Current Residual
Main Decision Linked
Risk / Prevention Actions Main Action
Theme Risk (or Opportunity) Event Consequence (Impact) Risk Mitigation Actions Action (accept residual risk
TECOP
Opportunity (& Opportunity Realisation) Party
Party at …)
L M H L M H
TECOP
Opportunity (& Opportunity Realisation) Party
Party at …)
L M H L M H
Pending Free Issue Vendor documents are stil pending to be PDO's urgent intervention required to expedite the issue as this
Risk Impact on Completion of the project PDO
Vendor Documets received for free issue materials is pending for a long time.
Risk Pre-Start Up Audit Duration of Prestart Up Audit Completion of Project PDO Optimize the duration of Prestart up audit
On-Off valves are long lead items. This may - Meeting with PDO project team & function for any Vendor
AP Flare (On-Off
Risk adversaly affect the entire project completion, Impact on Schedule other alternative. (ADOR / - XTREM PTFE material testing at 266.5°C. METSO
valve)
if On-Off valves are not delivered in time. - Expediting meetings, teleconferance with vendor. METSO)
1 - 4 Gre n Periodic As es ment
Periodic As es ment PM
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5