP) = 1.88


Activity operational cost per crew day / ADP = 12,659.98 Birr/t
Total Oper. unit cost including 35% overhead & profit = 17,090.97 Birr/t
Activity replacement cost per crew day / ADP = 47.00 Birr/t
Total Repl. unit cost including 35% overhead & profit = 63.45 Birr/t
Total Activity Unit Rate = 17,154.42 Birr/t

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 126 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 96.03(a) Category: Labour intensive ADP= March 21, 2017
Activity Name: Planting of grass cuttings Scope: Ancillary Works 0.05 Result: 113,415.69 Birr/ha

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.51
2 Equ.op.III 1 1.00 39.79 39.79 3.36
3 Labour I 10 80.00 12.62 1,009.49 85.14
4
Labour Sub-total 1,185.70 28.83
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand tools
3
4
5
Equipment Sub-total 514.88 426.76 88.12 10.38
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Grass Cuttings ha 50,000.00 0.050 2,500.00 - 100.00
2
Material Sub-total 2,500.00 - 60.79
Total Cost per crew day 4,112.46 88.12

Average daily production (ADP) = 0.05


Activity operational cost per crew day / ADP = 82,249.17 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 111,036.39 Birr/ha
Activity replacement cost per crew day / ADP = 1,762.45 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 2,379.31 Birr/ha
Total Activity Unit Rate = 113,415.69 Birr/ha

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 127 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 96.03(b) Category: Labour intensive ADP= March 21, 2017
Activity Name: Seeding Scope: Ancillary Works 0.10 Result: 56,707.85 Birr/ha

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.51
2 Equ.op.III 1 1.00 39.79 39.79 3.36
3 Labour I 10 80.00 12.62 1,009.49 85.14
4
Labour Sub-total 1,185.70 28.83
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand tools
3
4
5
Equipment Sub-total 514.88 426.76 88.12 10.38
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Grass Seeds ha 25,000.00 0.100 2,500.00 - 100.00
2
Material Sub-total 2,500.00 - 60.79
Total Cost per crew day 4,112.46 88.12

Average daily production (ADP) = 0.10


Activity operational cost per crew day / ADP = 41,124.59 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 55,518.19 Birr/ha
Activity replacement cost per crew day / ADP = 881.22 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 1,189.65 Birr/ha
Total Activity Unit Rate = 56,707.85 Birr/ha

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 128 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 96.04 Category: Labour intensive ADP= March 21, 2017
Activity Name: Replacement or replanting of trees and growth Scope: Ancillary Works 500.00 Result: 139.59 Birr/Each
management

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Labor Foreman 1 8.00 17.05 136.42 11.51
2 Equ.op.III 1 1.00 39.79 39.79 3.36
3 Labour I 10 80.00 12.62 1,009.49 85.14
4
Labour Sub-total 1,185.70 2.30
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand tools
3
4
5
Equipment Sub-total 514.88 426.76 88.12 0.83
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Tree No 100.00 500.000 50,000.00 - 100.00
2
Material Sub-total 50,000.00 - 96.88
Total Cost per crew day 51,612.46 88.12

Average daily production (ADP) = 500.00


Activity operational cost per crew day / ADP = 103.22 Birr/Each
Total Oper. unit cost including 35% overhead & profit = 139.35 Birr/Each
Activity replacement cost per crew day / ADP = 0.18 Birr/Each
Total Repl. unit cost including 35% overhead & profit = 0.24 Birr/Each
Total Activity Unit Rate = 139.59 Birr/Each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 129 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 99.02(a) Category: Labour intensive ADP= March 21, 2017
Activity Name: Masonry Safety Barrier Scope: Ancillary Works 14.00 Result: 1,007.61 Birr/m

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Mason Foreman 1 4.00 54.57 218.27 7.95
2 Equ.op.III 1 3.00 39.79 119.37 4.35
3 Mason I 5 40.00 22.17 886.72 32.30
4 Carpenter II 1 4.00 54.57 218.27 7.95
5 Labour II 5 40.00 13.64 545.67 19.88
6 Labour I 8 60.00 12.62 757.12 27.58
Labour Sub-total 2,745.42 - 29.83
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Dump truck,6*4 (12m3) 12M3 2.00 481.75 104.04 585.79 963.50 208.07 61.96
2 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 38.04
3 Hand Tools
Equipment Sub-total 1,673.67 1,555.15 704.31 16.90
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Cement Quintal 255.78 8.40 2,148.55 - 43.82
2 Sand m3 461.54 2.02 930.46 - 18.98
3 Stone M3 106.02 33.03 16.10 1,707.00 531.82 34.82
4 Lean Concrete M3 1,735.05 169.18 0.05 91.09 8.88 1.86
5 Formwork m2 172.07 5.51 0.15 25.81 0.83 0.53
Material Sub-total 4,902.92 541.53 53.27
Total Cost per crew day 9,203.48 1,245.83

Average daily production (ADP) = 14.00


Activity operational cost per crew day / ADP = 657.39 Birr/m
Total Oper. unit cost including 35% overhead & profit = 887.48 Birr/m
Activity replacement cost per crew day / ADP = 88.99 Birr/m
Total Repl. unit cost including 35% overhead & profit = 120.13 Birr/m
Total Activity Unit Rate = 1,007.61 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 130 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2 Activity No : 99.02(b) Category: Labour intensive ADP= March 21, 2017
Activity Name: Scope: Ancillary Works 30.00 Result: 845.03 Birr/m
Safety Barrier Precast Concrete as per drawing

Labour
Hours per Hourly cost
Item No Type Daily cost % for operation
crew day (Indexed)
1 Carpenter I 1 8.00 40.93 327.40 29.30
2 Bar Sett.I 1 8.00 30.69 245.55 21.97
3 Labour I 5 40.00 12.62 504.75 45.17
4 Equ.op.III 1 1.00 39.79 39.79 3.56
Labour Sub-total 1,117.49 - 6.16
Equipment
Hours per
Item No Type Capacity Hourly cost Daily cost % for Operaton
crew day
Oper. C. Repl.C. Total. C. Oper. C. Repl.C.
1 Concrete Mixer,Trailer Mounted 250 Lit 1.00 42.64 8.28 50.92 42.64 8.28 8.67
2 Concrete Vibrator 5 HP 1.00 22.48 2.43 24.91 22.48 2.43 4.57
3 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 86.76
Equipment Sub-total 491.88 98.83 2.71
Material
Item No Type Unit Unit price Quantity Daily cost % for Operaton
Oper. C. Repl. C. Oper. C. Repl. C.
1 Sand m3 461.54 4.36 2,010.46 12.17
2 Cement Quintal 255.78 39.20 10,027.60 60.70
3 Crushed Aggregate M3 243.73 84.20 6.53 1,592.55 550.19 9.64
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.05 1,015.52 6.15
5 Formwork m2 172.07 5.51 10.89 1,873.84 59.98 11.34
Material Sub-total 16,519.96 550.19 91.12
Total Cost per crew day 18,129.33 649.02

