SCHEDULE SUMMARY KEY EVENTS STATUS HIGHLIGHTS & ISSUES OF CONCERN OVERALL STATUS OF V2
Item Date Progress Highlights
Impact
(Days)
Trend
Prog.
Forecast / ● Baseline Programme Rev. 07a submitted on 12th May 2015
Float
Var.
Description DPS Date
Award Date 10-Jul-12 Actual (A)
Overall Works Progress 99.71 97.86 1.85 Excavation at underpass 7-Feb-15 25-Feb-15 A -49 Construction
Problem : Delayed for Enternal works at Station
Planned Actual Variance Cause : Slow work by sub-contractor
Item SBG Launcing Pier KD25-DS07 17-Dec-14 21-Feb-15 A -66
(%) (%)
Consequence : Delay impact to follow on works - overall station completion
Construction Complete 100 99.71 -0.29 Practical Completion 29-Feb-16 25-Aug-16 -131 Action : Gadang to ensure any delays are mitigated by additional working hours or extra equipment
LAND AQUISITION SAFETY, HEALTH & ENVIRONMENT OVERALL PROGRESS % S-CURVE SPI & EV TRENDS
Trend
Private w/o encum' 29-Sep-12 29-Sep-12 Stop work orders from PDP 0
Float > 50 Days Float between 0 & 50 Days OR > 50 with declining float Float < 0 Trend - Positive Trend - Unchanged / Improving Trend - Negative No Impact Program Impact