GADANG ENGINEERING (M) SDN. BHD.

: V2 - KOTA DAMANSARA STATION TO DATARAN SUNWAY


PROJEK MASS TRANSIT LEMBAH KELANG - JAJARAN SUNGAI BULOH - KAJANG July-16
STATION

SCHEDULE SUMMARY KEY EVENTS STATUS HIGHLIGHTS & ISSUES OF CONCERN OVERALL STATUS OF V2
Item Date Progress Highlights

Impact
(Days)

Trend
Prog.
Forecast / ● Baseline Programme Rev. 07a submitted on 12th May 2015

Float
Var.
Description DPS Date
Award Date 10-Jul-12 Actual (A)

Notice to Proceed 26-Jul-12


Commence Utilities Relocation - KD25
17-Jan-13 17-Jan-13 A 0 Issues / Areas of Concern :
Commence 1st Bored Pile - Baseline Programme
Completion Date 29-Sep-16 5-Nov-12 22-Oct-12 A 14
Preliminaries Load Test Problem :
OVERALL PROGRESS (Rev.07a) Commence 1st Pile Cap - KD25 9-Feb-13 18-Jan-13 A 22 Cause : NIL
Consequence :
this period last period
Item Variance 12-Mar-13 25-Mar-13 A -13 Action :
(Rev.07a) (Rev.07a) Commence 1st Column - KD25

Overall Works Progress 99.71 97.86 1.85 Excavation at underpass 7-Feb-15 25-Feb-15 A -49 Construction
Problem : Delayed for Enternal works at Station
Planned Actual Variance Cause : Slow work by sub-contractor
Item SBG Launcing Pier KD25-DS07 17-Dec-14 21-Feb-15 A -66
(%) (%)
Consequence : Delay impact to follow on works - overall station completion
Construction Complete 100 99.71 -0.29 Practical Completion 29-Feb-16 25-Aug-16 -131 Action : Gadang to ensure any delays are mitigated by additional working hours or extra equipment

CRITICAL PATH TOTAL FLOAT PRINCIPAL ACTIVITIES STATUS RISK MANAGEMENT :


Principal Activity Planned qty Actual qty Variance

Piling (No) 622 622 0

Pilecap (Nos) 152 152 0

Pier (Nos) 140 140 0

Pier Heads (Nos) 140 140 0

Box Girder Erection (span) 124 124 0

LAND AQUISITION SAFETY, HEALTH & ENVIRONMENT OVERALL PROGRESS % S-CURVE SPI & EV TRENDS
Trend

Land Date Forecast /


Land Type Item No. Trend
Required Actual

Government w/o encum' 10-Jul-12 31-Mar-12 (A) Major Incidents 0

Government w/ encum' 27-Jul-12 27-Jul-12 Notices from DOE or DOSH 0

Private w/o encum' 29-Sep-12 29-Sep-12 Stop work orders from PDP 0

Private w/ encum' 31-Dec-12 31-Dec-12 NCR overdue for closure 10

People receiving SHE induction 0

CRITICAL PATH Tool Box Talk 70

PROJECT STATUS SUMMARY

Float > 50 Days Float between 0 & 50 Days OR > 50 with declining float Float < 0 Trend - Positive Trend - Unchanged / Improving Trend - Negative No Impact Program Impact

File:D:\MRTV2\Monthly Report 31 July 2016\KVMRT Dashboard V2 July 16.xlsxKVMRT Aug 16