PECIKO ONSHORE DEVELOPMENT PROJECT

PHASE IV - PCK4 / EPSC3


MANHOUR ESTIMATE
NO DESCRIPTION SIZE QTY MANHOUR ESTIMATE TOTAL MANHOUR REMARKS
PE PS PC ENG DES CAD PE PS PC ENG DES CAD
ELECTRICAL ENGINEERING

1 Site Visit A4 2 40 40 0 0 0 80 80 0
2 Preparation deliverable list A4 1 10 10 0 0 0 10 10 0
3 Procurement - Engineering (Bulk Material) A4 1 30 0 0 0 30 0 0

LIST :
4 Electrical Load Balances and Consumer List A4 1 60 0 0 0 60 0 0
5 Cable List A4 1 10 20 0 0 0 10 20 0

MATERIAL TAKE OFF :


6 Cable Routing A4 1 10 20 10 0 0 0 10 20 10
7 Accessories for erection A4 1 10 20 10 0 0 0 10 20 10
8 Earthing layout A4 1 10 20 10 0 0 0 10 20 10

DRAWINGS:
9 Electrical Symbol and Legend A1 1 2 5 10 0 0 0 2 5 10
10 1-PR-9200 Normal Substation Cable Routing A1 1 5 10 15 0 0 0 5 10 15
11 1-PR-9200 Essential Substation Cable Routing A1 1 5 10 15 0 0 0 5 10 15
12 3-PR-9250 Substation Cable Routing A1 1 5 10 15 0 0 0 5 10 15
13 PPA Main Cable Routing - North A1 1 5 10 15 0 0 0 5 10 15
14 Electrical Cable Routing - Turbo Generator Area A1 1 5 10 15 0 0 0 5 10 15
15 Cable Routing - Power Plant A1 1 5 10 15 0 0 0 5 10 15
16 PPA Main Cable Routing - South A1 1 5 10 15 0 0 0 5 10 15
17 Substation Earthing Layout A1 1 5 10 15 0 0 0 5 10 15
18 PPA General Lighting Layout A1 1 5 10 15 0 0 0 5 10 15
19 Earthing Layout - Compression Unit Area A1 4 5 10 15 0 0 0 20 40 60
20 Earthing Layout - Slug Catcher Unit Area A1 4 5 10 15 0 0 0 20 40 60
21 Earthing Layout - Scrappe and Manifoldr Unit Area A1 4 5 10 15 0 0 0 20 40 60
22 Earthing Layout - Oily Water Treatment A1 4 5 10 15 0 0 0 20 40 60
23 Lighting Layout - Substation A1 4 5 10 15 0 0 0 20 40 60
24 Lighting Layout - Compression Unit Area A1 4 5 10 15 0 0 0 20 40 60
25 Lighting Layout - Slug Catcher Unit Area A1 4 5 10 15 0 0 0 20 40 60
26 Lighting Layout - Scrappe and Manifoldr Unit Area A1 4 5 10 15 0 0 0 20 40 60
27 Lighting Layout - Oily Water Treatment A1 4 5 10 15 0 0 0 20 40 60

