ID Task Name Qty. Duration Start Finish 17 May '21
21 Jun '2126 Jul '2130 Aug '21
04 Oct '21
08 Nov '21
13 Dec '21
M T W T F S S M T W T F S S M T
67 8th Floor - 11th Floor 500 Panels 20 days Mon 06-09-21 Sat 25-09-21
68 Terrace Floor 125 Panels 5 days Sun 26-09-21 Thu 30-09-21
69 Semi-Unitized Area & Louvers 47 days Tue 21-09-21 Sun 07-11-21
70 SUCW Outer Frame 20 days Tue 21-09-21 Sun 10-10-21
71 SUCW Sub-Frame 20 days Mon 11-10-21 Sun 31-10-21
72 Louvers 5 days Mon 01-11-21 Sun 07-11-21
73 Delivery to Site 94 days Tue 17-08-21 Tue 16-11-21
74 UCW Area 60 days Tue 17-08-21 Wed 13-10-21
75 2nd Floor - 3rd Floor 250 Panels 10 days Tue 17-08-21 Thu 26-08-21
76 4th Floor - 7th Floor 500 Panels 20 days Fri 27-08-21 Wed 15-09-21
77 8th Floor - 11th Floor 500 Panels 20 days Thu 16-09-21 Tue 05-10-21
78 Terrace Floor 125 Panels 7 days Wed 06-10-21 Wed 13-10-21
79 Semi-Unitized Area & Louvers 36 days Mon 11-10-21 Tue 16-11-21
80 SUCW Outer Frame 15 days Mon 11-10-21 Tue 26-10-21
81 SUCW Sub-Frame 15 days Mon 01-11-21 Tue 16-11-21
82 Louvers 5 days Mon 08-11-21 Fri 12-11-21
83 Installation 121 days Fri 20-08-21 Wed 15-12-21
84 UCW Area 75 days Fri 20-08-21 Sun 31-10-21
85 2nd Floor - 3rd Floor 250 Panels 15 days Fri 20-08-21 Fri 03-09-21
86 4th Floor - 7th Floor 500 Panels 20 days Sat 04-09-21 Thu 23-09-21
87 8th Floor - 11th Floor 500 Panels 25 days Fri 24-09-21 Mon 18-10-21
88 Terrace Floor 125 Panels 12 days Tue 19-10-21 Sun 31-10-21
89 ACP (incl Coping, Soffit, Closure, etc.) 90 days Sat 18-09-21 Wed 15-12-21
90 Alum. Framing Material Installation 60 days Sat 18-09-21 Tue 16-11-21
91 ACP Sheet Installation 77 days Fri 01-10-21 Wed 15-12-21
92 Semi-Unitized Area & Louvers 50 days Wed 27-10-21 Wed 15-12-21
93 SUCW Outer Frame 20 days Wed 27-10-21 Tue 16-11-21
94 SUCW Sub-Frame 25 days Wed 17-11-21 Sat 11-12-21
95 Louvers 3 days Sun 12-12-21 Wed 15-12-21
96 Spider Glazing Installation 36 days Thu 11-11-21 Wed 15-12-21
97 Glass Railing & Canopy 36 days Thu 11-11-21 Wed 15-12-21
98 Snag Rectification, Water Testing & Project Handover 60 days Mon 01-11-21 Wed 29-12-21