HCMC MRT Ba Son Station Schedule [2020.11.

25]
Q'ty 2020 2021
Balance Work Info. B1F B2F PIC Oct Nov Dec Jan Feb
18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Balance Mechanical Works

BAS System
DDC Panel Installation 6 nos 4 2 Cang DDC Panel delivery Factory Test DDC Panel
24 days
4 workers 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 nos/day
BAS Device Installation 1 lot 1 1 Cang BAS device delivery BAS Device Installation
18 days
2 workers Long 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
pcs./day
Compressed Air System HPT incerase Manpower & catch up
Trunking & Copper Piping 1,500 m 1340 160 Danh Copper Piping
24 days
3 workers 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
63 m/day
Installation Pneumatic panel and connection 2 nos 2 0 Danh Equipment delivery Installation Pneumatic panel and connection
18 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2
0 pcs./day
HPT incerase Manpower & catch up
MSFD Connection 24 nos 22 2 Danh waiting installation work MSFD Connection
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2
pcs./day
HPT incerase Manpower & catch up
Ducting system
Duct work 448 m2 258 190 Gia Fabrication at factory Duct work
36 days
4 workers 10% Long 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
12 m2/day
Saccardo Nozzle 96 m2 96 Tiet Material Approval & Fabrication Saccardo Nozzle
36 days
4 workers 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
3 m2/day

BAS System Waiting install Equipment from HPT & SMJO


Terminal connection for equipments 1 lot 1 1 Cang Waititng Archi hand over Terminal connection for equipments
24 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
pcs./day Waiting install Equipment from Archi
Conduit & wiring for Shutter & Escalator 1 lot 1 1 Cang Waititng Archi hand over Conduit & wiring for Shutter & Escalator
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2
0 pcs./day
Waiting Archi hand over AHU area
Chilled Water System
Valve Installation and AHU connection 4 nos 2 2 Binh Waititng Archi hand over epoxy Valve Installation and AHU connection
36 days
4 workers Tien 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
pcs./day
Compressed Air System Waiting dismantle KD storage
Installation MSFD Tunnel 24 nos 22 2 Danh Installation MSFD Tunnel
36 days
4 workers 60% 0% Lam 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
1 pcs./day
Waiting Archi hand over Ceiling
Ducting system
Air Grille Installation 389 pcs 253 136 Long Waiting Archi hand over ceiling Air Grille installation
42 days
4 workers Gia 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
9 pcs./day
Fire Fighting System
Sprinkler head 2 lot 1 1 Binh Waiting Archi hand over Sprinkler head
24 days
2 workers 60% 30% 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
pcs./day
Fire Hydrant box and Extinguisher 100 pcs 80 20 Binh Waiting Archi hand over Fire Hydrant box and Extinguisher
24 days
3 workers 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
4 pcs./day Waiting Archi hand over Cylinder Room
FM200 1 lot 1 Long Waiting Archi hand over FM200 Equipment
18 days
FM200 Equipments & connect to cylinder 2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
pcs./day
Plumbing System
Sanitary Fixture and connection work 15 nos 12 3 Lam Waiting Archi hand over Sanitary Fixture (exclude of Toilet area) and connection work
24 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
pcs./day
Fire tank Room
Civil & Arch Finishing Work Waiting Archi hand over Waiting Archi hand over Fire Tank area
Duct work and grille 20 m2 0 20 Long Duct work
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2
2 m2/day Waiting Archi hand over Fire Tank area
Fire pump and Accessories (valve…) 2 lot 0 6 Binh Fire pump and Accessories
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2
Waiting Archi hand over Fire Tank area
pcs./day
Piping system 45 m 0 45 Binh Piping system
24 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 m/day Need be confirm Equipment delivery by SMJO
FF Control Panel 2 lot 0 2 Cang Control Panel provide and will delivery by SMJO Control Panel
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2
0 m/day
HCMC MRT Ba Son Station Schedule [2020.11.25]
Q'ty 2020 2021
Balance Work Info. B1F B2F PIC Oct Nov Dec Jan Feb
18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Drainage Pump room
Drainage pump and Accessories (valve…) 6 lot 4 2 Lam Drainage pump and Accessories
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2
pcs./day Waiting Archi hand over Pump room area
Piping system 40 m Lam Piping system
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2
Waiting Archi hand over Pump room area
3 m/day
Control Panel 6 lot 4 2 Cang Waiting Control Panel delivery Control Panel
18 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0 m/day
Foul Pump room
Foul pump and Accessories (valve…) 2 lot 1 2 Lam Drainage pump and Accessories
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 Waiting Archi hand over Pump room area
pcs./day
Piping system 16 m Binh Piping system
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2 Waiting Archi hand over Pump room area
1 m/day
Control Panel 2 lot 1 2 Cang Waiting Control Panel delivery Control Panel
12 days
2 workers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0 m/day
Water Tank Room Waiting Archi hand over
Civil & Arch Finishing Work
Cold Water pump and accessories 2 lot 2 Lam Water pump and accessories
12 days
4 Workers 4 4 4 4 4 4 4 4 4 4 4 4 Waiting Archi hand over Pump room area
0 pcs/day
Make-Up Water Pumps and accessories 2 nos 2 Make-Up Water Pumps and accessories
6 days Binh
3 workers 3 3 3 3 3 3 Waiting Archi hand over Pump room area
pcs./day
Piping system 65 m 65 Lam Piping system
24 days
4 workers 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
8 pcs./day Waiting Archi hand over Pump room area
Area E (Include Entrance 1+2+3)
Civil & Archi Finishing work Waiting Archi hand over

Installation Ducting 120 m2 120 Ducting


30 days
3 Workers 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Waiting Archi hand over area
4 m2/day
Installation FF + Chiller pipe 65 m 65 FF + Chiller pipe
30 days
2 Workers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 m/day Waiting Archi hand over area
Installation Plumbing pipe ( CIP, PPR) 63 m 63 Plumbing pipe ( CIP, PPR)
18 days
3 Workers 15% 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
4 m/day Waiting Archi hand over area
BAS Trunking and Cabling 1,655 m 1655 BAS Trunking and Cabling (1665m)
24 days
2 Workers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Waiting Archi hand over area
69 m/day
Equipment (FCU, Griller, Pump, Sprinkler, Hydrant box…) 1 lot 1 Equipment (FCU, Griller, Pump, Sprinkler, Hydrant box…)
36 days
3 Workers 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Toilet
Arch Finishing Work Arch Finishing Work Waiting Archi hand over Toilet area
Sanitary Fixture and connection work 123 nos 123 Sanitary Fixture and connection work
48 days B1F: C,D
4 workers 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
pcs./day