You are on page 1of 5

Data Date: 26-Nov-12

Activity ID

Page 1 of 5

Oakland Army Base


Construction Sequencing

Architectural Dimensions/Acumen Building Enterprise, Inc.


Software Used: Oracle Primavera P6 Release 8.1
Activity Name

Org
Dur

Rem
Dur

Start

Finish

Dur %
Comp

Total
Float

2013
Q4

OAB Construction
Construc
Sequencing Nov 2012
OAB SEQUENCING
SEQUE
PROJECT NOV 2012
MS MARITIME
MARIT

1081

1081

01-Apr-13

07-Jun-17

0%

Q1
01-Apr-13

1081

1081

01-Apr-13

07-Jun-17

0%

01-Apr-13

441

441

01-Apr-13

24-Dec-14

0%

640

01-Apr-13

67

01-Apr-13

84

84

01-Apr-13

30-Jul-13

0%

A1000

RELOCATE POWER POLES

20

20

01-Apr-13*

26-Apr-13

0%

A1010

RELOCATE UTILITIES CONFLICTING WITH MARITIME B

20

20

29-Apr-13

24-May-13

0%

71

A1020

RELOCATE UTILITY CONNECTION/SERVICES FOR WAR

40

40

03-Jun-13*

30-Jul-13

0%

67

37

37

01-Oct-13

22-Nov-13

0%

313

MS-1 MA
MARITIME PRELIMINARY DETOUR

MS-2 MARITIME
MA
DETOUR

Q2

01-Apr-13*

2014
Q3

Q4

Q2

2015
Q3

Q4

Q2

2016
Q3

Q4

Q1

Q2

10

01-Oct-13*

15-Oct-13

0%

313

10

10

08-Oct-13

22-Oct-13

0%

313

A1050

PLACE AGG BASE MARITIME BYPASS DETOUR

10

10

16-Oct-13

29-Oct-13

0%

313

16-Oct-13

A1060

INSTALL TEMP LIGHTING/SIGNALS MARTIME BYPASS D

15

15

16-Oct-13

05-Nov-13

0%

313

16-Oct-13

A1070

ASPHALT PAVE MARITIME BYPASS DETOUR

06-Nov-13

13-Nov-13

0%

313

A1080

INSTALL KRAIL / STRIPING / SIGNS MARITIME BYPASS D

14-Nov-13

20-Nov-13

0%

313

A1090

MOVE TRAFFIC ONTO MARITIME BYPASS DETOUR

21-Nov-13

22-Nov-13

0%

313

397

397

03-Jun-13

24-Dec-14

0%

640

03-Jun-13

363

363

03-Jun-13

06-Nov-14

0%

313

03-Jun-13

01-Oct-13*

15-Oct-13, INSTALL TEMPORARY DRAINAGE FOR MARITIME BYPASS DETOUR

08-Oct-13

22-Oct-13, ROUGH/FINE GRADE MARITIME BYPASS DETOUR


29-Oct-13, PLACE AGG BASE MARITIME BYPASS DETOUR

06-Nov-13
14-Nov-13
21-Nov-13

05-Nov-13, INSTALL TEMP LIGHTING/SIGNALS MARTIME BYPASS DETOUR


13-Nov-13, ASPHALT PAVE MARITIME BYPASS DETOUR
20-Nov-13, INSTALL KRAIL / STRIPING / SIGNS MARITIME BYPASS DETOUR
22-Nov-13, MOVE TRAFFIC ONTO MARITIME BYPASS DETOUR
24-Dec-14
06-Nov-14

A1160

INSTALL JOINT TRENCH MARITIME

55

55

03-Jun-13*

20-Aug-13

0%

375

A1100

DEMO CURB/GUTTER/SIDEWALK

25-Nov-13

04-Dec-13

0%

313

A1110

PULVERIZE EXISTING ASPHALT CONCRETE

03-Dec-13

05-Dec-13

0%

313

03-Dec-13

A1120

ROUGH GRADE TO SUBGRADE

06-Dec-13

12-Dec-13

0%

313

06-Dec-13

A1130

ROUGH IN WET UTILITIES

120

120

13-Dec-13

03-Jun-14

0%

313

13-Dec-13

A1150

FINE GRADE MARITIME

10

10

04-Jun-14

17-Jun-14

0%

313

A1190

INSTALL EBMUD WATERLINE

40

40

18-Jun-14

12-Aug-14

0%

313

A1200

INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS

20

20

06-Aug-14

02-Sep-14

0%

328

A1170

INSTALL BASE ROCK MARITIME

15

15

13-Aug-14

02-Sep-14

0%

313

A1180

INSTALL CURB & GUTTER / SIDEWALK

20

20

03-Sep-14

30-Sep-14

0%

313

A1240

INSTALL LIGHTS / SIGNALS

25

25

24-Sep-14

28-Oct-14

0%

313

A1210

ASPHALT PAVE MARITIME

01-Oct-14

07-Oct-14

0%

313

A1220

RAISE UTILITIES

15

15

08-Oct-14

28-Oct-14

0%

313

A1230

INSTALL STRIPING / SIGNAGE

29-Oct-14

04-Nov-14

0%

313

29-Oct-14

A1250

SWITCH TRAFFIC ONTO MARITIME

05-Nov-14

06-Nov-14

0%

313

20-Aug-13, INSTALL JOINT TRENCH MARITIME


25-Nov-13

04-Dec-13, DEMO CURB/GUTTER/SIDEWALK


05-Dec-13, PULVERIZE EXISTING ASPHALT CONCRETE
12-Dec-13, ROUGH GRADE TO SUBGRADE
03-Jun-14, ROUGH IN WET UTILITIES
04-Jun-14

