  Project: 1 - One Hyderabad - Somajiguda 
Jubilee Hills Rd 45
Hyderabad , Telangana 500033
P: 799-564-4999

Site Diary: Friday 25/3/2022 

Site Diary Completed & Distributed


The Site Diary was completed and distributed by Prasanna Kumar Prodduturi on Sat Mar 26, 2022 at 10:38pmIST.

MAN HOURS LOG 270.0 Workers  |   2247.0 Man Hours

No. Contact/Company Workers # Man Location     

Hours Hours

1 10 12.0 120.0 Block-C>B3>Grade Slab>RCC

  

  Notes: B3 LEVEL REINFORCEMENT WORK AND STEEL STRAIGHTENING WORK.  

B2 LEVEL GRINDING WORK AND MASON WORK.

2 Pranava Group 37 12.0 444.0 Club House>GF   

  Notes: Club House (DLR) 25-03-2022  

Malay Roy (carpenter)

Carpenter = 10

Helper .= 02

Tanzil Aalam (fitter)

Fitter = 10

Helper =. 10

Sk sing (unskilled)

Mason m/s = 01

Helper M/c = 0 4

Total = 37,no's

3 Pranava Group 31 1.0 31.0 Block-C>05FL>Flat-06   

  Notes: Tower-c structure (DLR) 25-03-2022  

SHUTTERING

Carpenter = 06

Helper = 07

Page 1 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

No. Contact/Company Workers # Man Location     

Hours Hours

REINFORCEMENT

Fitter = 06

Helper = 07

UNSKILLED

Mason m/s = 01

Helper M/c = 04

Total = 31 no's

4 UIC 12 8.0 96.0 Block-B>Terrace &   

Above>Services Area

  Notes: Tower-B structure (DLR) 25-03-2022  

Kishore Biswas (carpenter)

Carpenter = 03

Helper = 02

Jaffer (fitter)

Fitter = 00

Helper = 00

Sk sing (unskilled)

Mason m/s = 01

Helper M/c = 04

Curring M/c = 2

5 Pranava Group 31 8.0 248.0   

  Notes: [A-BLOCK-  

11th,12th,13th Floor]

[B-BLOCK-

9th,10th Floor]

Total-31(including cutting and shifting)

6 APK IMPEX 3 8.0 24.0 Block-B>03FL>Flat-01   

  Notes: Grouting in toilets flooring and Wall cladding  

Page 2 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

No. Contact/Company Workers # Man Location     

Hours Hours

7 contractor 1 6 8.0 48.0 Block-A>03FL>Common

Area>Balcony>South   
Side>Planter Box

  Notes: Scaffolding works  

8 UIC 10 0.0 0.0 Block-C   

  Notes: 5masons and 5 Helpers sir  

2masons are working on plastering in flat GF no 7.

3mason is working on flat no 106 Blockwork

9 contractor 2 3 9.0 27.0 Block-A>14FL>Flat-01>Living   

Room>Balcony/Deckspace

  Notes: Red bricks 1st layer marking in progress  

10 contractor 2 3 9.0 27.0 Block-A>13FL>Flat-02>Living

Room>Balcony/Deckspace   

  Notes: Wirecut cladding works  

11 contractor 2 5 9.0 45.0 Block-A>12FL>Flat-01>Living

Room>Balcony/Deckspace   

  Notes: Wirecut cladding works  

12 contractor 2 4 9.0 36.0 Block-A>12FL>Flat-02>Living   

Room>Balcony/Deckspace

  Notes: Wirecut cladding works  

13 APK IMPEX 3 9.0 27.0 Block-A>02FL>Lobby Area

  

  Notes: Floor tilling works  

14 Leak and Seal 6 10.0 60.0 Commercial Block   

  Notes: Commercial water proofing at 6 and 7th and 8th preparation  

15 UIC 31 10.0 310.0 Commercial Block   

  Notes: Commercial block 11 th 12 th 13th and service lifts block work and plaster  

16 UIC 9 12.0 108.0 Commercial Block   

  Notes: O4 carpentors and 5 unskilled helper LMR shuttering and touch up works  

17 Pranava Group 18 8.0 144.0   

  Notes: -->A-block [(2-mason+1helper)-10th floor conductes packing, (2 unskilled 2nd,3rd floor cleaning)]  

Page 3 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

No. Contact/Company Workers # Man Location     

Hours Hours

-->B-block [(1-mason+1 helper)- 4th,5th floor conductes packing,(4 unskilled podium, ground,2nd floor cleaning)]

-->MISCELLANEOUS

[(2 Masons+2 helpers snags closing by TATA ], [2 unskilled diverted to police station]

18 APK IMPEX 3 8.0 24.0 Block-A>02FL>Lobby Area

  

  Notes:  

19 Stoneman 7 8.0 56.0 Block-A>14FL>Flat-02

  

  Notes: Screed work  

20 Stoneman 4 8.0 32.0 Block-A>03FL>Flat-01>Living

Room   

  Notes: Final polishing work  

21 Pradhan Enterprises 34 10.0 340.0

  

  Notes: Block A&B  

      270.0   2247.0    

Man Hours Log's Attachments: 

1.  