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 604.31 Birr/m
Total Oper. unit cost including 35% overhead & profit = 815.82 Birr/m
Activity replacement cost per crew day / ADP = 21.63 Birr/m
Total Repl. unit cost including 35% overhead & profit = 29.21 Birr/m
Total Activity Unit Rate = 845.03 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 131 of 145


JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Overhead and Profit Factor


Overhead & Profit Factor 1.35

Date March 21, 2017

Project Duration
Total Construction Period (Months) 12
Mobilization Period (Months) 0

Stadia Engineering Works Consultant PLC Page 1 of 145


JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Calculation Of Hourly Indexed Salary of Direct Labour


I.Labor Classification
Item No. I SUPERVISOR CLASS
1 Labourer Foreman
2 Quarry Foreman
3 Quarry Supervisor
4 Mason Foreman
5 Carpenter Foreman
6 Construction Foreman
7 Superintendant I
8 Superintendant II
Item No. II TECHNICAL CLASS
1 Electrician II
2 Mechanic II
3 Welder II
4 Electrician III
5 Mechanic III
6 Welder I
Item No. III OPERATORS CLASS
1 Equipment Operator I
2 Equipment Operator II
3 Equipment Operator III
4 Equipment Operator IV
5 Equipment Operator V
6 Sta.Equipment Operator I
7 Sta.Equipment Operator II
8 Sta.Equipment Operator III
9 Stat.Equip. Oper. IV
Item No. IV TRADEMEN CLASS
1 Powder man I
2 Powder man II
3 Barsetter I
4 Barsetter II
5 Carpenter I
6 Carpenter II
7 Carpenter III
8 Mason I
9 Mason II
10 Mason III
Item No. V SKILLED CLASS
1 Labourer II
2 Helper II
3 Helper III
4 Labourer III
Item No. VI UNSKILLED CLASS
1 Labourer I
2 Helper I

Stadia Engineering Works Consultant PLC Page 1 of 145


JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Calculation Of Hourly Indexed Salary of Direct Labour

II. Working Days per Month


a) No. of Working days per week (Monday - Saturday)= 6 day/week
b) No. of Working hours for one working day= 8 hour/day
c) Working hours/week (a*b)= 48 hour/week
d) Distributed Working hours/day in a week (c/a)= 8 hour/day
e) Working weeks/year (365.25days/7days)= 52.18 week/year
f) Working hours/month (e*c/12 months)= 208.71 hour/month
g) Working days/month (f/d)= 26.09 day/month

III.PAID NON-PRODUCTION DAYS

1.Annual leave per month,taking 19 days annual leave (19 days/12month)


= 1.58 day/month

2.Public holidays per month,12 holidays per year excluding Easter(12 days/12 month)
= 1.00 day/month

3.Leave for family event per month ,mourning,wedding..assuming 1.5 days per year(1.5 days /12 month)
= 0.13 day/month

4.Leave for special purpose per month,court case 6 days leave(6 days/12month)

= 0.50 day/month

5.Sick leave per month: (Treshhold is one month per year. Then assuming 15 days in a year(15 days/12
month)
= 1.25 day/month
6.Bad weather per month,assuming 60 rainy days in a year(60 days/12month)
= 5.00 day/month
7.Clothing and shoes supplies(assumed to be 1 day per month)
= 1.00 day/month
8.Pension/severance contribution to workers per month 11.00% (11.00%*g)
= 2.87 day/month
9.Maternal leave of 90 days - Considering a single mother's pregnancy once in 3 years
- Considering an average of 800 employees per month with Gender proportion (y)=40
(females)/1485 (Total no. of employee)=0.027; out of which 50.0% of them can give
birth
- Hence, the Maternal leave per month is = (90 days/ 36 month)*y*50.0%
= 0.03 day/month

Stadia Engineering Works Consultant PLC Page 2 of 145


JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Calculation Of Hourly Indexed Salary of Direct Labour


10.Perdiem for field workers ,by considering regular employees, 70.0% of the monthly salary (70.0%*g)
= 18.26 day/month
11.Insurance,by assuming 1.0% of monthly salary (1.0%*g)
= 0.26 day/month
12.Desert Allowance, 15.0% of basic salary (15.0%*g)
= 3.91 day/month

IV.LABOR INDEX FACTOR

1.Regular salary(g/g)= 1.000


2.Annual leave(1/g)= 0.061
3.Public holydays(2/g)= 0.038
4.Leave for family events(3/g)= 0.005
5.Leave for special purposes(4/g)= 0.019
6.Sick leave(5/g)= 0.048
7.Bad weather(6/g)= 0.192
8.Clothing & shoe(7/g)= 0.038
9.Pension/severance(8/g)= 0.110
10.Maternal leave(9/g)= 0.001
11.Perdiem for field workers(10/g)= 0.700
12.Insurance(11/g)= 0.010
13.Desert Allowance(12/g)= 0.150

Index factor = 2.372

Stadia Engineering Works Consultant PLC Page 3 of 145


JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Calculation Of Hourly Indexed Salary of Direct Labour


