You are on page 1of 3

ID Task Name Qty.

Duration Start Finish 17 May '21


21 Jun '2126 Jul '2130 Aug '21
04 Oct '21
08 Nov '21
13 Dec '21
M T W T F S S M T W T F S S M T
1 PRANAVA'S THE BUSINESS PARK, Hyderabad 229.25 days Sat 22-05-21 Wed 29-12-21
2 LOI Receipt 1 day Tue 01-06-21 Tue 01-06-21
3 Project Technical Submission 60.25 days Sat 22-05-21 Mon 19-07-21
4 Project Schedule R0 (Pre-Contract Finalization) 1 day Sat 22-05-21 Sat 22-05-21
5 Revised Project Schedule R1 with Approval 10 days Wed 02-06-21 Sat 12-06-21
6 Project Schedule R1 with Manpower Histograms, Logistics 10 days Sun 13-06-21 Wed 23-06-21
Plan, Equipment Plan, Cash-Flow
7 Safety Document (HSE) 4 days Wed 02-06-21 Sun 06-06-21
8 QA/QC Document (ITP's, Checklist, PQP, Policy) 10 days Wed 02-06-21 Sat 12-06-21
9 Work Method Statements 10 days Sun 13-06-21 Wed 23-06-21
10 Material TDS Submission & Approval 10 days Thu 24-06-21 Sat 03-07-21
11 Sample Board Submission & Approval 15 days Mon 05-07-21 Mon 19-07-21
12 Design & Engineering 73 days Wed 02-06-21 Thu 12-08-21
13 Dwg. Received from Client 1 day Wed 02-06-21 Thu 03-06-21
14 RFI, if any 4 days Fri 04-06-21 Tue 08-06-21
15 Comments on RFI 2 days Wed 09-06-21 Fri 11-06-21
16 System Dwg. Preparation & Submission incl. Struc. Calc. 8 days Sat 12-06-21 Mon 21-06-21
17 System Dwg. Approval 3 days Tue 22-06-21 Thu 24-06-21
18 Grid Marking Dwg. Submission 6 days Sat 12-06-21 Fri 18-06-21
19 Grid Marking Dwg. Approval 3 days Sat 19-06-21 Tue 22-06-21
20 Shop Dwg. Preparation & Submission R0 with Struc. Calc. 15 days Fri 25-06-21 Fri 09-07-21
(all Typology)
21 Approval / Comments on Shop Dwg. R0 (from Architect 6 days Sat 10-07-21 Fri 16-07-21
and Façade Consultant)
22 Shop Dwg. Preparation & Submission R1 (all Typology) 10 days Sat 17-07-21 Tue 27-07-21
23 Approval / Comments on Shop Dwg. R1 (from Architect 4 days Wed 28-07-21 Sat 31-07-21
and Façade Consultant)
24 Shop Dwg. Final Submission R2 (all Typology) 6 days Sun 01-08-21 Sat 07-08-21
25 Final Approval / Comments on Shop Dwg. R2 (from 4 days Sun 08-08-21 Thu 12-08-21
Architect and Façade Consultant)
26 MTO Release 41 days Tue 22-06-21 Sat 31-07-21
27 UCW Area (incl. Accessories items) 15 days Tue 22-06-21 Wed 07-07-21
28 ACP (incl. Accessories items) 10 days Wed 07-07-21 Fri 16-07-21
29 SUCW, Louvers , Spider Glazing and Glass Railing 15 days Sat 17-07-21 Sat 31-07-21
30 Die Development 39 days Fri 25-06-21 Sun 01-08-21
31 Die Dwgs Submission 2 days Fri 25-06-21 Sun 27-06-21
Page 1
ID Task Name Qty. Duration Start Finish 17 May '21
21 Jun '2126 Jul '2130 Aug '21
04 Oct '21
08 Nov '21
13 Dec '21
M T W T F S S M T W T F S S M T
32 Counter Dwgs from Extruder 2 days Mon 28-06-21 Wed 30-06-21
33 Approval of Die Dwgs 2 days Thu 01-07-21 Sat 03-07-21
34 Die Making 30 days Sun 04-07-21 Sun 01-08-21
35 Procurement & Delivery 106 days Wed 30-06-21 Sat 09-10-21
36 Procurement (Order Release process) 49 days Wed 30-06-21 Mon 16-08-21
37 UCW Area 18 days Wed 30-06-21 Sat 17-07-21
38 Alum. Extruded Profiles (55 MT) 55MT 7 days Wed 30-06-21 Wed 07-07-21
39 Glass 7 days Thu 08-07-21 Wed 14-07-21
40 Hardware & Accessories 10 days Thu 08-07-21 Sat 17-07-21
41 ACP 15 days Sat 17-07-21 Sat 31-07-21
42 Alum. Framing Material 7 days Sat 24-07-21 Sat 31-07-21
43 ACP Sheet 7 days Sat 17-07-21 Fri 23-07-21
44 Semi-Unitized Area & Louvers 23 days Sat 24-07-21 Mon 16-08-21
45 Alum. Profiles 7 days Sat 24-07-21 Sat 31-07-21
46 SUCW Glass 7 days Sun 01-08-21 Sun 08-08-21
47 Hardware & Accessories 7 days Mon 09-08-21 Mon 16-08-21
48 Louver Accessories 7 days Mon 09-08-21 Mon 16-08-21
49 Delivery to Almech Factory 73 days Sat 31-07-21 Sat 09-10-21
50 UCW Area 52 days Sat 31-07-21 Sun 19-09-21
51 Alum. Extruded Profiles (55 MT) 55 MT 45 days Fri 06-08-21 Sat 18-09-21
52 Glass 45 days Sat 07-08-21 Sun 19-09-21
53 Hardware & Accessories 45 days Sat 31-07-21 Mon 13-09-21
54 ACP 32 days Wed 25-08-21 Fri 24-09-21
55 Alum. Framing Material 25 days Wed 25-08-21 Fri 17-09-21
56 ACP Sheet 30 days Thu 26-08-21 Fri 24-09-21
57 Semi-Unitized Area & Louvers 27 days Tue 14-09-21 Sat 09-10-21
58 Alum. Profiles 15 days Sun 19-09-21 Mon 04-10-21
59 SUCW Glass 20 days Mon 20-09-21 Sat 09-10-21
60 Hardware & Accessories 15 days Tue 14-09-21 Tue 28-09-21
61 Louver Accessories 15 days Tue 14-09-21 Tue 28-09-21
62 Fab. & Delivery 102 days Mon 09-08-21 Tue 16-11-21
63 Fab. / Production 92 days Mon 09-08-21 Sun 07-11-21
64 UCW Area 55 days Mon 09-08-21 Thu 30-09-21
65 2nd Floor - 3rd Floor 250 Panels 10 days Mon 09-08-21 Thu 19-08-21
66 4th Floor - 7th Floor 500 Panels 17 days Fri 20-08-21 Sun 05-09-21

