EPCC FOR MULTIPURPOSE TANK PROJECT TOWELL ENGINEERING SERVICES CO LLC 01-Apr-18

Client : ORPIC

Contractor: TOWELL ENGINEERING SERVICES CO LLC

Activity ID Activity Name Original Start Finish 2018 2019 2020


Duration
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
600 01-May-18 22-Dec-19 22-Dec-19, EPCC FOR MULTIPURPOSE TANK PROJECT
EPCC FOR MULTIPURPOSE TANK PROJECT
600 01-May-18 22-Dec-19 22-Dec-19, Milestones
Milestones
TES-ORP-MPT-1308 Award of Contract 0 01-May-18 Award of Contract
TES-ORP-MPT-1309 Contract Mobilzation 0 08-Jun-18 Contract Mobilzation
TES-ORP-MPT-1310 Submission of Detailed Designs & Drawings 0 29-Nov-18 Submission of Detailed Designs & Drawings
TES-ORP-MPT-1311 Completion & Acceptance of Construction Drawings 0 17-Jan-19 Completion & Acceptance of Construction Drawings
TES-ORP-MPT-1312 Placement of PO for LLI's 0 02-Dec-18 Placement of PO for LLI's
TES-ORP-MPT-1313 Placement of PO for Other Materials 0 01-Mar-19 Placement of PO for Other Materials
TES-ORP-MPT-1314 Delviery of Equipments at Site 0 20-Jun-19 Delviery of Equipments at Site
TES-ORP-MPT-1315 Completion of Civil Works 0 12-Apr-19 Completion of Civil Works
TES-ORP-MPT-1316 Completion of Mechanical & Piping Works 0 24-Nov-19 Completion of Mechanical & Piping Works

TES-ORP-MPT-1317 Completion of Electrical Works 0 16-Jun-19 Completion of Electrical Works


TES-ORP-MPT-1318 Completion of Instrumentation Works 0 07-Nov-19 Completion of Instrumentation Works
TES-ORP-MPT-1319 Subsantial completion 0 24-Nov-19 Subsantial completion
TES-ORP-MPT-1320 Completion of Commissioning 0 04-Dec-19 Completion of Commissioning
TES-ORP-MPT-1321 Final Completion of the Project 0 22-Dec-19 Final Completion of the Project
68 01-May-18 08-Jul-18 08-Jul-18, Contract Mobilization - General
Contract Mobilization - General
TES-ORP-MPT-1302 Award of Contract 1 01-May-18 01-May-18
TES-ORP-MPT-1303 Kick of Meeting 1 08-May-18 09-May-18
TES-ORP-MPT-1304 Submisson of Contract Documents 15 19-May-18 03-Jun-18
(Performance Bond, Bank Guarantee, Insurance
etc...)
TES-ORP-MPT-1305 Submission of Project Documents (Method 45 09-May-18 23-Jun-18
statements, HSE, QA/QC, Execution Plans etc...)
TES-ORP-MPT-1306 Site office Setup 30 08-Jun-18 08-Jul-18
TES-ORP-MPT-1307 Mobilzation of Resources (Manpower & Equipments) 15 24-May-18 08-Jun-18
263 09-May-18 27-Jan-19 27-Jan-19, Engineering
Engineering
Engineering - Preliminary & Misc Activities 263 09-May-18 27-Jan-19 27-Jan-19, Engineering - Preliminary & Misc Activities
TES-ORP-MPT-1322 Pre-Engineering Site Visit & Report 10 09-May-18 19-May-18
TES-ORP-MPT-1324 Need List 4 19-May-18 23-May-18
TES-ORP-MPT-1333 Receipt of Need List Docuemnts 20 23-May-18 12-Jun-18
TES-ORP-MPT-1339 Design Review 0 17-Jul-18 Design Review
TES-ORP-MPT-1343 HAZOP Review 0 17-Aug-18 HAZOP Review
TES-ORP-MPT-1344 Receipt of Major Equipment Vendor Data 0 08-Oct-18 Receipt of Major Equipment Vendor Data
TES-ORP-MPT-1345 Substantial Engineering Completion 0 08-Dec-18 Substantial Engineering Completion
TES-ORP-MPT-1346 Residual Engineering Completion 0 27-Jan-19 Residual Engineering Completion
TES-ORP-MPT-1347 Long lead Items RFQs 0 21-Jul-18 Long lead Items RFQs
TES-ORP-MPT-1463 SIL (IPF) Review 0 08-Oct-18 SIL (IPF) Review
TES-ORP-MPT-1464 FEED Verification Report 25 23-May-18 17-Jun-18
Detailed Engineering 253 19-May-18 27-Jan-19 27-Jan-19, Detailed Engineering
Process 134 05-Jun-18 17-Oct-18 17-Oct-18, Process
TES-ORP-MPT-1356 Project Design Basis 12 05-Jun-18 17-Jun-18
TES-ORP-MPT-1357 Process Simulations & Report 35 07-Jun-18 12-Jul-18
TES-ORP-MPT-1358 Process Flow Diagram & Heat Mass Balance Diagram (PFS + HMB)
12 08-Jun-18 20-Jun-18
TES-ORP-MPT-1359 P & IDs 25 10-Jun-18 05-Jul-18
TES-ORP-MPT-1365 Tie-in & Shutdown Philo sophy 15 20-Jun-18 05-Jul-18
TES-ORP-MPT-1368 Operating, Control & Safe guarding Philosophy 20 17-Jun-18 07-Jul-18
TES-ORP-MPT-1371 Equipment List 5 27-Jul-18 01-Aug-18
TES-ORP-MPT-1374 Process Datasheets - Equipments 15 29-Jun-18 14-Jul-18
TES-ORP-MPT-1381 P & IDs after DR 16 22-Jul-18 07-Aug-18
TES-ORP-MPT-1395 P & IDs After HAZOP (IFD) 15 22-Aug-18 06-Sep-18
TES-ORP-MPT-1402 Final P & IDs 9 08-Oct-18 17-Oct-18
TES-ORP-MPT-1440 Hazardous Area Classification Drawings 5 13-Jun-18 18-Jun-18
TES-ORP-MPT-1460 Line List 10 22-Aug-18 01-Sep-18
TES-ORP-MPT-1465 Process Datasheets - Instruments 10 29-Jun-18 09-Jul-18
DR, HAZOP Review 61 07-Jul-18 06-Sep-18 06-Sep-18, DR, HAZOP Review
TES-ORP-MPT-1348DR Info Pack 1 07-Jul-18 08-Jul-18
TES-ORP-MPT-1349DR Event 2 15-Jul-18 17-Jul-18
TES-ORP-MPT-1350DR Report 5 17-Jul-18 22-Jul-18
TES-ORP-MPT-1351DR Closeout Report 25 17-Jul-18 11-Aug-18
TES-ORP-MPT-1352HAZOP Info Pack 1 07-Aug-18 08-Aug-18