Table 1 Indexed Hourly Salary List March 21, 2017
Title Name

Grade A

Grade D

Monthly
Average

Indexed
Annual

Hourly
Salary
Salary

Salary

Salary
Daily
a b c=(a+b)/2 d=c*12 e=d/313 f=e/8*2.372
Driver I 2,800.00 2,800.00 2,800.00 33,600.00 107.35 31.83
Driver II 3,000.00 3,000.00 3,000.00 36,000.00 115.02 34.10
Driver III 3,200.00 3,200.00 3,200.00 38,400.00 122.68 36.38
Driver IV 3,400.00 3,400.00 3,400.00 40,800.00 130.35 38.65
Driver V 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
Equ.op.I 2,000.00 2,000.00 2,000.00 24,000.00 76.68 22.74
Equ.op.II 2,500.00 2,500.00 2,500.00 30,000.00 95.85 28.42
Equ.op.III 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
Equ.op.IV 9,000.00 9,000.00 9,000.00 108,000.00 345.05 102.31
Equ.op.V 10,000.00 10,000.00 10,000.00 120,000.00 383.39 113.68
St.eq.opI 2,000.00 2,000.00 2,000.00 24,000.00 76.68 22.74
St.eq.opII 2,500.00 2,500.00 2,500.00 30,000.00 95.85 28.42
St.eq.opIII 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
St.eq.opIV 9,000.00 9,000.00 9,000.00 108,000.00 345.05 102.31
St.eq.opV 12,000.00 12,000.00 12,000.00 144,000.00 460.06 136.42
Labour I 1,110.00 1,110.00 1,110.00 13,320.00 42.56 12.62
Labour II 1,200.00 1,200.00 1,200.00 14,400.00 46.01 13.64
Labour III 1,350.00 1,350.00 1,350.00 16,200.00 51.76 15.35
Helper I 1,650.00 1,650.00 1,650.00 19,800.00 63.26 18.76
Helper II 2,100.00 2,100.00 2,100.00 25,200.00 80.51 23.87
Carpenter I 3,600.00 3,600.00 3,600.00 43,200.00 138.02 40.93
Carpenter II 4,800.00 4,800.00 4,800.00 57,600.00 184.03 54.57
Bar Sett.I 2,700.00 2,700.00 2,700.00 32,400.00 103.51 30.69
Bar Sett.II 3,600.00 3,600.00 3,600.00 43,200.00 138.02 40.93
Powder Man I 2,700.00 2,700.00 2,700.00 32,400.00 103.51 30.69
Powder Man II 3,600.00 3,600.00 3,600.00 43,200.00 138.02 40.93
Mason I 1,950.00 1,950.00 1,950.00 23,400.00 74.76 22.17
Mason II 2,850.00 2,850.00 2,850.00 34,200.00 109.27 32.40
Mason III 4,200.00 4,200.00 4,200.00 50,400.00 161.02 47.75
Elec. I 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
Elec. II 5,700.00 5,700.00 5,700.00 68,400.00 218.53 64.80
Elec. III 6,300.00 6,300.00 6,300.00 75,600.00 241.53 71.62
Welder I 1,800.00 1,800.00 1,800.00 21,600.00 69.01 20.46
Welder II 4,000.00 4,000.00 4,000.00 48,000.00 153.35 45.47
Welder III 5,700.00 5,700.00 5,700.00 68,400.00 218.53 64.80
Mechanic I 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
Mechanic II 4,500.00 4,500.00 4,500.00 54,000.00 172.52 51.16
Mechanic III 6,300.00 6,300.00 6,300.00 75,600.00 241.53 71.62
Mat. Prod. Sup. 8,000.00 8,000.00 8,000.00 96,000.00 306.71 90.95
Batch plant Sup. 7,600.00 7,600.00 7,600.00 91,200.00 291.37 86.40
Mason Foreman 4,800.00 4,800.00 4,800.00 57,600.00 184.03 54.57
Carp. Foreman 5,700.00 5,700.00 5,700.00 68,400.00 218.53 64.80
Labor Foreman 1,500.00 1,500.00 1,500.00 18,000.00 57.51 17.05
Quarry Foreman 5,000.00 5,000.00 5,000.00 60,000.00 191.69 56.84
Safetyman I 3,000.00 3,000.00 3,000.00 36,000.00 115.02 34.10
Const.For I 4,000.00 4,000.00 4,000.00 48,000.00 153.35 45.47
Const.For II 6,500.00 6,500.00 6,500.00 78,000.00 249.20 73.89
Surveyor 8,000.00 8,000.00 8,000.00 96,000.00 306.71 90.95
Stadia Engineering Works Consultant PLC Page 4 of 145
JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Table 2: Basic Material Price List March 21, 2017

Price at Source Transportation Price at Site


Description Unit (Birr) cost (Birr) (Birr)
Diesel Litre - - 16.02
Petrol Litre - - 17.88
Cement Quintal 235.78 20.00 255.78
Binding wire Kg - - 32.00
Reinforcement Bar (Mild, Grade-40) t 18,260.00 800.00 19,060.00
Reinforcement Bar (Mild, Grade-60) t 19,130.00 800.00 19,930.00
Bitumen:
Bitumen - MC-30 Kg 27.39 1.00 28.39
Bitumen - AC-60/70 Kg 18.10 1.00 19.10
Bitumen - AC-80/100 Kg 25.00 1.00 26.00
Bitumen - AC RC-70 Kg 28.07 1.00 29.07
Bitumen - MC-3000 Kg 25.60 1.00 26.60
Explosive Material
Ammonium Nitrate Kg - - 60.00
Power Jell Kg - - 90.00
Electrical Detonator No - - 65.00
Cord m - - 16.00
Connecting wire m - - 12.00
Lumber m3 - - 10,000.00

Equaliptus Pole (Dia. 100mm, 8m long) No - - 100.00


Sand m 3
- - 461.54
Nails kg - - 26.50
Chipwood No - - 420.00
Elastomeric Bearing
(400mm*300mm*69mm) No - - 7,452.00
Elastomeric Bearing
(400mm*250mm*45mm) No - - 4,050.00
Electrode, #4 Kg - - 79.60
Bituminous Paper, (2mm thick) M2 - - 35.00
PVC Pipe, 110mm No - - 184.80
Perforated PVC Pipe, 150mm No - - 369.60
Gabion boxes, 1m*1m*1m No 364.50 10.00 374.50
Gabion boxes, 2m*1m*1m No - - 686.58
Gabion boxes, 1.5m*1m*1m No - - 561.75

PVC-coated Gabion boxes,3*3*1*1m No 3,841.76 40.00 3,881.76


Geo-Textile filter fabric M2 - - 75.00
Impermeable Membrane M2 - - 25.00
Geogrid M 2
195.18 8.00 203.18
Thermoplastic paint l - - 37.44
Glass beads Kg - - 26.00
Sign faces made by Alluminium alloy M2 - - 1,073.00
Tree No - - 100.00
Ply wood No - - 60.00
Guardrail m - - 320.04
Thermoplastic paint l - - 37.44
Steel Pipes (Dia. 75mm) No - - 600.00
Steel Pipes (Dia. 150mm) No - - 1,000.00
Split Pipes (Dia. 150mm) No - - 1,800.00
Grass Cuttings ha - - 50,000.00
Grass Seeds ha - - 25,000.00
Grass Seeds ha - - 25,000.00
Urea t 11,000.00 800.00 11,800.00
Reflector No - - 20.00

Stadia Engineering Works Consultant PLC Page 1 of 145


JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Table 3: Equipment Cost March 21, 2017