17-Jun-14, FINE GRADE MARITIME

18-Jun-14

12-Aug-14, INSTALL EBMUD WATERLINE

06-Aug-14

02-Sep-14, INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS

13-Aug-14

02-Sep-14, INSTALL BASE ROCK MARITIME

03-Sep-14

30-Sep-14, INSTALL CURB & GUTTER / SIDEWALK

24-Sep-14
01-Oct-14

28-Oct-14, INSTALL LIGHTS / SIGNALS


07-Oct-14, ASPHALT PAVE MARITIME

08-Oct-14

28-Oct-14, RAISE UTILITIES


04-Nov-14, INSTALL STRIPING / SIGNAGE

34

34

07-Nov-14

24-Dec-14

0%

640

05-Nov-14
06-Nov-14, SWITCH TRAFFIC ONTO MARITIME
07-Nov-14
24-Dec-14

A2720

DEMO CURB/GUTTER/SIDEWALK

07-Nov-14

10-Nov-14

0%

640

07-Nov-14

10-Nov-14, DEMO CURB/GUTTER/SIDEWALK

A2730

PULVERIZE EXISTING ASPHALT CONCRETE

07-Nov-14

10-Nov-14

0%

640

07-Nov-14

10-Nov-14, PULVERIZE EXISTING ASPHALT CONCRETE

A2740

ROUGH GRADE TO SUBGRADE

11-Nov-14

12-Nov-14

0%

640

11-Nov-14

12-Nov-14, ROUGH GRADE TO SUBGRADE

A2750

ROUGH IN WET UTILITIES

10

10

13-Nov-14

26-Nov-14

0%

640

13-Nov-14

A2760

FINE GRADE MARITIME

27-Nov-14

28-Nov-14

0%

640

27-Nov-14

A2840

INSTALL LIGHTS / SIGNALS

10

10

28-Nov-14

11-Dec-14

0%

645

28-Nov-14

A2790

INSTALL BASE ROCK MARITIME

01-Dec-14

02-Dec-14

0%

640

01-Dec-14

A2810

INSTALL CURB & GUTTER / SIDEWALK

03-Dec-14

09-Dec-14

0%

640

03-Dec-14

A2820

ASPHALT PAVE MARITIME

10-Dec-14

11-Dec-14

0%

640

10-Dec-14

A2830

RAISE UTILITIES

12-Dec-14

18-Dec-14

0%

640

12-Dec-14

A2850

INSTALL STRIPING / SIGNAGE

19-Dec-14

22-Dec-14

0%

640

19-Dec-14

22-Dec-14, INSTALL STRIPING / SIGNAGE

A2860

OPEN FINAL ALIGNMENT MARITIME

23-Dec-14

24-Dec-14

0%

640

23-Dec-14

24-Dec-14, OPEN FINAL ALIGNMENT MARITIME

80

80

13-Dec-13

08-Apr-14

0%

353

80

80

13-Dec-13*

08-Apr-14

0%

353

BUILD STORM DRAIN OUTFALL

Milestone

Actual Level of Effort

Primary Baseline

Crtical Milestone

Critical Remaining Work

Baseline Milestone

Remaining Work

Remaining Level of Effort

Actual Work

Summary

2017
Q2
Q3
07-Jun-17

30-Jul-13, RELOCATE UTILITY CONNECTION/SERVICES FOR WAREHOUSES TO REMAIN


01-Oct-13
22-Nov-13

10

A1860

Q1

24-May-13, RELOCATE UTILITIES CONFLICTING WITH MARITIME BYPASS

03-Jun-13*

ROUGH/FINE GRADE MARITIME BYPASS DETOUR

MS-4 SD MARITIME OUTFALL

Q4

26-Apr-13, RELOCATE POWER POLES

INSTALL TEMPORARY DRAINAGE FOR MARITIME BYPA

MS-3.2 M
MARITIME STAGE 2

Q3

24-Dec-14

29-Apr-13

03-Jun-13*

Q1

30-Jul-13

A1040

MS-3.1 M
MARITIME STAGE 1

Q1

07-Jun-17

A1030

MS-3 MARITIME
MA
STREET

Print Date: 28-Jan-13

13-Dec-13
13-Dec-13*

PROGRESS SCHEDULE
Updated on January 28, 2013

26-Nov-14, ROUGH IN WET UTILITIES


28-Nov-14, FINE GRADE MARITIME
11-Dec-14, INSTALL LIGHTS / SIGNALS
02-Dec-14, INSTALL BASE ROCK MARITIME
09-Dec-14, INSTALL CURB & GUTTER / SIDEWALK
11-Dec-14, ASPHALT PAVE MARITIME
18-Dec-14, RAISE UTILITIES

08-Apr-14
08-Apr-14, BUILD STORM DRAIN OUTFALL

Date
19-Aug-11
28-Jan-13

Revision

Checked
Acumen
Acumen/TCC/RPP

Approved

Q4

Data Date: 26-Nov-12

Activity ID

Page 2 of 5

Oakland Army Base


Construction Sequencing

Architectural Dimensions/Acumen Building Enterprise, Inc.


