Project Management

with
Primavera P6 Professional R16.2

Trainer: Asif Raza M. Engg.


Head of Department, Civil Engineering
Quaid e Azam College of Engineering and Technology, Sahiwal
Understanding Relationships
Understanding Relationships
• Predecessor:
An activity whose start or finish controls start
or finish of another activity.

• Successor:
An activity whose start or finish is controlled
by start or finish of another activity.
Understanding Relationships
Understanding Relationships
• There are four types of relationships

– Finish to start (FS)


– Start to start (SS)
– Finish to finish (FF)
– Start to finish (SF)
Understanding Relationships
Understanding Relationships
Understanding Relationships
Understanding Relationships
Understanding Relationships
Understanding Relationships
Understanding Relationships
• Constraints
– Start on
– Finish on
– As late as possible
– Start on or before
– Start on or after
– Finish on or before
– Finish on or after
– Mandatory start
– Mandatory finish
Adding Relationships
To add relationships click on relationships tabs in bottom layout of Activities window
Adding Relationships in Sample Project
Activity
ID Activity Name Successor Relationship
A1000 Start of a Project A1010 SS
A1010 Contract Agreement A1020 FS
Mobilization and
A1020 Temporary facilities A1030 FS
A1030 Initital Survey A1040 FS
A1040 Site Clearance A1050 FS
A1050 Final Survey A1060 FS
A1060 Start of Earthwork A1070 SS
A1070 Excavation Layout A1080 FS
Excavation for
A1080 Foundations A1090 FS
A1090 Termite Proofing A1120 FS
A1100 Backfilling A1210 FF
A1110 Finish of Earthwork A1100 FF
Start of Foundations
A1120 structure work A1130 FS
A1130 Layout for PCC A1140 FS
A1140 PCC under Footings A1150,60 FS
A1150 Column Footing A1170 FS
A1160 Wall Footings FS
A1170 Columns upto Plinth FS
A1180 Plinth Beam A1160,70 FS
External and Internal
A1190 Water Proofing A1200 FS
A1200 Horizantal DPC A1210 FS
Finish of foundations
A1210 structure work FF
Adding Relationships in Sample Project
• Red Color Bars= Critical Activities and Remaining

• Green Color Bars=Non Critical Activities and Remaining

• Black Bars=Summary of WBS

• Sloid Red Lines=Critical Path and Driving Relation

• Black Solid Lines=Non critical path and driving relation

• Dotted Black Lines=Non Critical Path and Non driving relation, there
is some float in this activity
Scheduling Algorithm
Scheduling Algorithm
Scheduling Algorithm