Equipment Salvage Tyre Depreciation
Equipment Life Time Interest
Initial Cost Value Cost
Item Equipment Type Rated
HP (about)
Capacity (F/8hrs/ 250 Unit Price Tyre (E((1.03)G-1)
((E-L-H)/F)
(Birr) (Hours) days) 10% of E Size Qty Price (Set) Life /F)
(Birr/Hr)
(Yrs) (Birr) (Birr) (Hour) (Birr/Hr)

A B C D E F G H I J K L M N O
1 Dump truck,6*4 (8m3) 8M3 270 950,000 12,000 6.0 95,000 12-20,12R20 10 10,500.00 105,000.00 1,500 62.50 15.36
2 Dump truck,6*4 (12m3) 12M3 336 1,114,653 12,000 6.0 111,465 1200R20 11 10,500.00 115,500.00 1,500 73.97 18.03
3 Water truck,6*4 20000Lits 240 1,600,000 14,000 7.0 160,000 12R22.5 10 10,500.00 105,000.00 1,800 95.36 26.27
4 Asphalt Distributor 6000 Lit 200 4,800,000 14,000 7.0 480,000 11*20,12*20 6 10,500.00 63,000.00 2,200 304.07 78.81
5 Drill, Self Prop, Crawler Type 4500 Kg 200 5,400,000 10,000 5.0 540,000 - - 486.00 86.01
6 Excavator, Wheel Type 1.09M3 166 3,854,783 12,000 6.0 385,478 15.5*25 4 16,500.00 66,000.00 2,500 283.61 62.34
7 Excavator, Crawler Type 1.76M3 203 6,494,348 12,000 6.0 649,435 - - 487.08 105.02
8 Motor Grader 145-165 HP 165 7,399,565 10,000 5.0 739,957 13*24,14*24 6 13,000.00 78,000.00 1,300 658.16 117.86
9 Loader, Crawler 2-2.5 M3 189 7,421,304 10,000 5.0 742,130 - - 667.92 118.20
10 Loader, Wheel 2-2.5 M3 154 4,661,154 10,000 5.0 466,115 23.5*25 4 20,000.00 80,000.00 2,200 411.50 74.24
11 Roller,Vibrator,2Drums 8 ton 111.1 3,020,435 12,000 6.0 302,043 - - 226.53 48.84
12 Roller,Vibrator,2Drums 12 ton 130 3,258,261 12,000 6.0 325,826 - - 244.37 52.69
13 Roller,Pneumatic 10 ton 131 3,062,609 15,000 7.5 306,261 11*20 7 9,000.00 63,000.00 2,500 179.56 50.67
14 Crawler Dozer 280-330 HP 303 9,899,000 16,000 8.0 989,900 - - 556.82 165.05
15 Crusher Plant 51-100 TPH 370 15,000,000 17,000 8.5 1,500,000 10*20 16 9,000.00 144,000.00 4,000 785.65 252.03
16 Asphalt Paver, Crawler 2.5-8m 205 9,391,739 15,000 7.5 939,174 - - 563.50 155.39
17 Asphalt Plant 130-150TPH 1100 6,050,000 18,000 9.0 605,000 10*20 30 9,000.00 270,000.00 4,000 287.50 102.44
18 Asphalt Kettle, Trailer Mounted 1500-2000Lit 10 1,202,652 12,000 6.0 120,265 7.5*18 2 5,000.00 10,000.00 2,500 89.37 19.45
19 Spreader, Aggregate 5-7m 300 5,000,000 15,000 7.5 500,000 10*20 4 9,000.00 36,000.00 2,200 297.60 82.73
20 Concrete Vibrator 5 HP 5 18,700 8,000 4.0 1,870 - - 2.10 0.29
21 Concrete Mixer,Trailer Mounted 250 Lit 15 118,800.0 16,000 8.0 11,880 6.5*16 2 5,000.00 10,000.00 2,500 6.06 1.98
22 Concrete Mixer,Trailer Mounted 500 Lit 25 196,735.6 16,000 8.0 19,674 6.5*16 2 5,000.00 10,000.00 2,500 10.44 3.28
23 Air Compressor 600CFM 155 249,330 15,000 7.5 24,933 7.5*16 2 7,000.00 14,000.00 2,500 14.03 4.13
24 Water Pump 230 Lit/min 8 29,333 8,000 4.0 2,933 - - 3.30 0.46
25 Street Sweeper, Self Prop 1-2m 70 1,231,985 11,000 5.5 123,199 11.2*20 4 12,000.00 48,000.00 2,200 96.44 19.77
26 AC Welder, Diesel 300-400AMP 55 150,000 10,000 5.0 15,000 - - 13.50 2.39
27 Pick Up,Double cab,4*4,Diesel - 102 1,732,174 11,000 5.5 173,217 205R 16c,6J 4 5,000.00 20,000.00 2,100 139.91 27.80
28 Plate Compactor 5 37,500 8,000 4.0 3,750 - 4.22 0.59
29 Road Marking Machine 85 2,600,000 15,000 7.5 260,000 4 7,000.00 28,000.00 1,500 154.13 43.02
30 Asphalt Cutter 80,000 6,000 3.0 8,000 - 12.00 1.24

Stadia Engineering Works Consultant PLC Page 1 of 145


JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Table 3: Equipment Cost March 21, 2017

Tyre
Insurance Repair Cost Fuel Consumption Service Cost Operating Cost Owning Cost O&O Cost
Cost
Item Equipment Type Rated
HP (about)
Capacity Cost (Cost=U*
Rate % of (N*R) Factor (D*T) % of (V*W) (L/M) (S+V+X+Y) (N+O+Q) (Z+AA)
(E*P*G/F) Fuel Rate)
% N (Birr/Hr) (Lit/Hr/Hp) (Lit/Hr) V (Birr/Hr) (Birr/Hr) (Birr/Hr) (Birr/Hr) (Birr/Hr)
(Birr/Hr) (Birr/Hr)