Page 1 of 5
PECIKO ONSHORE DEVELOPMENT PROJECT
PHASE IV - PCK4 / EPSC3
MANHOUR ESTIMATE
NO DESCRIPTION SIZE QTY MANHOUR ESTIMATE TOTAL MANHOUR REMARKS
PE PS PC ENG DES CAD PE PS PC ENG DES CAD
28 Cable Tray Layout - Substation A1 4 2 5 10 0 0 0 8 20 40
29 Cable Tray Layout - Compression Unit Area A1 4 2 5 10 0 0 0 8 20 40
30 Cable Tray Layout - Slug Catcher Unit Area A1 4 2 5 10 0 0 0 8 20 40
31 Cable Tray Layout - Scrappe and Manifoldr Unit Area A1 4 2 5 10 0 0 0 8 20 40
32 Cable Tray Layout - Oily Water Treatment A1 4 2 5 10 0 0 0 8 20 40
33 PPA - General Road Ligthing Layout A1 4 5 10 15 0 0 0 20 40 60
34 Cable schedule A3 1 20 40 15 0 0 0 20 40 15
35 Interconnection Diagram A1 1 10 40 15 0 0 0 10 40 15
36 HV Typical Diagram and Protective A1 1 5 20 15 0 0 0 5 20 15
37 LV Typical Diagram and Protective A1 1 5 20 15 0 0 0 5 20 15
38 Typical Installation - Power Design Standards A1 1 5 20 15 0 0 0 5 20 15
39 Typical Installation - Lighting Design Standards A1 1 5 20 15 0 0 0 5 20 15
40 Typical Installation - Earthing Design Standards A1 1 5 20 15 0 0 0 5 20 15
41 1-PR-9200 - Substation Arrangement A1 1 5 20 15 0 0 0 5 20 15
42 3-PR-9250 - Substation Arrangement A1 1 5 20 15 0 0 0 5 20 15
Electrical Building:
43 Lighting/outlet layouts - Main Electrical Room A1 1 2 5 15 0 0 0 2 5 15
44 Earthing Layout - Main Electrical Room A1 1 2 5 15 0 0 0 2 5 15
45 Cable Tray Layout - Main Electrical Room A1 1 2 5 15 0 0 0 2 5 15
46 Equipment Layout - Main Electrical Room A1 1 2 5 15 0 0 0 2 5 15
47 Detail design - Main Electrical Room A1 1 2 5 15 0 0 0 2 5 15
48 Lighting/outlet layouts - Instrument Technical Room A1 1 2 5 15 0 0 0 2 5 15
49 Earthing Layout - Instrument Technical Room A1 1 2 5 15 0 0 0 2 5 15
50 Cable Tray Layout - Instrument Technical Room A1 1 2 5 15 0 0 0 2 5 15
51 Equipment Layout - Instrument technical Room A1 1 2 5 15 0 0 0 2 5 15
52 Detail design - Instrument Technical Room A1 1 2 5 15 0 0 0 2 5 15
53 Lighting/outlet layouts - Transformer Room A1 1 2 5 15 0 0 0 2 5 15
54 Earthing Layout - Transformer Room A1 1 2 5 15 0 0 0 2 5 15
55 Cable Tray Layout - Transformer Room A1 1 2 5 15 0 0 0 2 5 15
56 Equipment Layout - Transformer Room A1 1 2 5 15 0 0 0 2 5 15
57 Detail design - Transformer Room A1 1 2 5 15 0 0 0 2 5 15

Tie-in :
58 Tie-in Schedule A3 1 15 30 0 0 0 15 30 0
59 Tie-in Procedure A4 1 30 0 0 0 30 0 0
60 Tie-in Drawings A1 4 10 20 25 0 0 0 40 80 100
61 As Buil Drawing A3/A1 100 1 1 2 0 0 0 100 100 200

Page 2 of 5
PECIKO ONSHORE DEVELOPMENT PROJECT
PHASE IV - PCK4 / EPSC3
MANHOUR ESTIMATE
NO DESCRIPTION SIZE QTY MANHOUR ESTIMATE TOTAL MANHOUR REMARKS
PE PS PC ENG DES CAD PE PS PC ENG DES CAD

Sub Totals 0 0 0 687 1170 1435


3292
NOTE
Man hour Electrical Engineering of scope refer to
Appendix 2 - Battery Limits of Electrical Systems and PDCS

Page 3 of 5
PECIKO ONSHORE DEVELOPMENT PROJECT
PHASE IV - PCK4 / EPSC3
MANHOUR ESTIMATE
NO DESCRIPTION SIZE QTY MANHOUR ESTIMATE TOTAL MANHOUR COST ESTIMATE TOTAL COST REMARKS
PE PS PC ENG DES CAD PE PS PC ENG DES CAD PE PS PC ENG DES CAD US$