Software Used: Oracle Primavera P6 Release 8.1
Activity Name

Org
Dur

Rem
Dur

Start

Finish

Dur %
Comp

Total
Float

2013
Q4

WEST BURMA
BU

Q1

Q2

2014

596

596

02-Oct-13

22-Jan-16

0%

Q3
02-Oct-13

17

17

02-Oct-13

25-Oct-13

0%

331

02-Oct-13

WB-1 WE
WEST BURMA DETOUR

Print Date: 28-Jan-13

Q4

Q1

Q2

2015
Q3

Q4

Q1

2016

Q2

Q3

Q4

Q3

Q4

Q1

2017
Q2
Q3

25-Oct-13

A2520

INSTALL TEMPORARY DRAINAGE FOR W BURMA BYPA

02-Oct-13*

03-Oct-13

0%

331

02-Oct-13*

A2530

ROUGH/FINE GRADE W BURMA BYPASS DETOUR

04-Oct-13

07-Oct-13

0%

331

04-Oct-13

07-Oct-13, ROUGH/FINE GRADE W BURMA BYPASS DETOUR

A2540

PLACE AGG BASE W BURMA BYPASS DETOUR

08-Oct-13

09-Oct-13

0%

331

08-Oct-13

09-Oct-13, PLACE AGG BASE W BURMA BYPASS DETOUR

A2550

INSTALL TEMP LIGHTING/SIGNALS W BURMA BYPASS D

10-Oct-13

17-Oct-13

0%

331

10-Oct-13

A2560

ASPHALT PAVE W BURMA BYPASS DETOUR

18-Oct-13

21-Oct-13

0%

331

18-Oct-13

21-Oct-13, ASPHALT PAVE W BURMA BYPASS DETOUR

A2570

INSTALL KRAIL / STRIPING / SIGNS W BURMA BYPASS D

22-Oct-13

23-Oct-13

0%

331

22-Oct-13

23-Oct-13, INSTALL KRAIL / STRIPING / SIGNS W BURMA BYPASS DETOUR

A2580

MOVE TRAFFIC ONTO W BURMA BYPASS DETOUR

24-Oct-13

25-Oct-13

0%

331

178

178

28-Oct-13

10-Jul-14

0%

331

24-Oct-13
25-Oct-13, MOVE TRAFFIC ONTO W BURMA BYPASS DETOUR
28-Oct-13
10-Jul-14
28-Oct-13

WB-1 WE
WEST BURMA RECONSTRUCT

Q1
Q2
22-Jan-16

03-Oct-13, INSTALL TEMPORARY DRAINAGE FOR W BURMA BYPASS DETOUR

17-Oct-13, INSTALL TEMP LIGHTING/SIGNALS W BURMA BYPASS DETOUR

A1600

ROUGH GRADE TO SUBGRADE

20

20

28-Oct-13

25-Nov-13

0%

331

A1900

INSTALL LIGHTWEIGHT CELLULAR CONCRETE FILL

40

40

26-Nov-13

27-Jan-14

0%

331

A1610

ROUGH IN WET UTILITIES

40

40

28-Jan-14

24-Mar-14

0%

331

A1620

FINE GRADE WEST BURMA

10

10

25-Mar-14

07-Apr-14

0%

331

A1630

INSTALL JOINT TRENCH WEST BURMA

20

20

08-Apr-14

05-May-14

0%

331

08-Apr-14

05-May-14, INSTALL JOINT TRENCH WEST BURMA

A1640

INSTALL EBMUD WATERLINE

20

20

08-Apr-14

05-May-14

0%

331

08-Apr-14

05-May-14, INSTALL EBMUD WATERLINE

A1650

INSTALL BASE ROCK WEST BURMA

10

10

06-May-14

19-May-14

0%

331

A1660

INSTALL CURB & GUTTER / SIDEWALK

20

20

20-May-14

16-Jun-14

0%

331

20-May-14

A1670

INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS

10

10

20-May-14

02-Jun-14

0%

341

20-May-14

A1680

ASPHALT PAVE WEST BURMA

17-Jun-14

23-Jun-14

0%

331

17-Jun-14

A1690

RAISE UTILITIES

24-Jun-14

30-Jun-14

0%

336

24-Jun-14

A1700

INSTALL LIGHTS / SIGNALS

10

10

24-Jun-14

07-Jul-14

0%

331

24-Jun-14

A1710

INSTALL STRIPING / SIGNAGE

08-Jul-14

09-Jul-14

0%

331

08-Jul-14

09-Jul-14, INSTALL STRIPING / SIGNAGE

A1720

SWITCH TRAFFIC ONTO WEST BURMA

10-Jul-14

10-Jul-14

0%

331

10-Jul-14

10-Jul-14, SWITCH TRAFFIC ONTO WEST BURMA


19-Oct-15

25-Nov-13, ROUGH GRADE TO SUBGRADE

26-Nov-13

27-Jan-14, INSTALL LIGHTWEIGHT CELLULAR CONCRETE FILL

28-Jan-14

24-Mar-14, ROUGH IN WET UTILITIES

25-Mar-14

07-Apr-14, FINE GRADE WEST BURMA

06-May-14

19-May-14, INSTALL BASE ROCK WEST BURMA


16-Jun-14, INSTALL CURB & GUTTER / SIDEWALK
02-Jun-14, INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS
23-Jun-14, ASPHALT PAVE WEST BURMA
30-Jun-14, RAISE UTILITIES
07-Jul-14, INSTALL LIGHTS / SIGNALS

