Site Diary: Friday 25/3/2022
Site Diary: Friday 25/3/2022
Project: 1 - One Hyderabad - Somajiguda
Jubilee Hills Rd 45
Hyderabad , Telangana 500033
P: 799-564-4999
Hours Hours
Carpenter = 10
Helper .= 02
Fitter = 10
Helper =. 10
Sk sing (unskilled)
Mason m/s = 01
Helper M/c = 0 4
Total = 37,no's
SHUTTERING
Carpenter = 06
Helper = 07
Hours Hours
REINFORCEMENT
Fitter = 06
Helper = 07
UNSKILLED
Mason m/s = 01
Helper M/c = 04
Total = 31 no's
Above>Services Area
Carpenter = 03
Helper = 02
Jaffer (fitter)
Fitter = 00
Helper = 00
Sk sing (unskilled)
Mason m/s = 01
Helper M/c = 04
Curring M/c = 2
Notes: [A-BLOCK-
11th,12th,13th Floor]
[B-BLOCK-
9th,10th Floor]
Hours Hours
Area>Balcony>South
Side>Planter Box
Room>Balcony/Deckspace
Room>Balcony/Deckspace
Room>Balcony/Deckspace
Room>Balcony/Deckspace
Notes: Commercial block 11 th 12 th 13th and service lifts block work and plaster
Notes: O4 carpentors and 5 unskilled helper LMR shuttering and touch up works
Notes: -->A-block [(2-mason+1helper)-10th floor conductes packing, (2 unskilled 2nd,3rd floor cleaning)]
Hours Hours
-->B-block [(1-mason+1 helper)- 4th,5th floor conductes packing,(4 unskilled podium, ground,2nd floor cleaning)]
-->MISCELLANEOUS
[(2 Masons+2 helpers snags closing by TATA ], [2 unskilled diverted to police station]
Notes:
Room
270.0 2247.0
Man Hours Log's Attachments:
1.
IMG_20220325_101006.jpg IMG_20220325_101022.jpg
7. contractor 1
IMG_2022_03_25_10_33_20_453.jpg
10. contractor 2
IMG_2022_03_25_11_06_32_884.jpg
11. contractor 2
IMG_2022_03_25_11_09_19_647.jpg IMG_2022_03_25_11_09_32_248.jpg
IMG_2022_03_25_11_21_08_339.jpg
1648196758880.326904_tempImage.jpeg
19. Stoneman
1648197022899.849854_tempImage.jpeg 1648197022730.752930_tempImage.jpeg
20. Stoneman
1648197198159.427246_tempImage.jpeg
IMG-20220325-WA0020.jpg
EQUIPMENT LOG
No. Equipment Name Cost Code Hrs Operating Hrs Idle Inspected? Inspection Time Location
BLOCK
Notes: Passenger hoist of commercial block has been break down. From 2days. All material shifting activities had been stopped
Cement
Silo 01 - 87MT
Silo 02 - 93MT
**24/03/22
Silo - 02 -> MT
EQUIPMENT LOG
No. Equipment Name Cost Code Hrs Operating Hrs Idle Inspected? Inspection Time Location
Consumed *****
Admixture
Notes: D block excavation work stones shifting work,gravel shifting work 01 nos Operator, 01 nos Helper working
3.
IMG_20220325_101939.jpg IMG_20220325_185403.jpg
IMG-20220325-WA0015__01.jpg IMG-20220325-WA0000__01.jpg
IMG_20220325_220555__01.jpg
DELAY LOG
Comments: Due to non availability of brush bond rfx chemical in site water proofing activites has been delayed and
Mep works also has been delaying lack of clearance from water proofing
Works
Manapower
Comments: Commerical block Pour-7 Pour-8 works are getting delayed due to non availability of sufficient man power
of carpenter
CONSTRUCTIONS PVT
LTD
(DLR) 25-03-2022
Carpenter = 10
Helper .= 02
Fitter = 10
Helper =. 10
Sk sing (unskilled)
Mason m/s = 01
Helper M/c = 0 4
LIMTED
CONSTRUCTIONS PVT
LTD
Kishorr biswas(carpenter)
Carpenter = 05
Helper .= 06
Sk sing (unskilled)
Mason m/s = 01
Helper M/c = 0 4
By Date Copies To
Page 11 of 11 Printed on 26/3/2022 at 10:38 PM IST