A B C D P Q R S T U V W X Y Z AA AB
1 Dump truck,6*4 (8m3) 8M3 270 2.16% 10.26 80% 50.00 0.0591 16.0 255.63 20% 51.13 70.00 426.76 88.12 514.88
2 Dump truck,6*4 (12m3) 12M3 336 2.16% 12.04 80% 59.18 0.0535 18.0 287.98 20% 57.60 77.00 481.75 104.04 585.79
3 Water truck,6*4 20000Lits 240 3.00% 24.00 80% 76.29 0.0625 15.0 240.30 20% 48.06 58.33 422.98 145.63 568.61
4 Asphalt Distributor 6000 Lit 200 1.50% 36.00 80% 243.26 0.1200 24.0 384.48 25% 96.12 28.64 752.49 418.89 1,171.38
5 Drill, Self Prop, Crawler Type 4500 Kg 200 1.00% 27.00 70% 340.20 0.1100 22.0 352.44 10% 35.24 - 727.88 599.01 1,326.89
6 Excavator, Wheel Type 1.09M3 166 0.45% 8.67 70% 198.53 0.1090 18.1 289.87 25% 72.47 26.40 587.26 354.62 941.88
7 Excavator, Crawler Type 1.76M3 203 0.45% 14.61 70% 340.95 0.1090 22.1 354.47 25% 88.62 - 784.05 606.71 1,390.76
8 Motor Grader 145-165 HP 165 0.50% 18.50 50% 329.08 0.1270 21.0 335.70 25% 83.92 60.00 808.70 794.52 1,603.22
9 Loader, Crawler 2-2.5 M3 189 0.45% 16.70 90% 601.13 0.1000 18.9 302.78 25% 75.69 - 979.60 802.82 1,782.42
10 Loader, Wheel 2-2.5 M3 154 0.45% 10.49 60% 246.90 0.1000 15.4 246.71 25% 61.68 36.36 591.65 496.23 1,087.88
11 Roller,Vibrator,2Drums 8 ton 111.1 0.40% 6.04 70% 158.57 0.1500 16.7 266.97 20% 53.39 - 478.94 281.42 760.36
12 Roller,Vibrator,2Drums 12 ton 130 0.40% 6.52 70% 171.06 0.1600 20.8 333.22 20% 66.64 - 570.92 303.58 874.49
13 Roller,Pneumatic 10 ton 131 0.40% 6.13 70% 125.69 0.1600 21.0 335.78 20% 67.16 25.20 553.82 236.35 790.18
14 Crawler Dozer 280-330 HP 303 0.50% 24.75 90% 501.14 0.1320 40.0 640.74 30% 192.22 - 1,334.09 746.61 2,080.71
15 Crusher Plant 51-100 TPH 370 1.00% 75.00 90% 707.08 0.2000 74.0 1,185.48 33% 391.21 36.00 2,319.77 1,112.67 3,432.45
16 Asphalt Paver, Crawler 2.5-8m 205 1.50% 70.44 80% 450.80 0.0800 16.4 262.73 25% 65.68 - 779.21 789.34 1,568.55
17 Asphalt Plant 130-150TPH 1100 1.50% 45.38 90% 258.75 0.1000 110.0 1,762.20 33% 581.53 67.50 2,669.98 435.31 3,105.29
18 Asphalt Kettle, Trailer Mounted 1500-2000Lit 10 1.00% 6.01 50% 44.68 2.5000 25.0 400.50 13% 50.06 4.00 499.25 114.83 614.07
19 Spreader, Aggregate 5-7m 300 1.00% 25.00 80% 238.08 0.1410 42.3 677.65 20% 135.53 16.36 1,067.62 405.33 1,472.95
20 Concrete Vibrator 5 HP 5 0.40% 0.04 50% 1.05 0.2500 1.3 20.03 7% 1.40 - 22.48 2.43 24.91
21 Concrete Mixer,Trailer Mounted 250 Lit 15 0.40% 0.24 50% 3.03 0.1300 2.0 31.24 14% 4.37 4.00 42.64 8.28 50.92
22 Concrete Mixer,Trailer Mounted 500 Lit 25 0.40% 0.39 50% 5.22 0.1000 2.5 40.05 14% 5.61 4.00 54.88 14.12 68.99
23 Air Compressor 600CFM 155 0.40% 0.50 50% 7.01 0.1290 20.0 320.32 14% 44.84 5.60 377.78 18.65 396.43
24 Water Pump 230 Lit/min 8 0.25% 0.04 80% 2.64 0.3750 3.0 48.06 14% 6.73 - 57.43 3.80 61.23
25 Street Sweeper, Self Prop 1-2m 70 0.40% 2.46 50% 48.22 0.2600 18.2 291.56 22% 64.14 21.82 425.74 118.67 544.41
26 AC Welder, Diesel 300-400AMP 55 0.40% 0.30 50% 6.75 0.1820 10.0 160.36 14% 22.45 - 189.56 16.19 205.75
27 Pick Up,Double cab,4*4,Diesel - 102 1.30% 11.26 50% 69.95 0.0590 6.0 96.41 16% 15.43 9.52 191.31 178.96 370.27
28 Plate Compactor 5 1.50% 0.28 50% 2.11 0.1000 0.5 8.01 7% 0.56 - 10.68 5.09 15.77
29 Road Marking Machine 85 2.00% 26.00 80% 123.31 0.2200 18.7 299.57 20% 59.91 18.67 501.46 223.15 724.61
30 Asphalt Cutter 2.00% 0.80 90% 10.80 - - - 0% - - 10.80 14.04 24.84

Stadia Engineering Works Consultant PLC Page 2 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 4: Production rate of Construction Activities


March 21, 2017
Activity No. Activity Name Unit Main Resource to be Allocated Production Rate
No Type & Capacity
Materials Production
a Borrow Material production M3 1 Crawler Dozer 686.00
b Select Material production M3 1 Crawler Dozer 560.00
c Quarry Rock Production M3 1 Crawler Dozer 480.00
Rock Crushing -Surface & concrete
d M3 1 Crusher Plant 240.00
Aggregate
e Rock Crushing -Base Aggregate M3 1 Crusher Plant 260.00
f Rock Crushing -Sub Base Aggregate M3 1 Crusher Plant 280.00
g Hot Mix Production (AC - 60/70) M3 1 Asphalt Plant 200.00
h Hot Mix Production (AC - 80/100) M3 1 Asphalt Plant 200.00
i Pipe Production(Dia.36) Each 15 Pipe Molds 15.00
j Pipe Production(Dia.42) Each 15 Pipe Molds 15.00
k Pipe Production(Dia.48) Each 15 Pipe Molds 15.00
l Guide Post Production Each 1 Concrete Mixer 30.00
m KM Post Production Each 1 Concrete Mixer 30.00
n HCB Production Each 1 HCB Machine 160.00
o Sand Production M3 1 Excavator, Wheel Type 28.00
p Sand Hauling M3 1 Front End Loader (2.5 M3) 1,129.41
q Formwork - Minor Drainage M2 1 Carp. Foreman 32.00
r Duct Marker Blocks Production Each 1 Concrete Mixer 30.00
s Class A bedding (Class 20/20 concrete) M3 1 Concrete Mixer 1/4 M3 12.00
t Rock Crushing -Chip Aggregate M3 1 Crusher Plant 200.00

