Professional Documents
Culture Documents
Code: 216W-PHMD-TP-C-0000105
Rev: B Sheet 1 of 14
APPR’D APPR’D
REV. DATE DESCRIPTION PREPARED CHECKED
DPTM. PROJ.
Project: 216W
Code: 216W-PHMD-TP-C-0000105
Rev: B Sheet 2 of 14
TABLE OF CONTENTS
GLOSSARY ................................................................................................................................... 3
1 INTRODUCTION ........................................................................................................................ 4
1.1 Project Description ........................................................................................................... 4
1.2 Purpose of the Document ................................................................................................ 6
1.3 Order of Precedence ......................................................................................................... 6
1.4 Definitions ......................................................................................................................... 6
1.5 Terminology ...................................................................................................................... 7
2 GENERAL DESIGN PHILOSOPHY .......................................................................................... 8
GLOSSARY
1 INTRODUCTION
SONATRACH has decided to develop the Peripheral Fields of Hassi Messaoud, which include the
development of the following fields:
Lot Nº01 – it concerns the development of five (5) fields located at the SOUTHERN
PERIPHERY of Hassi Messaud, the fields are:
This PROJECT LOT covers the gathering, a new Gas and Oil separation plant (GOSP) at Hassi
Guettar (HGA) and the transfer of gas and oil effluents to the existing Hassi Messaoud plants
(UTBS and CIS) for further treatment and stabilization of the oil and associated gas.
Lot Nº02 – it concerns the development of the EASTERN PERIPHERY of Hassi
Messaoud, the fields are:
This PROJECT LOT covers the gathering network and the multiphasic pumps at BRA and
Damrane to transfer the crude oil to the existing Rhourde el Baguel Plant for further
treatment and stabilization of the oil and associated gas.
Lot Nº03 – it concerns the development of peripheral NORD of Hassi Messaoud located at
Rhourde Chegga (RDC).
This PROJECT LOT covers the gathering network and the multiphasic pumps at RDC to
transfer the crude oil to the existing CINA plant at Hassi Messaoud.
Lot Nº04 – it concerns the development of the UPSIDE NORTH fields of Hassi Messaoud.
This PROJECT LOT covers the gathering network and a new Gas and Oil separation plant
(GOSP) located at UN2-1, to transfer the separated oil to the existing CINA Plant and the
gas to the existing ZCINA plant at Hassi Messaoud through different oil & gas pipelines.
In case of conflict between documents the ENGINEER shall take precedence in the following
order:
1. Algerian legal requirements (Algerian laws, edicts, regional or local regulations, etc.).
2. Sonatrach standards.
3. FEED documentation.
1.4 DEFINITIONS
INDEPENDENT
Inspection Body or Authority appointed by the CA
VERIFICATION BODY
1.5 TERMINOLOGY
The fundamental purpose of alarm annunciation (presentation to the operator) will be alert the
operator to deviations from normal operating conditions. The ultimate objective is to prevent, or
at least minimise, physical and economic loss by triggering operator intervention in response to
the alarm. A key factor in operator response effectiveness is the speed and accuracy with which
the operator can identify the alarms that require immediate action.
Prioritization of alarms
Design of alarms
The advent of computer based control systems has created a situation where it is possible to
configure large numbers of alarms with minimal cost or consideration as to whether they are truly
necessary. Historically, alarms have also been created in an unstructured manner. This has
resulted in:
- Too many alarms being configured (e.g., alarms that do not have associated operator
actions).
- Poor alarm system performance (e.g., bad actors, increased potential for alarm floods).
- Increased potential for operator error (e.g., operator missing an important alarm during a
flood or taking incorrect action based on a received alarm).
- Significant demand on operator and engineer resources and additional costs to rectify
alarm performance problems.
Alarm systems are often used to notify operators of events that do not meet the criteria for being
an alarm.
Operator notifications can represent abnormal that may not require an operator action.
Avoid nuisance alarms when change in process condition has not incurred or when alarm condition
comes and goes on a regular basis or intermittently.
During operation, an analysis of the alarm frequency will be carried out to detect nuisance alarms.