22-Jan-16

70

70

19-Oct-15

22-Jan-16

0%

A1470

ROUGH GRADE TO SUBGRADE

19-Oct-15*

23-Oct-15

0%

A1480

ROUGH IN WET UTILITIES

20

20

26-Oct-15

20-Nov-15

0%

A1490

FINE GRADE WEST BURMA

23-Nov-15

27-Nov-15

0%

A1500

INSTALL JOINT TRENCH WEST BURMA

10

10

30-Nov-15

11-Dec-15

0%

30-Nov-15

11-Dec-15, INSTALL JOINT TRENCH WEST BURMA

A1510

INSTALL EBMUD WATERLINE

10

10

30-Nov-15

11-Dec-15

0%

30-Nov-15

11-Dec-15, INSTALL EBMUD WATERLINE

A1520

INSTALL BASE ROCK WEST BURMA

14-Dec-15

18-Dec-15

0%

A1530

INSTALL CURB & GUTTER / SIDEWALK

10

10

21-Dec-15

01-Jan-16

0%

21-Dec-15

A1540

INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS

21-Dec-15

25-Dec-15

0%

21-Dec-15

A1550

ASPHALT PAVE WEST BURMA

04-Jan-16

05-Jan-16

0%

04-Jan-16

A1560

RAISE UTILITIES

06-Jan-16

12-Jan-16

0%

06-Jan-16

A1570

INSTALL LIGHTS / SIGNALS

10

10

06-Jan-16

19-Jan-16

0%

06-Jan-16

A1580

INSTALL STRIPING / SIGNAGE

20-Jan-16

21-Jan-16

0%

20-Jan-16

A1590

SWITCH TRAFFIC ONTO WEST BURMA

22-Jan-16

22-Jan-16

0%

70

70

02-Jul-15

07-Oct-15

0%

435

02-Jul-15

22-Jan-16
22-Jan-16, SWITCH TRAFFIC ONTO WEST BURMA
07-Oct-15

70

70

02-Jul-15

07-Oct-15

0%

435

02-Jul-15

WB-2 WEST
WE
BURMA STREET

EAST BURMA
BUR
EB-1 EAS
EAST BURMA STREET

19-Oct-15*

23-Oct-15, ROUGH GRADE TO SUBGRADE

26-Oct-15

20-Nov-15, ROUGH IN WET UTILITIES

23-Nov-15

27-Nov-15, FINE GRADE WEST BURMA

14-Dec-15

18-Dec-15, INSTALL BASE ROCK WEST BURMA


01-Jan-16, INSTALL CURB & GUTTER / SIDEWALK
25-Dec-15, INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS
05-Jan-16, ASPHALT PAVE WEST BURMA
12-Jan-16, RAISE UTILITIES
19-Jan-16, INSTALL LIGHTS / SIGNALS
21-Jan-16, INSTALL STRIPING / SIGNAGE

07-Oct-15

A1730

ROUGH GRADE TO SUBGRADE

02-Jul-15

08-Jul-15

0%

435

A1740

ROUGH IN WET UTILITIES

20

20

09-Jul-15

05-Aug-15

0%

435

A1750

FINE GRADE EAST BURMA

06-Aug-15

12-Aug-15

0%

435

A1760

INSTALL JOINT TRENCH EAST BURMA

10

10

13-Aug-15

26-Aug-15

0%

435

13-Aug-15

26-Aug-15, INSTALL JOINT TRENCH EAST BURMA

A1770

INSTALL EBMUD WATERLINE

10

10

13-Aug-15

26-Aug-15

0%

435

13-Aug-15

26-Aug-15, INSTALL EBMUD WATERLINE

A1780

INSTALL BASE ROCK EAST BURMA

27-Aug-15

02-Sep-15

0%

435

A1800

INSTALL CURB & GUTTER / SIDEWALK

10

10

03-Sep-15

16-Sep-15

0%

435

03-Sep-15

A1790

INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS

03-Sep-15

09-Sep-15

0%

440

03-Sep-15

Milestone

Actual Level of Effort

Primary Baseline

Crtical Milestone

Critical Remaining Work

Baseline Milestone

Remaining Work

Remaining Level of Effort

Actual Work

Summary

02-Jul-15

08-Jul-15, ROUGH GRADE TO SUBGRADE

09-Jul-15
06-Aug-15

27-Aug-15

PROGRESS SCHEDULE
Updated on January 28, 2013

Date
19-Aug-11
28-Jan-13

05-Aug-15, ROUGH IN WET UTILITIES


12-Aug-15, FINE GRADE EAST BURMA

02-Sep-15, INSTALL BASE ROCK EAST BURMA


16-Sep-15, INSTALL CURB & GUTTER / SIDEWALK
09-Sep-15, INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS

Revision

Checked
Acumen
Acumen/TCC/RPP

Approved

Q4

Data Date: 26-Nov-12

Activity ID

Activity Name

Org
Dur

Rem
Dur

Start

Finish

Dur %
Comp

Total
Float

ASPHALT PAVE EAST BURMA

A1820

RAISE UTILITIES

A1830

INSTALL LIGHTS / SIGNALS

A1840

INSTALL STRIPING / SIGNAGE

A1850

SWITCH TRAFFIC ONTO EAST BURMA

WAKE AVE
WA-1 WA
WAKE DETOUR

Print Date: 28-Jan-13

2013
Q4

A1810

Page 3 of 5

Oakland Army Base


Construction Sequencing

Architectural Dimensions/Acumen Building Enterprise, Inc.