Construction Activities
15.01(a) 1 Crawler Dozer 0.77
15.01(b) Maintenance of Diversion km 1 Crawler Dozer 0.70
15.01(c) 1 Crawler Dozer 0.77
15.01(d) 1 Safety Man 1.00
15.01(e) 1 Safety Man 1.00
21.01 Clearing and Grubbing ha 1 Crawler Dozer 1.10
22.06(a) Demolishing Plain concrete 1 Excavator, Wheel Type 30.00
22.06(b) Demolishing Reinforced concrete 1 Excavator, Wheel Type 18.00
22.06(c) Demolishing Masonry Structures - mortared 1 Excavator, Crawler Type 20.00
22.06(d) Demolishing Masonry Structures - dry 1 Excavator, Crawler Type 30.00

31.01(a) Open Drain Excavation (in soft) m3 1 Wheel Excavator(2.5m3) 120.00


31.01(b) Open Drain Exc. (in Hard) (Extra-over) m3 1 Wheel Excavator(2.5m3) 100.00
31.05 2 Motor Grader (120-150 FWHP) 1,200.00
32.01(a) Minor Structures Excavation (in Soft) m3 1 Wheel Excavator(2.5m3) 150.00
32.01(b) Minor Structures Exc. (in Hard) (Extra-over) m3 1 Wheel Excavator(2.5m3) 90.00

32.02(a) Backfilling using the excavated material m3 1 Dump Truck 7m 3


70.00
Backfilling using Imported selected
32.02(b) m3 1 Dump Truck 7m 3
70.00
material
36'' diameter R.C pipe installation on class
32.03(a)(i) 1 Front End Loader (2.0-2.5 M3) 11.00
A Bedding
42'' diameter R.C pipe installation on class
32.03(a)(ii) 1 Front End Loader (2.0-2.5 M3) 11.00
A Bedding
48'' diameter R.C pipe installation on class
32.03(a)(iii) 1 Front End Loader (2.0-2.5 M )
3
11.00
A Bedding
36'' diameter R.C pipe installation on class B
32.03(b)(i) 1 Front End Loader (2.0-2.5 M3) 11.00
Bedding
42'' diameter R.C pipe installation on class B
32.03(b)(ii) 1 Front End Loader (2.0-2.5 M3) 11.00
Bedding
48'' diameter R.C pipe installation on class B
32.03(b)(iii) m 1 Front End Loader (2.0-2.5 M3) 11.00
Bedding
Service Duct using ordinary pipes (150mm
32.16(a) m 1 Mason I 20.00
diameter steel pipes)
Service Duct using split pipes (150mm
32.16(b) 1 Mason I 20.00
diameter steel pipes)
32.17 Duct marker blocks No. 1 Labor Forman 20.00
32.18 Chambers for ducts 1 Concrete Mixer 1/4 M3 7.00
Class 25/20 Concrete Curbing (size .45m X .
33.01(a)(i) m 1 Concrete Mixer 1/4 M3 155.00
17m)
Class 25/20 Concrete Curbing (size .20m X .
33.01(a)(ii) m 1 Concrete Mixer 1/4 M3 240.00
25m)

Stadia Engineering Works Consultant PLC Page 1 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 4: Production rate of Construction Activities


March 21, 2017
Activity No. Activity Name Unit Main Resource to be Allocated Production Rate
Concrete Chute (Class 20/20) including
33.03(a) 1 Concrete Mixer 1/4 M3 100.00
Formwork
Concrete lining (Class 20/20) including
33.09(a) 1 Concrete Mixer 1/4 M3 12.00
Formwork
Pedestrian drain covers (Class 25/20 -
33.17(b)(i) No. 1 Concrete Mixer 30.00
1.4mX1.2mX0.15m)
Pedestrian drain covers (Class 25/20 -
33.17(b)(ii) 1 Concrete Mixer 30.00
1.6mX1.2mX0.15m)
Vehicle drain covers (Class 25/20
33.17(b)(iii) No. 1 Concrete Mixer 30.00
-1.6mX1.2mX0.20m)
34.01(b)(i) Stone Pitching for outlet & inlet of culverts m2 1 Mason II 50.00
34.03(b) Cement-mortared stone walls m3 1 Mason Forman 8.00
Pre-cast concrete blocks for side walk
34.04(c) m2 1 Labor Forman 96.00
pavement

Removal of unsuitable material and


41.01(b) m3 1 Crawler Dozer 585.67
replacement with suitable material
41.02 Road bed preparation and compaction m3 1 Motor Grader (120-150 FWHP) 586.00
42.01(a) Cut to fill m3 2 Motor Grader (120-150 FWHP) 1,200.00
42.01(b) Borrow to fill m3 2 Motor Grader (120-150 FWHP) 1,200.00
42.01(c) Rock fill m3 1 Crawler Dozer 685.00
42.01(d) Improved subgrade m3 2 Motor Grader (120-150 FWHP) 980.00
42.03(a) Common (normal) excavation m3 2 Crawler Dozer 1,120.00
42.03(b) Rock excavation m3 1 Crawler Dozer 400.00
Reinstatement of rock (hard) material
43.01(a) 1 Crawler Dozer 0.350
borrow areas
Reinstatement of common (normal or soft)
43.01(b) 1 Crawler Dozer 0.500
material borrow areas
44.04 Side fills or Fill-flattening 2 Motor Grader (120-150 FWHP) 1,200.00