Nuisance alarms are alarms that indicate an abnormal condition when none exists.
The alarm philosophy would follow the latest Instrument Society of America (ISA) guidelines on
process control system alarms. The alarm philosophy must be applied to the design and
configuration of all control logic. Alarms will meet the definition and specific criteria defined below:
- The indication must be targeted to the operator to be an alarm, not to provide information to
an engineer, maintenance technician, or manager.
- The alarm must indicate a problem, not a normal process condition or normal operational
event (e.g., pump stopped, valve closed).
- There must be a defined operator response to correct the condition and bring the process
back to a desired (safe and/or productive) state. If the operator does not need to respond,
then the condition should not be an alarm. A notification that has no associated operator
action should be defined as an alert or message. Acknowledging the alarm or logging a
measurement is not considered an operator response (does not correct the abnormal
situation). Typical operator responses to alarm include:
Notifications that do not meet the criteria for being an alarm fall into several categories:
Alert - An audible and/or visible means of indicating to the operator an abnormal equipment or
process condition that requires awareness. An alert will be indicated separately (segregated) from
an alarm indication.
Prompt - A notification which requires an action to be taken by the operator as part of normal
operation (e.g., start sequence when ready, take a sample, add material).
Message - Provides information about the status of normal operations that does not require the
operator to act. As an example, when a process or piece of equipment has moved from one mode
of operation to another, it may be desirable to inform the operator of this progress with a message
Events - Used for automated logging of discrete changes to the system or process (e.g., plant
equipment state changes, trips, alarm activation, and acknowledge). They are used primarily for
review and analysis (e.g., for post incident analysis). Equipment and process events should be
elevated to an alarm if there is an associated operator action(s).
The following basic alarm principles should be applied to alarm design and configuration:
- Each alarm should alert, inform and guide: The information presented to the operator
should not simply be the tag number of the measuring or sensing instrument but shall
(where possible) offer an indication of what has gone wrong and also why it has occurred.
- The alarm system should be designed to meet user needs and operate within ergonomic
requirements Ref.(2). This means that the support information alarm should:
o Be presented at a rate that the user can deal with particularly when the plant system
is upset or in an unusual condition.
Project: 216W
Code: 216W-PHMD-TP-C-0000105
Rev: B Sheet 12 of 14
- Every alarm presented to the operator should be relevant and unique: Alarms should be
designed so that they are worthy of operator action in all plant states and operating
conditions in which they are displayed. Each configured alarm shall be unambiguous and
not duplicated by other alarms. Multiple alarms should not be annunciated for a single
problem / event such as those requiring the same operator action.
- Every alarm should have a defined response: If there is no associated operator action then
the condition should not be configured as an alarm. Adequate time should be allowed for
the operator to analyze the situation and carry out a defined response.
- Adequate time should be allowed for the operator to carry out a defined response
- The consequence if the alarm is not treated properly by the operator should be explicit.
- Monitoring performance of the alarm system should be assessed during design and
commissioning to ensure that it is usable and effective under all operating conditions.
Regular auditing should be continued throughout the plant system life to confirm that good
performance is maintained.
- Engineering should follow structured methodology in which every alarm should be justified,
documented and properly engineered. This initial investment in the design should be
sufficient to avoid the operational problems which result at the end in overall higher lifetime
costs.
o Timely: Not long before any response is needed or too late to do anything.
o Prioritized: Indicating the importance that the operator deals with the problem.
Alarm management is an ongoing process that is never completed. The work process for effective
alarm management is defined by an alarm management lifecycle as described in the ISA-18.2
standard.
Detailed Design: Alarm design and HMI design. Output: Completed alarm design.
Implementation: Install alarms, initial testing, and initial training. Output: Alarm response
procedures
Operation: Operator responds to alarms, refresher training. Output: Alarm event data.
Maintenance: Inspection, repair and replacement, periodic testing. Output: Alarm reliability data.
Monitoring & Assessment: Monitor alarm data and report performance. Output: Alarm monitoring
reports, proposed changes.
Audit: Periodic audit of alarm management processes. Output: Recommendations for improvement
5 REFERENCES