Software Used: Oracle Primavera P6 Release 8.1

Q1

Q2

2014
Q3

Q4

Q1

Q2

2015
Q3

Q4

Q1

Q2

2016
Q3

Q1

435

17-Sep-15

21-Sep-15

25-Sep-15

0%

440

21-Sep-15

10

10

21-Sep-15

02-Oct-15

0%

435

21-Sep-15

05-Oct-15

06-Oct-15

0%

435

05-Oct-15

06-Oct-15, INSTALL STRIPING / SIGNAGE

07-Oct-15

07-Oct-15

0%

435

07-Oct-15

07-Oct-15, SWITCH TRAFFIC ONTO EAST BURMA

78

78

01-Oct-13

27-Jan-14

0%

807

01-Oct-13

17

17

01-Oct-13

24-Oct-13

0%

807

01-Oct-13

01-Oct-13*

02-Oct-13

0%

807

01-Oct-13*

03-Oct-13

04-Oct-13

0%

807

03-Oct-13

04-Oct-13, ROUGH/FINE GRADE WAKE BYPASS DETOUR

A1280

PLACE AGG BASE WAKE BYPASS DETOUR

07-Oct-13

08-Oct-13

0%

807

07-Oct-13

08-Oct-13, PLACE AGG BASE WAKE BYPASS DETOUR

A1290

INSTALL TEMP LIGHTING/SIGNALS WAKE BYPASS DETO

09-Oct-13

16-Oct-13

0%

807

09-Oct-13

A1300

ASPHALT PAVE WAKE BYPASS DETOUR

17-Oct-13

18-Oct-13

0%

807

17-Oct-13

18-Oct-13, ASPHALT PAVE WAKE BYPASS DETOUR

A1310

INSTALL KRAIL / STRIPING / SIGNS WAKE BYPASS DETO

21-Oct-13

22-Oct-13

0%

807

21-Oct-13

22-Oct-13, INSTALL KRAIL / STRIPING / SIGNS WAKE BYPASS DETOUR

A1320

MOVE TRAFFIC ONTO WAKE BYPASS DETOUR

23-Oct-13

24-Oct-13

0%

807

61

61

25-Oct-13

27-Jan-14

0%

807

ROUGH GRADE TO SUBGRADE

25-Oct-13

28-Oct-13

0%

807

25-Oct-13

A1340

ROUGH IN WET UTILITIES

20

20

29-Oct-13

26-Nov-13

0%

807

29-Oct-13

A1360

FINE GRADE WAKE

27-Nov-13

02-Dec-13

0%

807

27-Nov-13

A1370

INSTALL JOINT TRENCH WAKE

10

10

03-Dec-13

16-Dec-13

0%

807

03-Dec-13

16-Dec-13, INSTALL JOINT TRENCH WAKE

A1380

INSTALL EBMUD WATERLINE

10

10

03-Dec-13

16-Dec-13

0%

807

03-Dec-13

16-Dec-13, INSTALL EBMUD WATERLINE

A1390

INSTALL BASE ROCK WAKE

17-Dec-13

18-Dec-13

0%

807

17-Dec-13

A1410

INSTALL CURB & GUTTER / SIDEWALK

10

10

19-Dec-13

06-Jan-14

0%

807

19-Dec-13

A1400

INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS

19-Dec-13

30-Dec-13

0%

812

19-Dec-13

A1430

ASPHALT PAVE WAKE

07-Jan-14

08-Jan-14

0%

807

07-Jan-14

A1440

RAISE UTILITIES

09-Jan-14

15-Jan-14

0%

812

09-Jan-14

A1420

INSTALL LIGHTS / SIGNALS

10

10

09-Jan-14

22-Jan-14

0%

807

09-Jan-14

A1450

INSTALL STRIPING / SIGNAGE

23-Jan-14

24-Jan-14

0%

807

23-Jan-14

24-Jan-14, INSTALL STRIPING / SIGNAGE

A1460

SWITCH TRAFFIC ONTO WAKE

27-Jan-14

27-Jan-14

0%

807

27-Jan-14

27-Jan-14, SWITCH TRAFFIC ONTO WAKE

1081

1081

01-Apr-13

07-Jun-17

0%

01-Apr-13

405

01-Apr-13

28-Oct-13, ROUGH GRADE TO SUBGRADE


26-Nov-13, ROUGH IN WET UTILITIES
02-Dec-13, FINE GRADE WAKE

18-Dec-13, INSTALL BASE ROCK WAKE


06-Jan-14, INSTALL CURB & GUTTER / SIDEWALK
30-Dec-13, INSTALL LIGHT POLE / SIGNAL POLE FOUNDATIONS
08-Jan-14, ASPHALT PAVE WAKE
15-Jan-14, RAISE UTILITIES
22-Jan-14, INSTALL LIGHTS / SIGNALS