Primary Baseline Critical Remaining Work Page 1 of 8

Actual Work Milestone


Remaining Work Summary
EPCC FOR MULTIPURPOSE TANK PROJECT TOWELL ENGINEERING SERVICES CO LLC 01-Apr-18
Client : ORPIC

Contractor: TOWELL ENGINEERING SERVICES CO LLC

Activity ID Activity Name Original Start Finish 2018 2019 2020


Duration May
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
TES-ORP-MPT-1353HAZOP Event 2 15-Aug-18 17-Aug-18
TES-ORP-MPT-1354HAZOP Report 5 17-Aug-18 22-Aug-18
TES-ORP-MPT-1355HAZOP Closeout Report 20 17-Aug-18 06-Sep-18
Tank 93 17-Jun-18 18-Sep-18 18-Sep-18, Tank
TES-ORP-MPT-1198 Tank Design calculation 10 17-Jun-18 27-Jun-18
TES-ORP-MPT-1228 Tank GA drawing 15 27-Jun-18 12-Jul-18
TES-ORP-MPT-1229 Input for Civil foundation design 25 12-Jul-18 06-Aug-18
TES-ORP-MPT-1230 Sketch plate drawings 20 06-Aug-18 26-Aug-18
TES-ORP-MPT-1231 Final MTO 8 26-Aug-18 03-Sep-18
TES-ORP-MPT-1232 Final AFC drawings approval 15 03-Sep-18 18-Sep-18
Piping 253 19-May-18 27-Jan-19 27-Jan-19, Piping
TES-ORP-MPT-1406 Plot Plan 25 19-May-18 13-Jun-18
TES-ORP-MPT-1415 Key Plan 10 21-Jun-18 01-Jul-18
TES-ORP-MPT-1424 Piping General Arrangement Drawings (GADs) 65 01-Aug-18 05-Oct-18
TES-ORP-MPT-1425 Stress Analysis 45 07-Sep-18 22-Oct-18
TES-ORP-MPT-1426 Piping GADs Final 45 24-Oct-18 08-Dec-18
TES-ORP-MPT-1427 Piping Isometrics 75 03-Nov-18 17-Jan-19
TES-ORP-MPT-1429 Preliminary MTO 10 16-Jul-18 26-Jul-18
TES-ORP-MPT-1430 Final MTO 10 17-Jan-19 27-Jan-19
TES-ORP-MPT-1458 Intermediate MTO 15 05-Oct-18 20-Oct-18
Civil & Structural 207 19-May-18 12-Dec-18 12-Dec-18, Civil & Structural
TES-ORP-MPT-1428 SOW for Geotechnical Survey 15 19-May-18 03-Jun-18
TES-ORP-MPT-1431 Design & Drawings for Multipurpose Tank 50 19-Aug-18 08-Oct-18
TES-ORP-MPT-1432 Design & Drawings for AR Change Pumps 25 12-Sep-18 07-Oct-18
TES-ORP-MPT-1439 Design & Drawings for Structural Works 35 25-Oct-18 29-Nov-18
TES-ORP-MPT-1446 Site Grading Drawings 15 13-Jun-18 28-Jun-18
TES-ORP-MPT-1456 Roads, Fence & Storm Water Drainage Layouts 15 18-Jun-18 02-Jul-18
TES-ORP-MPT-1457 SOW for Topogr aphical Surv ey 15 03-Jun-18 18-Jun-18
TES-ORP-MPT-1459 Design & Drawings for Pipe Supports 25 17-Nov-18 12-Dec-18
TES-ORP-MPT-1468 Design & Drawings for Pipe Sleepers 30 22-Oct-18 21-Nov-18
Electrical 178 05-Jul-18 30-Dec-18 30-Dec-18, Electrical
