PROPOSED TIMELINE (CONSIDERING 65 WORKING DAYS FOR CONSTRUCTION WORKS AT SITE) FOR BDREN NEW OFFICE FITOUT WORK@

NAVANA HR TOWER
EACH CLUSTER-4 DAYS
DESIGN PHASE (15 WORKING DAYS) CONSTRUCTION PHASE (65 WORKING DAYS) RESPOSIBLE
SL.NO. DESCRIPTION OF WORKS REMARKS
VENDOR
1ST 2ND 3RD 4TH 5TH 6TH 7TH 8TH 9TH 10TH 11TH 12TH 13TH 14TH 15TH 16TH 17TH 18TH

Aug-01~Aug-04 Aug-05~Aug-08 Aug-09~Aug-12 Aug-13~Aug-16 Aug 17~Aug 20 Aug 21~Aug 24 Aug 25~Aug 28 Aug 29~Sep 01 Sep 02~Sep 05 Sep 06~Sep 09 Sep 10~Sep 13 Sep 14~Sep 17 Sep 18~Sep 21 Sep 22~Sep 25 Sep 26~Sep 29 Sep 30~Nov 03 Nov 04~Nov 07 Nov 08~Nov11
1 Site receiving,cleaning & temporary utility works
2 GFC drawing preparation FCA
3 Setting up of site office FCA
4 Site marking works FCA
5 Necessary Civil works@ new toilet block and pantry area FCA
6 Related plumbing works FCA
7 Cable tray installation works FCA
8 Electrical conduiting works FCA
9 IT & PA conduiting works FCA
10 Sprinkler piping FCA
11 Safety security conduiting works FCA
12 FCU units relocation FCA
13 HVAC copper and drain piping works FCA
14 HVAC ducting works FCA
15 Dry partition wall work FCA
16 Gypsum / solid ceiling framing works FCA
17 Electrical cabling works FCA
18 IT & PA cabling works FCA
19 Safety & security cabling works FCA
20 Board fixing works in solid ceiling FCA
21 Paint work of 1st coat FCA
22 Floor finish works of ceramic/ other tiles FCA
23 Glass partition/panel framing works FCA
24 Starting of loose furniture works (factory made) FCA
25 HVAC diffuser and return Grill installation works FCA
26 Electrical fitting works with switches & sockets FCA
27 IT & PA equipment installation works FCA
28 Safety & security equipment installation works FCA
29 Sprinkler head installation and pressure test FCA
30 Paint works of 2nd coat FCA
31 Floor finish works of wooden / vinyl floor FCA
32 Grid ceiling framing works FCA
33 Board fixing works in grid ceiling area FCA
34 Furniture delivery at site FCA
35 Furniture installation work FCA
36 Commissioning of electrical, PA, IT and other equipment FCA
37 Handover of Data Center infrastructure
38 Signage & wall paper / decorated paint works FCA
39 Paint works of last coat & touch ups FCA
40 Roller blinds installation work FCA
41 Additional works (if any) FCA
42 Hand over to the client FCA
Mode of
payment

Important Notes:

1. Each Cluster- 4 (Four) working days


2. The timeline gets activated the day after signing the agreement and receiving the retainer.
3. Site construction works: It is a 65 (working) days time-period project
4. GFC Drawing Preparation: 15 (Working) days
5. Date of Commencement: August 1, 2023 (Tentative. BdREN will confirm)
6. Handover Date: November 8, 2023 (After confirmation on*5 from BdREN)
7. Client needs to confirm the shared time slots with the Third party (if any) before giving approval to FCA to proceed with this timeline.
Any delay from LL/Third party (if any) end will create impact on this master timeline and FCA will not take any responsibilities for the delay caused by LL /Third party.
8. Payment is expected to be received from the Client as per approved Payment Terms. However, if payment is not received by due date, handover date will be deferred by the number of days payment is delayed.
9.Idle days due to pending decision from BdREN on drawing and specifications will also be calculated and handover date will be extended likewise.

*List of Holidays considered:

1. August 15, 2023 (National Mourning Day)- 1 day


2. September 6, 2023 (Janmashtami)- 1 day
3. September 28, 2023 (Eid e Miladunnabi)- 1 Day

Submitted by

Ar.Farhana Choudhury
Principal, Farhana Choudhury & Associates