Home Construction Classic Schedule Layout 20-Jan-21 12:56

Activity ID Activity Name Original Duration Start Finish Resources Total Float

CH 1 Home Construction 61 10-Jan-21 06-Apr-21 0

A1190 Project Start 0 10-Jan-21* 0


CH 1.1 Site Preparation 1 10-Jan-21 11-Jan-21 0
A1000
Site Plan 1 10-Jan-21* 11-Jan-21 Architect 0
A1010
Grid Layout 1 10-Jan-21* 11-Jan-21 Engineer 0
CH 1.2 Sub Structure 12 11-Jan-21 27-Jan-21 0
A1050
Lay Foundation 5 14-Jan-21 21-Jan-21 Mason, Labor, Mixture, Sand, Cement, Crush, Steel Bar, Steel Fixer 0
A1020
Excavation of Foundation 3 11-Jan-21* 14-Jan-21 Excavator, Labor 0
A1060
DPC 3in 2 25-Jan-21* 27-Jan-21 Labor, Bitumen, Cement, Crush, Sand, Labor 0
A1040
Brick Footing 3 21-Jan-21* 25-Jan-21 Sand, Bricks, Mason, Labor, Cement 0

CH 1.3 Super Structure 49 27-Jan-21 06-Apr-21 0


A1140
W ater Tank 6 10-Mar-21* 17-Mar-21 Mason, Labor, Steel Fixer, Formwork, Sand, Cement, Crush, Bricks, Steel Bar 17
A1130
Shuttring 4 17-Feb-21 23-Feb-21 Labor, Formwork 0
A1110Roof 5 23-Feb-21* 01-Mar-21 Mason, Labor, Steel Fixer, Mixture, Sand, Cement, Crush, Steel Bar, Electrician, Mixture, PVC Pipes
0
A1200
Project Finish 0 06-Apr-21 0
A1120
Parapat Wall 7 10-Mar-21 19-Mar-21 Mason, Labor, Sand, Cement, Bricks 12
A1080
Mansory Work 18 27-Jan-21* 17-Feb-21 Mason, Labor, Sand, Cement 0
A1240
Curing of Slab 7 01-Mar-21 10-Mar-21 12
A1100
Column 4 27-Jan-21* 01-Feb-21 Mason, Labor, Steel Fixer, Sand, Cement, Crush, Steel Bar, Formwork 14
CH 1.4 Finish Work 26 01-Mar-21 06-Apr-21 0
A1270
Tiles 6 23-Mar-21 31-Mar-21 Mason, Labor, Cement, Marble and Tiles 2
A1220
Sanitary Fitting 4 01-Mar-21 05-Mar-21 Plumber, Sanitary Pipes, PVC Pipes 0
A1280
Plumbing 2 31-Mar-21 02-Apr-21 Plumber, Sanitary Porducts 2
A1230
Plaster 12 05-Mar-21 23-Mar-21 Mason, Labor, Cement, Sand 0
A1260
Painting 4 30-Mar-21 05-Apr-21 Painter, Paint 0
A1290
LED Bulbs 1 05-Apr-21 06-Apr-21 LED Lights and Fan, Electrician 0
A1210
Electric Fitting 4 01-Mar-21 05-Mar-21 Electrician, PVC Pipes, Electric Wires 0
A1250
Doors and Windows 5 23-Mar-21 30-Mar-21 Carpenter, Timber, Painter, Paint, Glass, Doors Lock and Handle 0

Page 1 of 1 TASK filter: All Activities