Q-TARP663.1 General
Q-TARP66 3 01-Jul-21 04-Jul-21 04-Jul-21, Q-TARP663.1 General
A1000 Award Of Contract 1 01-Jul-21 01-Jul-21 Award Of Contract
A1010 Initial Kick Of Meeting 1 04-Jul-21 04-Jul-21 Initial Kick Of Meeting
Q-TARP663.2 Documentation
Q-TARP66 10 05-Jul-21 15-Jul-21 15-Jul-21, Q-TARP663.2 Documentation
A1020 Material Approvals & Other Documentations 10 05-Jul-21 15-Jul-21 Material Approvals & Other Documentations
Q-TARP663.3 Construction
Q-TARP66 131 18-Jul-21 16-Dec-21 16-Dec-21, Q-TARP663.3 Construction
A1030 Installation Of Battery Bank & Associated Works 54 18-Jul-21 18-Sep-21 Installation Of Battery Bank & Associated Works
A1040 Testing and Commissioning of Battery Bank 24 12-Sep-21 09-Oct-21 Testing and Commissioning of Battery Bank
A1050 Installation Of UPS & Associated Works 68 21-Sep-21 08-Dec-21 Installation Of UPS & Associated Works
A1060 Testing and Commissioning of UPS 10 06-Dec-21 16-Dec-21 Testing and Commissioning of UPS
Q-TARP663.4 Documentation And Final Handov
Q-TARP66 14 13-Dec-21 28-Dec-21 28-Dec-21, Q-TARP663.4 Documentation And Final Handover
A1070 As Built & Final Documentation 13 13-Dec-21 27-Dec-21 As Built & Final Documentation
A1080 Final Handover 1 28-Dec-21 28-Dec-21 Final Handover