Project Name: Al Safwa Tower - Salmiya (210001)

Activity ID Activity Name Original Start Finish


Duration 2021
Jan Feb Mar Apr May Jun Jul Aug Sep
206.00d 06-Jan-21 30-Jul-21 30-Jul-21, 210001 Al Safwa Tower Salmiya
210001 Al Safwa Tower Salmiya
206.00d 06-Jan-21 30-Jul-21 30-Jul-21, 210001.1 Project Initiation Phase
210001.1 Project Initiation Phase
A1220 Contract Signing 1.00d 06-Jan-21 06-Jan-21 Contract Signing
A1225 Calculation 1.00d 15-Mar-21 15-Mar-21 Calculation
A1230 Curtain wall Drawing Approvel 128.00d 25-Mar-21 30-Jul-21 Curtain wall Drawing Approvel
A1235 Doors & Window Drawing Approvel 128.00d 25-Mar-21 30-Jul-21 Doors & Window Drawing Approvel
82.00d 14-Apr-21 04-Jul-21 04-Jul-21, 210001.2 Glass Handrail
210001.2 Glass Handrail
A1000 Glass handrail steel Bracket 1.00d 14-Apr-21 14-Apr-21 Glass handrail steel Bracket
A1010 Glass(Holded by Main Contractor) 20.00d 15-Jun-21* 04-Jul-21 Glass(Holded by Main Contractor)
46.00d 11-May-21 25-Jun-21 25-Jun-21, 210001.3 Canopy 5 No's
210001.3 Canopy 5 No's
A1250 Main Steel 24.00d 11-May-21* 03-Jun-21 Main Steel
A1255 Cladding work 20.00d 06-Jun-21* 25-Jun-21 Cladding work
91.00d 18-Apr-21 17-Jul-21 17-Jul-21, 210001.4 Curtain Wall
210001.4 Curtain Wall
210001.4.1 Building - A 91.00d 18-Apr-21 17-Jul-21 17-Jul-21, 210001.4.1 Building -A
A1040 Aluminium Fabrication & Installation 43.00d 18-Apr-21 30-May-21 Aluminium Fabrication & Installation
A1050 Glass 37.00d 25-May-21* 30-Jun-21 Glass
A1060 Cover Cap with Silicone 25.00d 23-Jun-21* 17-Jul-21 Cover Cap with Silicone
210001.4.2 Building - B 49.00d 30-May-21 17-Jul-21 17-Jul-21, 210001.4.2 Building - B
A1070 Aluminium Fabrication & Installation 29.00d 30-May-21* 27-Jun-21 Aluminium Fabrication & Installation
A1080 Glass 26.00d 15-Jun-21* 10-Jul-21 Glass
A1090 Cover Cap with Silicone 25.00d 23-Jun-21* 17-Jul-21 Cover Cap with Silicone
58.00d 29-May-21 25-Jul-21 25-Jul-21, 210001.5 windows
210001.5 windows
210001.5.1 Building - A 32.00d 29-May-21 29-Jun-21 29-Jun-21, 210001.5.1 Building - A
210001.5.1.1 Floor Level 1 To 5 12.00d 29-May-21 09-Jun-21 09-Jun-21, 210001.5.1.1 Floor Level 1 To 5
A1100 Aluminium Windows Installation 10.00d 29-May-21* 07-Jun-21 Aluminium Windows Installation
A1110 Glass Installation 5.00d 05-Jun-21* 09-Jun-21 Glass Installation
210001.5.1.2 Floor Level 6 To 10 12.00d 08-Jun-21 19-Jun-21 19-Jun-21, 210001.5.1.2 Floor Level 6 To 10
A1120 Aluminium Windows Installation 10.00d 08-Jun-21* 17-Jun-21 Aluminium Windows Installation
A1130 Glass Installation 5.00d 15-Jun-21* 19-Jun-21 Glass Installation
210001.5.1.3 Floor Level 11 To 14 12.00d 18-Jun-21 29-Jun-21 29-Jun-21, 210001.5.1.3 Floor Level 11 To 14
A1140 Aluminium Windows Installation 10.00d 18-Jun-21* 27-Jun-21 Aluminium Windows Installation
A1150 Glass Installation 5.00d 25-Jun-21* 29-Jun-21 Glass Installation
210001.5.2 Building - B 32.00d 24-Jun-21 25-Jul-21 25-Jul-21, 210001.5.2 Building - B
210001.5.2.1 Floor Level 1 To 5 12.00d 24-Jun-21 05-Jul-21 05-Jul-21, 210001.5.2.1 Floor Level 1 To 5
A1160 Aluminium Windows Installation 10.00d 24-Jun-21* 03-Jul-21 Aluminium Windows Installation
A1170 Glass Installation 5.00d 01-Jul-21* 05-Jul-21 Glass Installation
210001.5.2.2 Floor Level 6 To 10 12.00d 04-Jul-21 15-Jul-21 15-Jul-21, 210001.5.2.2 Floor Level 6 To 10
A1180 Aluminium Windows Installation 10.00d 04-Jul-21* 13-Jul-21 Aluminium Windows Installation
A1190 Glass Installation 5.00d 11-Jul-21* 15-Jul-21 Glass Installation
210001.5.2.3 Floor Level 11 To 14 12.00d 14-Jul-21 25-Jul-21 25-Jul-21, 210001.5.2.3 Floor Level 11 To 14
A1200 Aluminium Windows Installation 10.00d 14-Jul-21* 23-Jul-21 Aluminium Windows Installation
A1210 Glass Installation 5.00d 21-Jul-21* 25-Jul-21 Glass Installation
15.00d 01-Jul-21 15-Jul-21 15-Jul-21, 210001.6 Frameless Glass Partitions
210001.6 Frameless Glass Partitions
A1300 Frameless Glass Partition Install 15.00d 01-Jul-21* 15-Jul-21 Frameless Glass Partition Install
45.00d 08-Jun-21 22-Jul-21 22-Jul-21, 210001.7 Aluminim Doors
210001.7 Aluminim Doors
A1290 Aluminium Door Installation 45.00d 08-Jun-21* 22-Jul-21 Aluminium Door Installation
10.00d 21-Jul-21 30-Jul-21 30-Jul-21, 210001.8 Finishing & Handover
210001.8 Finishing & Handover
Project Baseline Bar Critical Remaining Work Page 1 of 2 TASK filter: All Activities
Actual Work Milestone © Oracle Corporation
Remaining Work Summary
  06-May-21 14:13
Project Name: Al Safwa Tower - Salmiya (210001)

Activity ID Activity Name Original Start Finish


Duration 2021
Jan Feb Mar Apr May Jun Jul Aug Sep
A1275 Curtain Wall Handover 10.00d 21-Jul-21* 30-Jul-21 Curtain Wall Handover
A1276 Doors & Windows Handover 10.00d 21-Jul-21* 30-Jul-21 Doors & Windows Handover
A1280 Project & Documents Handover 10.00d 21-Jul-21* 30-Jul-21 Project & Documents Handover

Project Baseline Bar Critical Remaining Work Page 2 of 2 TASK filter: All Activities
Actual Work Milestone © Oracle Corporation