SNBP Detailed Schedule on Electrical & Control PROJECT: SOUTH NEGROS

Room Building 25MWe BIOMASS-FIRED POWER PLANT

Activity ID Activity Name Orig Dur Target Start Target Finish 2019 2020 2021
A A A A A

SNBP Master EPM Sche


Schedule - UPD - Updated as of May 15, 2019 1107 06-Mar-17 27-Nov-20

MAJOR MILESTONES & KEY DATES 1107 06-Mar-17 27-Nov-20

DESIGN ENGINEERING 430 07-Jun-18 21-Nov-19

PRELIMINARIES & GENERAL


GENE PROJECT REQUIREMENTS 564 06-Mar-17 28-Jan-19

PROCUREMENT ENGINEERING
ENGINE 522 23-Apr-18 30-Jan-20

SITE DEVELOPMENT 884 22-Mar-17 18-Mar-20

CONSTRUCTION 741 15-Jan-18 18-Jul-20

NON-TECHNICAL BUILDINGS
BUILDI 545 15-Jan-18 19-Nov-19

POWERPLANT STRUCTURES
STRUCTU 566 16-Aug-18 18-Jul-20
#04 Boiler & #02 Deaerator - Construction
C (by SNBP) 515 16-Aug-18 19-May-20
#21 Electrical & Control Room 352 20-Dec-18 04-Mar-20
Pre-Construction Preparation 14 20-Dec-18 09-Jan-19
Civil Works 90 18-Jan-19 10-May-19
SNBP-CO-ECRO-1010 Survey & Setting-Out 7 18-Jan-19 25-Jan-19 Survey & Setting-Out
SNBP-CO-ECRO-1020 Foundation Works 45 26-Jan-19 21-Mar-19 Foundation Works
SNBP-CO-ECRO-1030 Building Structure (Civil Works) 60 18-Feb-19 04-May-19 Building Structure (Civil W
SNBP-CO-ECRO-1040 Building Structure (Architectural Finishes) 45 14-Mar-19 10-May-19 Building Structure (Archit
#21 Battery Charger (Equipment)
(Equipmen 42 13-Sep-19 31-Oct-19
SNBP-CO-ECRO-1050 Battery Charger - Install Equipment Unit 14 13-Sep-19 28-Sep-19 Battery Charger - Inst
SNBP-CO-ECRO-1060 Battery Charger - Pull cables and terminate 21 21-Sep-19 15-Oct-19 Battery Charger - Pul
SNBP-CO-ECRO-1070 Battery Charger - Instrumentation & Control (Loop Wiring Checks) 14 16-Oct-19 31-Oct-19 Battery Charger - Ins
#21 UPS (Equipment) 49 22-Jun-19 19-Aug-19
SNBP-CO-ECRO-1080 UPS - Install Equipment Unit 14 22-Jun-19 08-Jul-19 UPS - Install Equipment U
SNBP-CO-ECRO-1090 UPS - Pull cables and terminate 21 09-Jul-19 01-Aug-19 UPS - Pull cables and te
SNBP-CO-ECRO-1100 UPS - Instrumentation & Control (Loop Wiring Checks) 14 02-Aug-19 19-Aug-19 UPS - Instrumentation &
#21 Distributed Control System (DCS) 48 22-Jun-19 17-Aug-19
SNBP-CO-ECRO-1110 Distributed Control System: Install Equipment Unit 14 22-Jun-19 08-Jul-19 Distributed Control System
SNBP-CO-ECRO-1120 Distributed Control System: Pull cables and terminate 21 08-Jul-19 31-Jul-19 Distributed Control Syste
SNBP-CO-ECRO-1130 Distributed Control System: Instrumentation & Control (Loop Wiring Checks) 14 01-Aug-19 17-Aug-19 Distributed Control Syst
Electrical Works (Main) 199 22-Jun-19 22-Feb-20
SNBP-CO-ECRO-1140 Electrical Works (Main) & Install Aircon. Unit 30 22-Jun-19 26-Jul-19 Electrical Works (Main)
SNBP-CO-ECRO-1150 Install Cable Trays for Equipment 21 27-Jul-19 22-Aug-19 Install Cable Trays for E
SNBP-CO-ECRO-1160 Power Supply Required 1 21-Feb-20 22-Feb-20 Power Supply R
#21 MV / LV Switchgear (Equipment)
(Equip 207 22-Jun-19 04-Mar-20
SNBP-CO-ECRO-1170 MV/LV Switchgear - Install Equipment Unit 14 22-Jun-19 08-Jul-19 MV/LV Switchgear - Insta
SNBP Detailed Schedule on Electrical & Control PROJECT: SOUTH NEGROS
Room Building 25MWe BIOMASS-FIRED POWER PLANT

Activity ID Activity Name Orig Dur Target Start Target Finish 2019 2020 2021
A A A A A
#14 Chimney 136 09-May-19 19-Oct-19
#11 Main Power Transformer 336 07-Feb-19 28-Mar-20
#33 LP HW Heater 168 18-Feb-19 13-Sep-19
#34 HP HW Heater 154 16-May-19 20-Nov-19
#32 Weighbridge and Measure
Measur Room 177 24-Aug-19 30-Mar-20
#30 Fire Water & SW pumps 164 21-Jun-19 10-Jan-20
#05 Baghouse 166 13-Aug-19 06-Mar-20
Fire Protection System 126 11-Jul-19 12-Dec-19
#20 Belt Conveyor (Fuel Handling
Hand to Boiler) 263 22-Mar-19 14-Feb-20
#23 Water Treatment Plant 209 07-Feb-19 22-Oct-19
Pipeline Sytem 214 25-Oct-19 18-Jul-20
#01 Steam Turbine Generators
Generator 310 13-Dec-18 07-Jan-20
#40 Waste Water Holding Pond
Pon 79 07-Mar-19 14-Jun-19
#19 Emergency Diesel Generator
Gener (w/ Diesel Tank & Pumps) 90 15-May-19 02-Sep-19
#09 Air Compressor Shed 193 04-Jul-19 29-Feb-20
#50 Distribution Board Room 99 02-May-19 30-Aug-19
#35 Gland Steam Condenser 226 04-Apr-19 13-Jan-20
#39 Bottom Ash Skip Storage 52 16-May-19 17-Jul-19
#56 Blowdown Sump 102 16-May-19 17-Sep-19
#41 Rainwater Collection Pond
Pon 66 09-May-19 26-Jul-19
Plant Lighting System 183 09-Jul-19 21-Feb-20
#15 BOP Pumps 134 05-Aug-19 21-Jan-20
#37 SW & DW Pump 95 14-Aug-19 09-Dec-19
Oil / Water Separator 186 21-May-19 08-Jan-20
Fire Detection & Alarm System
Syste 134 26-Jul-19 10-Jan-20
#51 Boiler Chemical Dosing S
System 34 16-May-19 26-Jun-19
#53 Feed Water Boiler Pump 34 16-May-19 26-Jun-19
#54 Condensate Boiler Pump 27 11-May-19 13-Jun-19
#55 Forced Draft Boiler Pump 34 16-May-19 26-Jun-19
#29 MV Cable Trench 42 06-Dec-19 29-Jan-20
Lightning Protection System 61 11-Sep-19 23-Nov-19

TESTING & COMMISSIONING


COMMISSIO 303 03-Sep-19 10-Sep-20

GENERAL PUNCHLIST & PROJECT CLOSE-OUT 66 11-Sep-20 27-Nov-20