51.01(a)(i) Gravel Sub-base m3 1 Motor Grader (120-150 FWHP) 480.00


52.01(c)(ii) Crushed -stone base m3 2 Motor Grader (120-150 FWHP) 800.00
0 0
61.01(a) Prime Coat (MC-30 cutback bitumen ) l 1 Asphalt Distributor 6000 Ltrs 8,570.00
Tack Coat (Stable-grade bitumen emulsion
62.01(a) 1 Asphalt Distributor 6000 Ltrs 4,000.00
(30%))
Double Surface Seal (150/200 penetration
63.02(b)* m2 1 Spreader, Aggregate 4,000.00
grade bitumen) 1st layer
Double Surface Seal (150/200 penetration
63.02(b) 1 Spreader, Aggregate 4,000.00
grade bitumen)
Asphaltic Concrete (50 mm thick, 80/100
64.02(a) m2 1 Asphalt Paver, Crawler 3,500.00
bitumen)
0 0
81.02(a) Major Structures Excavation (in Soft) m3 1 Wheel Excavator(2.5m3) 185.00
81.02(b) Major Structures Excavation (in Hard) m3 1 Wheel Excavator(2.5m3) 80.00
81.05(a) Backfill using excavated material 1 Front End Loader (2.0-2.5 M3) 200.00
81.05(b) Backfill using imported material m3 1 Front End Loader (2.0-2.5 M3) 200.00
81.05(c) Hand laid rock embankment 1 Labor Forman 40.00
81.08(a) Rock foundation fill 1 Labor Forman 30.00
81.08(c) Compacted granular foundation fill 1 Front End Loader (2.0-2.5 M3) 180.00
82.01(a ) Formwork for Class F1 surface finish 1 Carp. Foreman 32.00
82.01(b ) Formwork for Class F2 surface finish m2 1 Carp. Foreman 36.00
83.01(a)(i) Grade 60 Reinforcement Steel t 1 Steel - cutter 0.513
83.01(a)(ii) Grade 40 Reinforcement Steel t 1 Steel - cutter 0.513
84.01(a) Class 30/20 concrete in RC Structure m3 2 Concrete Mixer 1/2 M3 32.00
84.01(b) Class 25/20 concrete in RC Structure 2 Concrete Mixer 1/2 M3 32.00
84.01(c) Class 15/20 concrete in lean concrete m3 2 Concrete Mixer 1/2 M3 32.00
87.03 Elastomeric Bearing No. 1 AC Welder, Diesel 2.00
87.07 Concrete parapet m 1 Concrete Mixer 1/4 M3 66.00
87.13(a) Expansion joint with 20mm filler m 1 Carpenter II 8.10
87.19(a)(i) Dia. 100mm PVC drainage pipes 1 Mason I 16.00
87.19(b)(i) Dia. 200mm PVC pipe weep holes m 1 Mason I 48.00
87.23 Crushed Stone in drainage Strips m3 4 Labour I 8.00
89.01(b) Class "B" Stone Masonry m3 20 Mason I 25.00
810.01(a) MSE Gabion wall facing 1 Labor Forman 6.00
810.01(b) Polymeric (Geogrid) Reinforcements 1 Labor Forman 200.00
Drainage at interface of backfill and in-situ
810.01(c) 1 Dump Truck 7m3 110.00
soil
0 0

Stadia Engineering Works Consultant PLC Page 2 of 145


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 4: Production rate of Construction Activities


March 21, 2017
Activity No. Activity Name Unit Main Resource to be Allocated Production Rate
91.03(a)(i) Gabion boxes (2x1x1) 1 Labor Forman 8.00
91.03(a)(ii) Gabion boxes (1.5x1x1) 1 Labor Forman 8.00
91.04 Filter Fabric (Terram 1000 or equivalent) 1 Labor Forman 50.00
92.01(b) Guide Posts (reinforced concrete C- 20) 1 Labor Forman 50.00
92.01(c) Kilometer posts (reinforced concrete C- 20) No. 1 Labor Forman 20.00
93.01 Galvanized guard rails on steel post m 1 Welder I 20.00
94.01(a)(i) Traffic signs (Area not exceeding 2 m²) m2 1 Welder I 10.00
94.01(a)(ii) Traffic signs (Area exceeding 2 m²) 1 Welder I 8.00
94.02(a) Sign Supports (Concrete Class C 20/20) 1 Concrete Mixer(250 litre) 20.00
94.02(b) Sign Supports (Steel) No. 1 Mason I 20.00
Concrete in road sign footings including
94.03 m3 1 Dump Truck 4.80
exc. and backfilling (Class 15/20)
White lines (broken or unbroken) (width of
95.01(a) km 1 Road Marker 5.00
100mm)
Yellow lines (broken or unbroken) (width of
95.01(b) km 1 Road Marker 5.00
100mm)
95.04(a) In situ asphalt Speed Bumps 1 Labor Forman 40.00
95.04(b) In situ asphalt Rumble Strips 1 Labor Forman 12.00
96.01 Stockpiling of Topsoil 2 Crawler Dozer 1,120.00
96.02(a) Top-soiling 1 Labor Forman 60.00
96.02(b) Provide and apply chemical fertilizers 1 Labor Forman 1.875
96.03(a) Planting of grass cuttings 1 Labor Forman 0.05
96.03(b) Seeding 1 Labor Forman 0.10
Replacement or replanting of trees and
96.04 1 Labor Forman 500.00
growth management
99.02(a) Masonry Safety Barrier 1 Mason Forman 14.00
Safety Barrier Precast Concrete as per
99.02(b) 1 Concrete Mixer(250 litre) 30.00
drawing

Stadia Engineering Works Consultant PLC Page 3 of 145


JINKA TOWN ROAD PROJECT
Ethiopian Roads Authority
Alternative 2

Productivity calculation sheet for Dump Trucks and Loaders


Table 5: Dump Trucks (Production Depend on hualing Distance) March 21, 2017

Tested
D/Truck
Hauling Tested Load- Daily Daily
Cycle Time No of Trip Capacity Material Type To
Distance Speed Unload Production Production
(Hr) (No) (m3) be Haul
(Km) (Km/Hr) Time (m )
3
(km-m3)
(Compacted)
(Minute)
a b c d=c/60+a*2/b e=8/d f g=e*f h=a*g
Backfill material for
13.70 35 6 0.88 9.06 12 109 1,490
diversion
1.00 35 6 0.16 50.91 12 611 611 Clearing wasting
5.00 35 6 0.39 20.74 12 249 1,244 Cut Wasting
1.50 35 6 0.19 43.08 12 517 775 Top soil stockpiling
14.25 35 10 0.98 8.16 12 98 1,395 Crusher stone hauling
5.00 35 8 0.42 19.09 12 229 1,145 Cut to fill hauling
13.70 35 8 0.92 8.73 12 105 1,436 Borrow hauling
13.70 35 6 0.88 9.06 12 109 1,490 Natural subbase
26.50 35 40 2.18 3.67 12 44 1,166 Asphalt mix
Stone hauling (hand-
13.10 35 10 0.92 8.74 8 70 916
laid)
13.10 35 10 0.92 8.74 12 105 1,374 Stone hauling (fill)
5.00 35 10 0.45 17.68 12 212 1,061 Stone hauling (waste)
10.50 35 8 0.73 10.91 12 131 1,375 Sand hauling
26.50 35 6 1.61 4.96 12 59 1,576 Aggregate (Chipping)
26.50 35 6 1.61 4.96 12 59 1,576 Crushed Base course

Table 6: Loaders

Bucket
Cycle Time Efficiency Productivity
Loader Type Capacity Remark
(Minute) (%) (m3/day)
(m3)
a b c d=(480/b)*a*c
It works only for borrow & natural subbase loading b/c
Own 2.5 1.00 80% 960
a lot of time needed to separate boulders

It works for waste & crushed material loading b/c no


Own 2.5 0.85 80% 1,129
need of separation of boulders

NB: Efficiency of loader decreases due to many factors, but the mostly happened problem is shortage of working space due to quarry location.

