PP20146 Namit

PP20146
Standard Barchart
Activities: Entire program
2021 2022
Current
December January February March April May June July
Activity description Durn Start Finish 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22

Time Now - 21/12/2021


A000 - Bill Description Excavation 5 14 Dec 21 20 Dec 21 Bill Description Excavation
A010 - Surveying 5 22 Dec 21 28 Dec 21 A010 Surveying
A020 - Land acquisation 5 28 Dec 21 03 Jan 22 A020 Land acquisation
A030 - Cleaning 5 04 Jan 22 10 Jan 22 A030 Cleaning
A040 - Marking 5 11 Jan 22 17 Jan 22 A040 Marking
A050 - CBR Test 5 18 Jan 22 24 Jan 22 A050 CBR Test
A060 - Soil Test 5 25 Jan 22 31 Jan 22 A060 Soil Test
A070 - Excavation 5 01 Feb 22 07 Feb 22 A070 Excavation
A080 - Filling 5 08 Feb 22 14 Feb 22 A080 Filling
A090 - Leveling 5 15 Feb 22 21 Feb 22 A090 Leveling
A100 - Compacting 5 22 Feb 22 28 Feb 22 A100 Compacting
A110 - Earthwork in Embarkment 5 01 Mar 22 07 Mar 22 A110 Earthwork in Embarkment
A120 - Pavement work 5 08 Mar 22 14 Mar 22 A120 Pavement work
A130 - Rolling 5 15 Mar 22 21 Mar 22 A130 Rolling
A140 - Curing 5 22 Mar 22 28 Mar 22 A140 Curing
A150 - Road drainage system 5 29 Mar 22 04 Apr 22 A150 Road drainage system
A160 - Soling coat 5 05 Apr 22 11 Apr 22 A160 Soling coat
A170 - Road Marking 5 12 Apr 22 18 Apr 22 A170 Road Marking
A180 - Sign Installation 5 19 Apr 22 25 Apr 22 A180 Sign Installation
A190 - Grass plantation 5 26 Apr 22 02 May 22 A190 Grass plantation
A200 - Inspection 5 03 May 22 09 May 22 A200 Inspection

Printed 17:20:32 07 December 2021 Page 1 of 1