INSTRUMENTATION
General
1 Site Visit 1 40 40 40 40 0
2 Coordination meeting 1 20 20 20 20 0
3 Project management 0 0 0
4 Data collection for process 1 20 20 20 20 0
5 Preparation of general scope of work 1 10 10 10 10 0
6 Preparation deliverable list 1 10 10 10 10 0
7 Final Report 1 16 10 16 10 0
8 Procurement - Engineering (Tech. Evaluation) 1 200 80 200 80 0
9 Review Engineering Construction 1 200 200 200 200 0
10 Review document supply by client & vendor 1 200 80 200 80 0
11 Instrument Installation Design(Construction) 1 200 80 200 80 0
12 Instrument Materials (MTO) 1 40 60 40 60 0
13 Job Site Instrument Check Out & Calibration 1 200 80 200 80 0
0 0 0
Specification 0 0 0
14 Instrument Control System Specification A4 1 20 20 0 0
15 General Specification Instrumentation A4 1 20 20 0 0
16 Instrument Design and Installation Specification A4 1 20 20 0 0
17 Instrument Inspection & Testing Specification A4 1 20 20 0 0
18 ESD/Fire & Gas System Specification A4 1 20 20 0 0
0 0 0
Data Sheet 0 0 0
19 Analyzer EA 2 4 8 0 0
20 Shutdown / Blowdown valve EA 91 4 364 0 0
21 Pressure Gauge EA 77 2 154 0 0
22 Restriction Orifice/Orifice plate EA 52 4 208 0 0
23 Flow Tarnsmitter EA 6 4 24 0 0
24 Control Valve EA 29 2 58 0 0
25 Vortex EA 5 3 15 0 0
26 Level Transmitter 4 0 0 0
-Displacer Type EA 47 3 141 0 0
-Differential Pressure Type EA 6 2 12 0 0
-Radar Level Type EA 3 3 9 0 0
-Capacitive level type EA 5 2 10 0 0
27 Level Gauge EA 27 2 54 0 0
28 Pressure Transmitter EA 58 2 116 0 0
29 Pressure Differential Transmitter EA 32 2 64 0 0
30 Pressure Safety Valve EA 37 2 74 0 0
31 Differential Pressure Gauge EA 8 3 24 0 0
32 Thermowell/temperature Gauge EA 25 3 75 0 0
33 Temperature Transmitter EA 41 4 164 0 0
34 Thermowell EA 7 3 21 0 0
35 Push button shut-down EA 4 2 8 0 0
0 0 0
36 Instrument Distribution Board 230 VAC Unit 1 2 2 0 0
37 Instrument Distribution Board 48 VDC Unit 1 3 3 0 0
38 Hydraulic power units Unit 3 2 6 0 0
39 PCS Marshalling cabinet Unit 2 2 4
40 SSS Marshalling cabinet Unit 3 2 6
0 0 0
41 Instrument List A4 207 2 4 414 828 0
42 I/O List A4 205 2 4 410 820
0 0 0
Calculation Notes 0 0 0
43 Compex Control Loop Narratives A4 0 0 0
44 Sizing and Selection of Instruments A4 1 80 80 0 0
45 Calculation Notes A4 1 40 40 0 0
46 Vendor Data and Drawings A4 1 40 20 40 20 0
47 Tie-in Schedule A4 0 0 0
48 Tie-in Procedure A4 0 0 0
49 Instrument certification schedule A4 1 40 40 0 0
0 0 0
Drawing 0 0 0
50 Instrumentation Drawing Index A1 1 3 6 10 3 6 10
51 Instrumentation Location Plan A1 40 3 8 15 120 320 600
52 Instrumentation Block Diagram A1 2 3 6 10 6 12 20
53 Cable list and cable routing Layouts A1 40 3 8 15 120 320 600
54 Instrument Cable Tray Layout A1 30 3 8 15 90 240 450
55 Instrument Grounding Layout A1 30 3 8 15 90 240 450
56 Instrumentation Hook-Up Diagram A3 36 3 6 10 108 216 360
57 Instrumentation Details A1 30 2 6 10 60 180 300
58 Trouble shooting diagram A1 70 3 6 10 210 420 700
59 Instrumentation Connection Diagram A1 15 3 8 15 45 120 225
60 Cause & Effect Charts (Instrument Input) A1 8 6 8 10 48 64 80
61 F&G drawings A1 5 3 8 15 15 40 75
62 Control Room Layout A3 2 3 6 10 6 12 20
63 Control panel Drawing A1 6 3 6 10 18 36 60
64 Interconnection and Termination Drawings A1 15 3 6 10 45 90 150
65 Power Single Line Diagram A3 3 4 6 10 12 18 30
66 Marshalling cabinet drawings A1 4 3 6 10 12 24 40
67 Instrumentation Cable Schedule A3 8 4 6 10 32 48 80
68 Tie-in Drawings A3 5 4 6 10 20 30 50
69 As-Built Drawings A1/A3 350 1 1 2 350 350 700
Sub Totals 5314 5144 5000