PROJECT: 25MW BIOMASS - FIRED POWERPLANT

LOCATION: BRGY. 1 - POBLACION, LA CARLOTA CITY, NEGROS OCCIDENTAL

Status as of February 20, 2019 #21 ELECTRICAL & CONTROL ROOM BUILDING (Civil & Architectural Works)
(based on Labor Man-Hours)
12.00% 120.00%

CUMULATIVE PROGRESS %
PLAN (%)
ACTUAL (%) 10.51%
10.32%
PERIODIC PROGRESS %

10.00%
CUMULATIVE PLAN (%) 100.00%
CUMULATIVE ACTUAL (%)
8.78%

8.00% 80.00%
7.50% 7.56%

6.90% 6.92% 6.86%

6.22%
6.00% 5.89% 60.00%
5.62%
5.43%
5.26%

4.34%

4.00% 40.00%
3.57%
3.43%
2.94%
CUM. ACTUAL=27.65%
2.86%
2.56%
2.11%
1.98% 1.94%
2.00% 1.82% 1.82% 20.00%
1.67%
1.51%
1.03%

0.26%
0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.00%
0.00% 0.03%
0.00%
0.00% 0.00%
5-Dec-18 12-Dec-18 19-Dec-18 26-Dec-18 2-Jan-19 9-Jan-19 16-Jan-19 23-Jan-19 30-Jan-19 6-Feb-19 13-Feb-19 20-Feb-19 27-Feb-19 6-Mar-19 13-Mar-19 20-Mar-19 27-Mar-19 3-Apr-19 10-Apr-19 17-Apr-19 24-Apr-19 1-May-19 8-May-19 15-May-19 22-May-19 29-May-19
PLAN (%) 0.00% 0.00% 0.00% 0.00% 0.03% 0.26% 1.67% 1.98% 1.51% 2.86% 3.43% 3.57% 7.50% 5.62% 1.94% 1.82% 4.34% 6.92% 6.86% 10.51% 5.26% 10.32% 8.78% 7.56% 6.22% 1.03%
ACTUAL (%) 0.00% 0.00% 0.00% 0.00% 0.00% 2.94% 2.56% 5.43% 1.82% 2.11% 6.90% 5.89%
CUMULATIVE
0.00% 0.00% 0.00% 0.00% 0.04% 0.29% 1.96% 7.56% 8.20% 8.31% 11.74% 15.30% 22.81% 28.43% 30.37% 32.19% 36.54% 43.46% 50.32% 60.83% 66.09% 76.41% 85.18% 92.75% 98.97% 100.00%
PLAN (%)
CUMULATIVE
0.00% 0.00% 0.00% 0.00% 0.00% 2.94% 5.50% 10.93% 12.75% 14.86% 21.76% 27.65%
ACTUAL (%)

STATUS AS OF FEBRUARY 20, 2019


PROGRESS ACCOMPLISHMENT:
CUM. TARGET = 15.30%
CUM. ACTUAL = 27.65%
VARIANCE = 12.35%
REMARKS = Ahead of Schedule