07-Jun-17
04-Jun-14

296

296

01-Apr-13

04-Jun-14

0%

A2870

START MATERIAL HANDLING CONTRACT

01-Apr-13*

01-Apr-13

0%

01-Apr-13*

A2890

PREP MATERIAL HANDLING YARD TO ACCEPT IMPORT

20

20

02-Apr-13

29-Apr-13

0%

70

02-Apr-13

29-Apr-13, PREP MATERIAL HANDLING YARD TO ACCEPT IMPORT

A2930

INSTALL WICK DRAIN TEST UNDER NEW OUTFALL

20

20

02-Apr-13

29-Apr-13

0%

50

02-Apr-13

29-Apr-13, INSTALL WICK DRAIN TEST UNDER NEW OUTFALL

A2880

RELOCATE STORM DRAIN SYSTEM MH1

20

20

30-Apr-13

28-May-13

0%

50

A2900

TRUCK IMPORT FILL BROKERED BY CCIG

125

125

29-May-13

27-Nov-13

0%

50

A2910

INSTALL EROSION CONTROL MEASURES MH YARD

10

10

02-Dec-13

13-Dec-13

0%

50

A2920

LOAD/TRUCK/HAUL MH YARD DIRT TO ONSITE FILLS

100

100

16-Dec-13

07-May-14

0%

50

A2970

INSTALL NEW OUTFALL PIPE

20

20

08-May-14

04-Jun-14

0%

405

912

912

30-Apr-13

11-Nov-16

0%

148

01-Apr-13, START MATERIAL HANDLING CONTRACT

30-Apr-13

28-May-13, RELOCATE STORM DRAIN SYSTEM MH1

29-May-13

27-Nov-13, TRUCK IMPORT FILL BROKERED BY CCIG


02-Dec-13

13-Dec-13, INSTALL EROSION CONTROL MEASURES MH YARD

16-Dec-13

07-May-14, LOAD/TRUCK/HAUL MH YARD DIRT TO ONSITE FILLS


08-May-14

04-Jun-14, INSTALL NEW OUTFALL PIPE

30-Apr-13

11-Nov-16

A1890

CUT/CAP/RELOCATE EXISTING UTILITIES

10

10

30-Apr-13*

13-May-13

0%

640

A1880

DEMO EXISTING PAVEMENT / FACILITIES

14-May-13

20-May-13

0%

1045

14-May-13

20-May-13, DEMO EXISTING PAVEMENT / FACILITIES

A1920

RELOCATE EXISTING DIRT ONSITE

14-May-13

20-May-13

0%

640

14-May-13

20-May-13, RELOCATE EXISTING DIRT ONSITE

A1910

INSTALL WICK DRAINS

25

25

27-Apr-15*

29-May-15

0%

148

A1930

IMPORT FILL INC SURCHARGE

100

100

01-Jun-15

16-Oct-15

0%

148

A1940

SURCHARGE SETTLEMENT PERIOD

260

260

19-Oct-15

14-Oct-16

0%

148

A1950

REMOVE SURCHARGE

20

20

17-Oct-16

11-Nov-16

0%

148

527

527

01-Oct-13

16-Oct-15

0%

Primary Baseline

Critical Remaining Work

Baseline Milestone

Remaining Work

Remaining Level of Effort

Actual Work

Summary

02-Oct-15, INSTALL LIGHTS / SIGNALS

16-Oct-13, INSTALL TEMP LIGHTING/SIGNALS WAKE BYPASS DETOUR

A1330

Actual Level of Effort

25-Sep-15, RAISE UTILITIES

02-Oct-13, INSTALL TEMPORARY DRAINAGE FOR WAKE BYPASS DETOUR

23-Oct-13
24-Oct-13, MOVE TRAFFIC ONTO WAKE BYPASS DETOUR
25-Oct-13
27-Jan-14

Crtical Milestone

Q4

18-Sep-15, ASPHALT PAVE EAST BURMA

24-Oct-13

Milestone

2017
Q2
Q3

27-Jan-14

CC 1 CENTRAL
CEN
GATEWAY

Q4

0%

ROUGH/FINE GRADE WAKE BYPASS DETOUR

MH 2 MA
MATERIALS HANDLING PROJECT

Q3

18-Sep-15

INSTALL TEMPORARY DRAINAGE FOR WAKE BYPASS D

MH 1 MA
MATERIALS HANDLING EARLY

Q2

17-Sep-15

A1270

CC CENTRAL
CENTR

Q1

A1260

WA-2 WAKE
WA
STREET

Q4

30-Apr-13*

13-May-13, CUT/CAP/RELOCATE EXISTING UTILITIES

27-Apr-15*

29-May-15, INSTALL WICK DRAINS

01-Jun-15

16-Oct-15, IMPORT FILL INC SURCHARGE


19-Oct-15

14-Oct-16, SURCHARGE SETTLEMENT PER


17-Oct-16

01-Oct-13

PROGRESS SCHEDULE
Updated on January 28, 2013

11-Nov-16, REMOVE SURCHARGE

16-Oct-15

Date
19-Aug-11
28-Jan-13

Revision

Checked
Acumen
Acumen/TCC/RPP

Approved

Data Date: 26-Nov-12

Activity ID

Activity Name

Org
Dur

Rem
Dur

Start

Finish

Dur %
Comp

Total
Float

A2020

CUT/CAP/RELOCATE EXISTING UTILITIES

10

10

A2010

DEMO PAVEMENT / FACILITIES

10

10

A1960

BUILD WATER STORAGE POND FOR CC1 SITE

20

20

A2480

INSTALL WICK DRAINS

60

60

A2490

IMPORT FILL INC SURCHARGE

100

A2500

SURCHARGE SETTLEMENT PERIOD

A2510

REMOVE SURCHARGE

CC 2 CENTRAL
CEN
GATEWAY

01-Oct-13*

Q1

16-Oct-13

29-Oct-13

0%

16-Oct-13

30-Oct-13*

27-Nov-13

0%

30-Oct-13*

02-Dec-13

26-Feb-14

0%

100

27-Feb-14

16-Jul-14

0%

262

262

17-Jul-14

17-Jul-15

0%

65

65

20-Jul-15

16-Oct-15

0%

358

358

25-Jan-16

07-Jun-17

0%

01-Oct-13*

A2410

DEMO EXISTING PAVEMENT / FACILITIES

08-Feb-16

12-Feb-16

0%

A2470

