ABSTRACT OF COST
FIRST FLOOR + SECOND FLOOR + MUMTY
ITEM P.W. NB QTY. UNIT RATE AMOUNT
DISCRIPTION
D. O
No. No. No. Rs.
1 2 3 4 5 6 7 8

1 Plumbing 6.00 na 3000.00 18000.00

False Ceiling 2340 Sq.ft 80.00 187200

Toilet Flooring 264 Sq.ft 15.00 3960

Toilet Wall tiles 1268.00 Sq.ft 17.00 21556.00

Plaster 4596 Sq.ft 12.00 55152

Punning 4596.00 Sq.ft 10.00 45960.00

Wooden Flooring 283 Sq.ft 110.00 0

Tile Flooring(floor(1364) and skirting(436)) 1800.00 Sq.ft 15.00 27000.00

Air Conditioning 34.00 Sq.ft 500.00 17000.00

Painting 7000 Sq.ft 21.00 110000

Electrification 1950.00 Sq.ft 15.00 29250.00

Electric accessory installation 50 na 100.00 0

Fire Fighting na na na 6000

Bricks 1500 na 6.00 9000

Adhesives 40 na 480.00 19200

Sariya,Cement(85),morang(120),balu(150) 400 95 25.00 49150

Kitchen Tile 110 sq.ft 50.00 0

Toilet Granite 60.00 Sq.ft 120.00 7000.00

Windows na na na 23000.00

Carpenter na na na 10000.00

Staircase polish and scrubbing na na na 12000.00

Miscellaneous 0.00
vishnu 8000.00
cleaning 20000.00
labour work 20000.00
plumbing material 7000.00
electrical material 8000.00
stone laying 4000.00
freight 5000.00

Total 722428

Architect's Fee 0

Net Total 722428.00

Say Rs.