You are on page 1of 3

HCMC MRT Ventilation Tower at BA SON Station Schedule [2020.11.

26]
2021
Nov Dec Jan Feb Mar
No. Generator Building 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
S M TWR F S S M TWR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S SM T WR F S SM TWR F S SM TWR F S SM TWR F S SM TWR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S S M TWR F S S M TWR F S S M TWR F S S M TWR F S S M T WR F S S M T W
2FL - Roof (Cooling Tower Space)
Civil Work
Structure Work Structure Work

Architecture Work
Waterproofing Topping Concrete Plinth on Topping Concrete
Waterproofing on Plinth
Mechanical Works
1 Chiller System
Equipment Cooling Tower (2 sets)
Make up Tank
Chemical Dosing (1pc)
Piping Cooling water pipe (30m)
Drainage water pipe (18m)
Make up water pipe (30m)
2 VRV system
Equipment PCU (11 units)
Trunking & Piping Trunking & Copper pipe (184m)
3 Plumbing
Equipment & piping Cold water pipe (30m) Bip tap (1pc)
4 BAS
Trunking BAS trunking (25m) & conduit
Wiring BAS wiring (150m)

Electrical Works
1 Cable tray 181 m Cable tray
20 days
2 Conduit 557 m Conduit
28 days
3 Small cable 3,340 m Small cable
22 days
4 Big cable 155 m Big cable
3 days
5 Lighting 31 pcs Lighting
10 days
6 Wiring device 4 pcs Wiring device
2 days
2FL - Cylinder Room
Civil Work
Structure Work Structure Work

Architecture Work
AAC Wall Wall Finishing Epoxy Painting

Mechanical Works
1 FM200
Piping Piping
Cylinder Cylinder (7pcs)
Control Panel Control Panel

Electrical Works
1 Conduit 30 m Conduit
6 days
2 Small cable 360 m Small cable
6 days
3 Lighting 3 pcs Lighting
1 days
4 Wiring device 1 pcs Wiring device
1 days
2FL - Others
Civil Work
Structure Work Structure Work

Architecture Work Arch Finighing Work

Mechanical Works
1 FM 200
Equipment Lighting, Strobe & Horn

Electrical Works
1 Cable tray 40 m Cable tray
4 days
2 Conduit 460 m Conduit
23 days
3 Small cable 1,989 m Small cable
17 days
4 Lighting 48 pcs Lighting
16 days
5 FA detector 33 pcs FA detector
11 days
6 Wiring device 22 pcs Wiring device
11 days

1/3
HCMC MRT Ventilation Tower at BA SON Station Schedule [2020.11.26]
2021
Nov Dec Jan Feb Mar
No. Generator Building 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
S M TWR F S S M TWR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S SM T WR F S SM TWR F S SM TWR F S SM TWR F S SM TWR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S S M TWR F S S M TWR F S S M TWR F S S M TWR F S S M T WR F S S M T W
1FL - ECS Plant Room
Civil Work
Structure Work Structure Work

Architecture Work
Epoxy Painting

Mechanical Works
1 Ventilation
MSFD MSFD Installation (4 pcs)
2 Air Compressor
Air Compressor 2 units Air Compressor Equipment (2 sets)
Piping Air Compressor pipe
3 Chiller System
Chiller 2 units Chiller Installation (2 pcs)
Cooling Pump 2 units Cooling Pump
Chiller Pump 2 units Chiller Pump
Expansion Tank 1 units Expansion Tank
Chemical Dosing Unit 1 units Chemical Dosing
Piping 176 m Chilled water pipe
4 Fire Protection System
Fire Hose Cabinet 2 nos Fire hose cabinet
Piping 70 m Fire-Fighting Pipe
5 Plumbing System
Cold Water Piping 91 m Cold water pipe
Drainage Piping 107 m Drainage water pipe
Waste/Foul Piping 76 m Foul/Waste water pipe
6 VRV Trunking & Piping 506 m Trunking & Copper pipe
7 BAS
BAS Trunking 60 m BAS trunking & conduit
BAS Wiring 1500 m BAS wiring

Electrical Works
1 Cable tray 151 m Cable tray
25 days
2 Conduit 280 m Conduit
19 days
3 Small cable 1,180 m Small cable
12 days
4 Big cable 876 m Big cable
9 days
5 Lighting 22 pcs Lighting
7 days
6 FA detector 10 pcs FA detector
3 days
7 Wiring device 8 pcs Wiring device
4 days
1FL - Generator Room
Civil Work
Structure Work Structure Work

Architecture Work
Dust-proof on Plinth Epoxy Painting Grass Wool

Mechanical Works
1 FM 200 - Equipment FM 200 Equipment Installation
2 FM 200 - Piping Fire-Fighting Pipe

Electrical Works
1 Cable tray 158 m Cable tray Cable tray
26 days
2 Conduit 330 m Conduit
18 days
3 Small cable 1,240 m Small cable
12 days
4 Lighting 23 pcs Lighting
8 days
5 FA detector 33 pcs FA detector
8 days
6 Wiring device 7 pcs Wiring device
3 days
1FL - Blower Room
Civil Work
Structure Work Structure Work

Architecture Work
AAC Wall Dust-Proof Epoxy Painting Grass Wool

Mechanical Works

Electrical Works
1 Cable tray 14 m Cable tray
3 days
2 Conduit 150 m Conduit
15 days
3 Small cable 450 m Small cable
8 days
4 Big cable 148 m Big cable
3 days
5 Lighting 4 pcs Lighting
2 days
6 FA detector 2 pcs FA detector
1 days
7 Wiring device 2 pcs Wiring device
1 days
1FL - Other Rooms
Civil Work
Structure Work Structure Work

Architecture Work
Arch Finighing Work

Electrical Works
1 Cable tray 20 m Cable tray
7 days
2 Conduit 323 m Conduit
22 days
2/3
HCMC MRT Ventilation Tower at BA SON Station Schedule [2020.11.26]
2021
Nov Dec Jan Feb Mar
No. Generator Building 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
S M TWR F S S M TWR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S SM T WR F S SM TWR F S SM TWR F S SM TWR F S SM TWR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S S M T WR F S S M TWR F S S M TWR F S S M TWR F S S M TWR F S S M T WR F S S M T W
3 Small cable 970 m Small cable
16 days
5 Lighting 11 pcs Lighting
6 days
6 FA detector 2 pcs FA detector
1 days
7 Wiring device 8 pcs Wiring device
4 days

3/3