BUILD WATER STORAGE POND FDOR CC2 SITE

20

20

15-Feb-16

11-Mar-16

0%

A2430

INSTALL WICK DRAINS

15

15

14-Mar-16

01-Apr-16

0%

A2440

IMPORT FILL INC SURCHARGE

23

23

04-Apr-16

04-May-16

0%

A2450

SURCHARGE SETTLEMENT PERIOD

260

260

05-May-16

03-May-17

0%

A2460

REMOVE SURCHARGE

25

25

04-May-17

07-Jun-17

0%

953

953

01-Apr-13

09-Dec-16

0%

128

01-Apr-13

576

576

01-Apr-13

01-Jul-15

0%

205

01-Apr-13

206
67

DEMO EXISTING PAVEMENT / FACILITIES

28-Oct-13

01-Nov-13

0%

67

28-Oct-13

A1990

BUILD WATER STORAGE POND FOR CE1 SITE

10

10

04-Nov-13

18-Nov-13

0%

67

04-Nov-13

A2290

INSTALL WICK DRAINS

25

25

19-Nov-13

30-Dec-13

0%

261

A2300

IMPORT FILL INC SURCHARGE

36

36

19-Mar-14

07-May-14

0%

205

A2310

SURCHARGE SETTLEMENT PERIOD

260

260

08-May-14

06-May-15

0%

205

A2320

REMOVE SURCHARGE

40

40

07-May-15

01-Jul-15

0%

205

953

953

01-Apr-13

09-Dec-16

0%

128

01-Apr-13*

26-Feb-14, INSTALL WICK DRAINS


16-Jul-14, IMPORT FILL INC SURCHARGE
17-Jul-15, SURCHARGE SETTLEMENT PERIOD
16-Oct-15, REMOVE SURCHARGE
25-Jan-16

0%

1076

0%

67

DEMO EXISTING PAVEMENT / FACILITIES

28-Oct-13

01-Nov-13

0%

67

28-Oct-13

A2990

BUILD WATER STORAGE POND FOR CE1 SITE

10

10

04-Nov-13

18-Nov-13

0%

67

04-Nov-13

A3020

INSTALL WICK DRAINS

25

25

07-Nov-14

11-Dec-14

0%

313

A3030

IMPORT FILL INC SURCHARGE

36

36

28-Aug-15

16-Oct-15

0%

128

A3040

SURCHARGE SETTLEMENT PERIOD

260

260

19-Oct-15

14-Oct-16

0%

128

A3050

REMOVE SURCHARGE

40

40

17-Oct-16

09-Dec-16

0%

128

70

70

28-Jan-14

05-May-14

0%

807

28-Jan-14

05-May-14

70

70

28-Jan-14

05-May-14

0%

807

28-Jan-14

05-May-14

01-Jul-15, REMOVE SURCHARGE

05-Apr-13, CUT/CAP/RELOCATE EXISTING UTILITIES

03-Jun-13*

25-Oct-13, DECONSTRUCT BUILDINGS


01-Nov-13, DEMO EXISTING PAVEMENT / FACILITIES
18-Nov-13, BUILD WATER STORAGE POND FOR CE1 SITE
07-Nov-14

11-Dec-14, INSTALL WICK DRAINS


28-Aug-15

CUT/CAP/RELOCATE EXISTING UTILITIES

10

10

28-Jan-14*

10-Feb-14

0%

807

DECONSTRUCT BUILDINGS

10

10

11-Feb-14

24-Feb-14

0%

807

11-Feb-14

A2060

DEMO EXISTING PAVEMENT / FACILITIES

25-Feb-14*

03-Mar-14

0%

807

25-Feb-14*

A2100

IMPORT FILL

45

45

04-Mar-14

05-May-14

0%

807

40

40

28-Jan-14

24-Mar-14

0%

837

28-Jan-14*

24-Feb-14, DECONSTRUCT BUILDINGS


03-Mar-14, DEMO EXISTING PAVEMENT / FACILITIES

04-Mar-14
28-Jan-14

05-May-14, IMPORT FILL


24-Mar-14

CUT/CAP/RELOCATE EXISTING UTILITIES

10

10

28-Jan-14*

10-Feb-14

0%

837

A2170

DEMO EXISTING PAVEMENT / FACILITIES

11-Feb-14

17-Feb-14

0%

837

A2140

EXCAVATE AND MOVE EXISTING STOCKPILE

25

25

18-Feb-14

24-Mar-14

0%

837

18-Feb-14

24-Mar-14, EXCAVATE AND MOVE EXISTING STOCKPILE

A2200

IMPORT FILL

23

23

18-Feb-14

20-Mar-14

0%

839

18-Feb-14

165

165

11-Jul-14

26-Feb-15

0%

594

20-Mar-14, IMPORT FILL


11-Jul-14

20

20

11-Jul-14

07-Aug-14

0%

594

28-Jan-14*
11-Feb-14

09-Dec-16, REMOVE SURCHARGE

10-Feb-14, CUT/CAP/RELOCATE EXISTING UTILITIES

A2150

Summary

14-Oct-16, SURCHARGE SETTLEMENT PER


17-Oct-16

A2130

Remaining Level of Effort

16-Oct-15, IMPORT FILL INC SURCHARGE

19-Oct-15

A2050

Actual Work

07-Jun-17, REMOV

09-Dec-16

25-Oct-13

Remaining Work

03-May-17, SURCHAR

01-Apr-13

05-Apr-13

Baseline Milestone

04-May-16, IMPORT FILL INC SURCHARGE

06-May-15, SURCHARGE SETTLEMENT PERIOD


07-May-15

03-Jun-13*

Primary Baseline

01-Apr-16, INSTALL WICK DRAINS

07-May-14, IMPORT FILL INC SURCHARGE

08-May-14

01-Apr-13*

Critical Remaining Work

11-Mar-16, BUILD WATER STORAGE POND FDOR CC2 SITE

30-Dec-13, INSTALL WICK DRAINS


19-Mar-14

Actual Level of Effort

12-Feb-16, DEMO EXISTING PAVEMENT / FACILITIES

18-Nov-13, BUILD WATER STORAGE POND FOR CE1 SITE

19-Nov-13

100

Crtical Milestone

05-Feb-16, CUT/CAP/RELOCATE EXISTING UTILITIES

01-Nov-13, DEMO EXISTING PAVEMENT / FACILITIES