Page 2
ID Task Name Qty. Duration Start Finish 17 May '21
21 Jun '2126 Jul '2130 Aug '21
04 Oct '21
08 Nov '21
13 Dec '21
M T W T F S S M T W T F S S M T
67 8th Floor - 11th Floor 500 Panels 20 days Mon 06-09-21 Sat 25-09-21
68 Terrace Floor 125 Panels 5 days Sun 26-09-21 Thu 30-09-21
69 Semi-Unitized Area & Louvers 47 days Tue 21-09-21 Sun 07-11-21
70 SUCW Outer Frame 20 days Tue 21-09-21 Sun 10-10-21
71 SUCW Sub-Frame 20 days Mon 11-10-21 Sun 31-10-21
72 Louvers 5 days Mon 01-11-21 Sun 07-11-21
73 Delivery to Site 94 days Tue 17-08-21 Tue 16-11-21
74 UCW Area 60 days Tue 17-08-21 Wed 13-10-21
75 2nd Floor - 3rd Floor 250 Panels 10 days Tue 17-08-21 Thu 26-08-21
76 4th Floor - 7th Floor 500 Panels 20 days Fri 27-08-21 Wed 15-09-21
77 8th Floor - 11th Floor 500 Panels 20 days Thu 16-09-21 Tue 05-10-21
78 Terrace Floor 125 Panels 7 days Wed 06-10-21 Wed 13-10-21
79 Semi-Unitized Area & Louvers 36 days Mon 11-10-21 Tue 16-11-21
80 SUCW Outer Frame 15 days Mon 11-10-21 Tue 26-10-21
81 SUCW Sub-Frame 15 days Mon 01-11-21 Tue 16-11-21
82 Louvers 5 days Mon 08-11-21 Fri 12-11-21
83 Installation 121 days Fri 20-08-21 Wed 15-12-21
84 UCW Area 75 days Fri 20-08-21 Sun 31-10-21
85 2nd Floor - 3rd Floor 250 Panels 15 days Fri 20-08-21 Fri 03-09-21
86 4th Floor - 7th Floor 500 Panels 20 days Sat 04-09-21 Thu 23-09-21
87 8th Floor - 11th Floor 500 Panels 25 days Fri 24-09-21 Mon 18-10-21
88 Terrace Floor 125 Panels 12 days Tue 19-10-21 Sun 31-10-21
89 ACP (incl Coping, Soffit, Closure, etc.) 90 days Sat 18-09-21 Wed 15-12-21
90 Alum. Framing Material Installation 60 days Sat 18-09-21 Tue 16-11-21
91 ACP Sheet Installation 77 days Fri 01-10-21 Wed 15-12-21
92 Semi-Unitized Area & Louvers 50 days Wed 27-10-21 Wed 15-12-21
93 SUCW Outer Frame 20 days Wed 27-10-21 Tue 16-11-21
94 SUCW Sub-Frame 25 days Wed 17-11-21 Sat 11-12-21
95 Louvers 3 days Sun 12-12-21 Wed 15-12-21
96 Spider Glazing Installation 36 days Thu 11-11-21 Wed 15-12-21
97 Glass Railing & Canopy 36 days Thu 11-11-21 Wed 15-12-21
98 Snag Rectification, Water Testing & Project Handover 60 days Mon 01-11-21 Wed 29-12-21

Page 3

You might also like