IMG_2022_03_25_10_07_04_649.jpg IMG_2022_03_25_10_04_04_255 (2).jpg

Page 4 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

IMG_2022_03_25_10_03_51_468 (2).jpg IMG_2022_03_25_10_03_51_468 (1).jpg

IMG_2022_03_25_10_04_04_255 (1).jpg IMG_20220325_100938.jpg

IMG_20220325_101006.jpg IMG_20220325_101022.jpg

7.  contractor 1 

IMG_2022_03_25_10_33_20_453.jpg

Page 5 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

10.  contractor 2 

IMG_2022_03_25_11_06_32_884.jpg

11.  contractor 2 

IMG_2022_03_25_11_09_19_647.jpg IMG_2022_03_25_11_09_32_248.jpg

13.  APK IMPEX 

IMG_2022_03_25_11_21_08_339.jpg

Page 6 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

18.  APK IMPEX 

1648196758880.326904_tempImage.jpeg

19.  Stoneman 

1648197022899.849854_tempImage.jpeg 1648197022730.752930_tempImage.jpeg

20.  Stoneman 

1648197198159.427246_tempImage.jpeg

Page 7 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

21.  Pradhan Enterprises 

IMG-20220325-WA0020.jpg

EQUIPMENT LOG

No. Equipment Name Cost Code Hrs Operating Hrs Idle Inspected? Inspection Time Location  

1 HOIST - COMMERCIAL 0.0 24.0 Yes   12:07PM   Commercial Block

BLOCK

  Notes: Passenger hoist of commercial block has been break down. From 2days. All material shifting activities had been stopped

labours are ideal . No action from MT and T 

2 Batching Plant 0.0 0.0 Yes   12:40PM  

  Notes: Today stock report

Cement

Silo 01 - 87MT

Silo 02 - 93MT

Ggbs Silo 03- 59MT

**24/03/22

Silo 01 -> 35.170MT

Silo - 02 -> MT

Silo - 03 -> 9.124MT

Page 8 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

EQUIPMENT LOG

No. Equipment Name Cost Code Hrs Operating Hrs Idle Inspected? Inspection Time Location  

Consumed *****

Admixture

Asian Paints (Maximoplast) - 7.5Barrels

Asian Paints Technoplast S300 - 8Barrels 

3 Excavator 6.01 6.01 Yes   09:54PM  

  Notes: D block excavation work stones shifting work,gravel shifting work 01 nos Operator, 01 nos Helper working  

Equipment Log's Attachments:

3. 

IMG_20220325_101939.jpg IMG_20220325_185403.jpg

IMG-20220325-WA0015__01.jpg IMG-20220325-WA0000__01.jpg

Page 9 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   

IMG_20220325_220555__01.jpg

         

DELAY LOG

Delay Type Start Time End Time Duration Location  

Material 12:05 AM 12:05 PM 12.0 Commercial Block  

  Comments: Due to non availability of brush bond rfx chemical in site water proofing activites has been delayed and

Mep works also has been delaying lack of clearance from water proofing

Third Party 09:50 AM 09:50 AM 0 Commercial Block  

Works

  Comments: Hoist Is not working for the last two days

Lack of Skilled 08:00 AM 08:00 PM 12.0  

Manapower

  Comments: Commerical block Pour-7 Pour-8 works are getting delayed due to non availability of sufficient man power

of carpenter

DAILY CONSTRUCTION REPORT LOG 57.0 Workers  |   672.0 Total Hours  

Foreman Journeyperson Apprentice Other  

No. Company Trade # of Workers Total # of Total # of Total # of Total  

Hours Workers Hours Workers Hours Workers Hours

1 UNIQIE INDIA RCC Structure 2 24.0 11 132.0 19 228.0 5 60.0  

CONSTRUCTIONS PVT

LTD

  Notes: Club House  

(DLR) 25-03-2022

Malay Roy (carpenter)

Carpenter = 10

Helper .= 02

Page 10 of 11 Printed on 26/3/2022 at 10:38 PM IST


 
 
   
 

DAILY CONSTRUCTION REPORT LOG 57.0 Workers  |   672.0 Total Hours  

Foreman Journeyperson Apprentice Other  

No. Company Trade # of Workers Total # of Total # of Total # of Total  

Hours Workers Hours Workers Hours Workers Hours

Tanzil Aalam (fitter)

Fitter = 10

Helper =. 10

Sk sing (unskilled)

Mason m/s = 01

Helper M/c = 0 4

2 NINA PERCEPT PRIVATE Waterproofing 0 0.0 0 0.0 0 0.0 4 36.0  

LIMTED

  Notes: South side of commerical Block joint treatment  

3 UNIQIE INDIA RCC Structure 1 12.0 0 0.0 10 120.0 5 60.0  

CONSTRUCTIONS PVT

LTD

  Notes: North strecth (DLR) 26-03-2022  

Kishorr biswas(carpenter)

Carpenter = 05

Helper .= 06

Sk sing (unskilled)

Mason m/s = 01

Helper M/c = 0 4

  TOTAL 3 36 11 132 29 348 14 156  