Milestone

07-Jun-17

25-Oct-13, DECONSTRUCT BUILDINGS

100

EXCAVATE FOR LIGHTWEIGHT FILL ON WEST BURMA R

Q4

05-Apr-13, CUT/CAP/RELOCATE EXISTING UTILITIES

03-Jun-13*

01-Apr-13*

2017
Q2
Q3

01-Jul-15

0%

A2940

Q1

04-May-17
09-Dec-16

0%

RAILROAD

Q4

05-May-16

25-Oct-13

CN 2 NORTH
NO
GATEWAY

Q3

27-Nov-13, BUILD WATER STORAGE POND FOR CC1 SITE

04-Apr-16

05-Apr-13

CN 1 NORTH
NO
GATEWAY

Q2

14-Mar-16

03-Jun-13*

CN NORTH

Q1

15-Feb-16

01-Apr-13*

A3010

Q4

08-Feb-16

DECONSTRUCT BUILDINGS

2016
Q3

25-Jan-16*

100

CUT/CAP/RELOCATE EXISTING UTILITIES

Q2

29-Oct-13, DEMO PAVEMENT / FACILITIES

A2980

Q1

15-Oct-13, CUT/CAP/RELOCATE EXISTING UTILITIES

100

A3000

Q4

20-Jul-15

0%

CE2

2015
Q3

17-Jul-14

05-Feb-16

A2040

Q2

27-Feb-14

25-Jan-16*

DECONSTRUCT BUILDINGS

Q1

02-Dec-13

10

CUT/CAP/RELOCATE EXISTING UTILITIES

Q4

10

A1980

2014
Q3

0%

CUT/CAP/RELOCATE EXISTING UTILITIES

CE1

Q2

15-Oct-13

A2400

CE EAST

Print Date: 28-Jan-13

2013
Q4

A2030

Page 4 of 5

Oakland Army Base


Construction Sequencing

Architectural Dimensions/Acumen Building Enterprise, Inc.


Software Used: Oracle Primavera P6 Release 8.1

10-Feb-14, CUT/CAP/RELOCATE EXISTING UTILITIES


17-Feb-14, DEMO EXISTING PAVEMENT / FACILITIES

11-Jul-14

PROGRESS SCHEDULE
Updated on January 28, 2013

26-Feb-15

07-Aug-14, EXCAVATE FOR LIGHTWEIGHT FILL ON WEST BURMA RR

Date
19-Aug-11
28-Jan-13

Revision

Checked
Acumen
Acumen/TCC/RPP

Approved

Data Date: 26-Nov-12

Activity ID

Page 5 of 5

Oakland Army Base


Construction Sequencing

Architectural Dimensions/Acumen Building Enterprise, Inc.


Software Used: Oracle Primavera P6 Release 8.1
Activity Name

Org
Dur

Rem
Dur

Start

Finish

Dur %
Comp

Total
Float

Print Date: 28-Jan-13

2013
Q4

Q1

Q2

2014
Q3

Q4

Q1

Q2

2015
Q3

Q4

Q1

Q2

2016
Q3

Q4

A2950

INSTALL LIGHTWEIGHT FILL ON WEST BURMA RR

20

20

08-Aug-14

04-Sep-14

0%

594

A2960

BUILD RAILROAD

125

125

05-Sep-14

26-Feb-15

0%

594

400

400

02-Jun-15

12-Dec-16

0%

127

26-Feb-15, BUILD RAILROAD


02-Jun-15
02-Jun-15

WHARVES

300

300

02-Jun-15

25-Jul-16

0%

227

A4750

Install Retofit Piles - Wharf 6

100

100

02-Jun-15

19-Oct-15

0%

127

A4760

Form/Rebar/Pour Pile Caps

100

100

20-Oct-15

07-Mar-16

0%

227

A4770

Form/Rebar/Pour Wharf Deck

100

100

08-Mar-16

25-Jul-16

0%

227

300

300

20-Oct-15

12-Dec-16

0%

127

Wharf 6

Wharf 6 1
1/2
A4780

Install Retofit Piles - Wharf 6 1/2

100

100

20-Oct-15

07-Mar-16

0%

127

A4790

Form/Rebar/Pour Pile Caps

100

100

08-Mar-16

25-Jul-16

0%

127

A4800

Form/Rebar/Pour Wharf Deck

100

100

26-Jul-16

12-Dec-16

0%

127

300

300

02-Jun-15

25-Jul-16

0%

227

Wharf 7
A4810

Install Retofit Piles - Wharf 7

100

100

02-Jun-15*

19-Oct-15

0%

227

A4820

Form/Rebar/Pour Pile Caps

100

100

20-Oct-15

07-Mar-16

0%

227

A4830

Form/Rebar/Pour Wharf Deck

100

100

08-Mar-16

25-Jul-16

0%

227

Milestone

Actual Level of Effort

Primary Baseline

Crtical Milestone

Critical Remaining Work

Baseline Milestone

Remaining Work

Remaining Level of Effort

Actual Work

Summary

08-Aug-14
05-Sep-14

Q1

Q2

Q3

Q4

2017
Q2
Q3

Q4

04-Sep-14, INSTALL LIGHTWEIGHT FILL ON WEST BURMA RR


12-Dec-16
25-Jul-16

02-Jun-15

19-Oct-15, Install Retofit Piles - Wharf 6


20-Oct-15

07-Mar-16, Form/Rebar/Pour Pile Caps


08-Mar-16

25-Jul-16, Form/Rebar/Pour Wharf Deck


12-Dec-16

20-Oct-15
20-Oct-15

07-Mar-16, Install Retofit Piles - Wharf 6 1/2


08-Mar-16

25-Jul-16, Form/Rebar/Pour Pile Caps


26-Jul-16

02-Jun-15

19-Oct-15, Install Retofit Piles - Wharf 7


20-Oct-15

07-Mar-16, Form/Rebar/Pour Pile Caps


08-Mar-16

Date
19-Aug-11
28-Jan-13

12-Dec-16, Form/Rebar/Pour Wharf De


25-Jul-16

02-Jun-15*

PROGRESS SCHEDULE
Updated on January 28, 2013

Q1

Revision

25-Jul-16, Form/Rebar/Pour Wharf Deck

Checked
Acumen
Acumen/TCC/RPP

Approved