Stadia Engineering Works Consultant PLC Page 1 of 145


Pay Item No. Description Unit Quantity Rate Amount
DIVISION 1000 GENERAL
ACCOMMODATION, SERVICES, AND ATTENDANCE FOR
1400
THE ENGINEER'S STAFF
14.01 Office Building Complete as specified including furniture. L. Sum 2,486,700.00 -
(Tables 1409/1 and 1409/5)
14.02 Laboratory Building Complete as specified including L. Sum 1,035,450.00 -
furniture. (Tables 1409/4 and 1409/6)
14.03 Items measured and paid for by the Lump sum
a Office Equipment as specified as per Table 1409/2 L. Sum 945,000.00 -
b Laboratory Equipment as specifies as required and specified L. Sum 3,000,000.00 -
in Tables 1409/3 (a), (b), (c) and/or (d)
14.04 Services
a Fixed Costs L. Sum 360,000.00 -
b Maintenance and Services for houses, offices and Month 76,723.58 -
laboratories.
14.05 Vehicles for Engineer and his staff
b Vehicle Type B No. 2,338,434.77 -
Provision of fuel and lubricants and the servicing,
14.06 maintenance, and repair of vehicles for the Engineer and
his staff
b Fuel, service and maintain vehicle , Type B Veh-mth 17,393.14

e Fuel, service and maintain vehicle in excess of 3,000 km for km 5.80


any vehicle in any one Calendar month, vehicle Type B
14.07 Attendance upon the Engineer and his staff
a Driver for the Engineer's vehicles Man-mth 8,968.81
b Chainman and Laborers Man-mth 4,324.25
c Laboratory Assistants Man-mth 4,324.25
d Cleaners Man-mth 4,324.25
e Watchman/Security Man-mth 4,324.25
Additional Offices and laboratory equipment ordered by
14.08
the Engineer
a Additional equipment ordered by the Engineer Prov. Sum
Laboratory testing to be carried out in external laboratories as
b Prov. Sum
instructed by the Engineer
Percentage allowed for overhead and profit on items 14.08 (a)
c and (b) % 35% -

Building, House Type, complete, as specified, including


14.09 fixtures furniture and
equipment (Tables 1409/7 and 1409/8)
a Type A housing No. 1,118,610.00 -
b Type B housing No. 370,102.50
c Type C housing (Blocks) No. 1,065,960.00
d Type D housing No. 1,445,850.00
14.10 Items measured by number
a Air conditioning units No. 31,735.74 -
14.11 Temporary facilities of the Engineer
a Month 44,347.50 -
Office fully fitted, furnished and equipped including all services
b Laboratory fully fitted, furnished and equipped including all Month 42,120.00 -
services
c Housing Accommodation fully fitted, furnished and equipped
including all services
i Type A houses Month 10,800.00 -
ii Type B houses Month 4,050.00 -
d Vehicles including all operating costs
ii Type B Month 81,000.00 -
e Survey Equipment Month 30,000.00
14.12 Communication Equipment for the Engineer
b SIM card for mobile phone (work-related usage) No. 20.25
c Airtime for work-related SIM card Month 8,100.00
1500 TRAFFIC MANAGEMENT
15.01 Temporary Diversions
a Construction of diversions km -
b Maintenance of Diversion km 0.70 172,087.46 120,461.22
c Reinstatement of Diversion km -
d Traffic Management – full width km -
e Traffic Management – half-width km -

1600 Social, Health, Safety and Environmental Protection and


Mitigation Measures
16.01 Preparation of Management Plans
a L. Sum 100,000.00
Site Environmental and Social Management Plan (SESMP)
b Health and Safety Management Plan (HSMP) L. Sum 100,000.00
16.02 Provision of Occupational Health and Safety Equipment L. Sum 1,331,250.00
with Worker Training

Provision of a suitably equipped and staffed Clinic in the


16.03 main construction camp; and the provision of first aid L. Sum 303,750.00
equipment, kits and medical supplies, sick bay and a
suitable ambulance service at all camps on the site

16.04 Watering of the road under construction, temporary Km 4.00 138,171.62 552,686.48
diversions, and access and haul roads at settlement areas
16.05
STD and HIV/AIDS Prevention and Control Programme
Conducting Knowledge, Attitude and Practice (KAP) surveys,
preparation of action plans on STD and HIV/AIDS alleviation
measures, provision of information and educational materials,
a counselling and testing services and establishment and Prov. Sum
training of peer educators and Anti-AIDS Committees

b % 35% -
Percentage allowed for overhead and profit on item 16.05 (a)
16.06 Liaison with Communities and Local Authorities
Establishment and management of a Project Liaison
a Committee (PLC) including the organization of public meetings Prov. Sum
and project related notices to the Community
b % 35% -
Percentage allowed for overhead and profit on item 16.06 (a)
16.07 Complimentary Interventions
Provision for the inclusion of complimentary interventions to
a Prov. Sum
the contract as agreed and directed by the Client
b % 35% -
Percentage allowed for overhead and profit on item 16.07 (a)
1000 General -TOTAL (Carried forward to Summary) 673,147.70

Note:
1 For all Buildings, Construction cost of 6000 Birr per m2 is considered and the rate is factored by 35% for overhead and profit.

2 Purchase value of Office Equipment is estimated to be 700000 Birr and when factored by overhead and profite the total cost is 945000 Birr.

3 Purchase value for Laboratory Equipment is 2222222.22 Birr and when factored by overhead and profite the total cost will be 3000000Birr.

Cost of Maintenance for type B vehicle per month: fuel=(3000/9)*16.02=5340, insurance=677.14 Birr, Service =1500 Birr, Maintenance and
4 repair=2500 Birr, tyre=2866.67 Birr, Total=12883.81 Birr per month and when factored by overhead and profit the total cost will be
17393.14 Birr.

Services for Engineers facilities in one month

Item No. Description Quantity Rate No. days amount


1 Generator for power supply 1 760.00 30 22,800.00
2 Water trucks for water supply 0.125 568.61 30 2,132.28
3 Supply of bottled water for Employer rep. 45 12.00 30 16,200.00
4 Supply of gas LS 30 2,000.00
5 Maintenance LS 30 3,000.00
6 Messing facilities LS 30 2,000.00
7 Attendance LS 30 1,200.00
8 Photograph LS 30 500.00
9 Assistance 5 33.33 30 5,000.00
10 Emergence equipments LS 30 2,000.00
Total 56,832.28
Over head and profit margin 0.35 19,891.30
Total cost of engineers service 76,723.58

You might also like