Overall Units

Report
Progress Todate
No
100.00%
Piling Works - Phase 3 & 4 100.00% Original Schedule IB Catch Up Plan
96.67% 1 6.67% 6.67%
94.00%
2 16.00% 16.00%
3 22.00% 22.00%
90.00%
4 26.67% 26.67%
84.67%
5 28.00% 28.00%
6 31.33% 31.33%
80.00% 78.00%
7 36.00% 36.00%
73.33% 8 40.67% 40.67%
68.67% 9 45.33% 45.34%
70.00%
10 48.00% 48.01%
64.00%
11 50.00% 48.56%
59.33% 12 54.67%
60.00%
13 59.33%
Work Progress (%)

54.67%
14 64.00%
48.56% 15 68.67%
50.00% 48.01%
48.00%
45.34%
45.33% 16 73.33%
17 78.00%
40.67%
18 84.67%
40.00%
36.00% 19 94.00%
20 96.67%
31.33%
21 100.00%
30.00% 28.00%
26.67%

22.00%

20.00%
16.00%
Series1 Series2
10.00% 6.67%

0.00%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Duration (Week)