TES-ORP-MPT-1433 Electrical Load List 15 05-Jul-18 20-Jul-18
TES-ORP-MPT-1434 SLDs 25 18-Jul-18 12-Aug-18
TES-ORP-MPT-1435 Key SLD 10 08-Jul-18 18-Jul-18
TES-ORP-MPT-1436 Sizing Calculations 25 31-Jul-18 25-Aug-18
TES-ORP-MPT-1437 Electrical Equipment Layout Preliminary 15 22-Jul-18 06-Aug-18
TES-ORP-MPT-1438 Cable Trench Layout 25 05-Oct-18 30-Oct-18
TES-ORP-MPT-1441 Earthing Layout 20 30-Oct-18 19-Nov-18
TES-ORP-MPT-1442 Lighting Layout 25 19-Nov-18 14-Dec-18
TES-ORP-MPT-1443 Cable Schedule 20 25-Aug-18 14-Sep-18
TES-ORP-MPT-1444 Electrical Bulk MTO 12 18-Dec-18 30-Dec-18
TES-ORP-MPT-1445 Lighting Protection Layout 20 28-Nov-18 18-Dec-18
TES-ORP-MPT-1461 Electrical Equipment Layout Final 15 10-Oct-18 25-Oct-18
TES-ORP-MPT-1466 Relay Setting Calculations 20 23-Nov-18 13-Dec-18
TES-ORP-MPT-1467 Inter Connection Drawings 20 25-Oct-18 14-Nov-18
Instrumentation 203 20-Jun-18 09-Jan-19 09-Jan-19, Instrumentation
TES-ORP-MPT-1372 Instrument Cable Trench Layout 25 23-Oct-18 17-Nov-18
TES-ORP-MPT-1373 Loop Drawings 20 11-Nov-18 01-Dec-18
TES-ORP-MPT-1375 Cable Schedule 20 19-Sep-18 08-Oct-18
TES-ORP-MPT-1376 Instrumnet Bulk MTO 7 02-Jan-19 09-Jan-19
TES-ORP-MPT-1447 Cause & Effect Diagram 15 20-Jun-18 05-Jul-18
TES-ORP-MPT-1448 I / O List 25 05-Jul-18 30-Jul-18
TES-ORP-MPT-1449 Instrument Index 25 02-Aug-18 27-Aug-18
TES-ORP-MPT-1450 Alarm & Trip Settings 25 22-Aug-18 16-Sep-18
TES-ORP-MPT-1451 ICTD - JB (Instrument Cable Terminat ion Drawin gs) 20 24-Nov-18 13-Dec-18
TES-ORP-MPT-1452 Instrument Location Layout 25 08-Dec-18 02-Jan-19
TES-ORP-MPT-1453 Control Room Layout - Preliminary 20 27-Aug-18 16-Sep-18
TES-ORP-MPT-1454 ICTD - System 15 14-Dec-18 28-Dec-18
TES-ORP-MPT-1455 Logic Diagrams 30 24-Oct-18 23-Nov-18
TES-ORP-MPT-1462 Control Room Layout - Final 15 09-Oct-18 24-Oct-18
SIL (IPF) Review 52 06-Sep-18 28-Oct-18 28-Oct-18, SIL (IPF) Review
TES-ORP-MPT-1377SIL (IPF) Info Pack 1 06-Sep-18 06-Sep-18

Primary Baseline Critical Remaining Work Page 2 of 8

Actual Work Milestone


Remaining Work Summary
EPCC FOR MULTIPURPOSE TANK PROJECT TOWELL ENGINEERING SERVICES CO LLC 01-Apr-18
Client : ORPIC

Contractor: TOWELL ENGINEERING SERVICES CO LLC

Activity ID Activity Name Original Start Finish 2018 2019 2020


Duration May
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
TES-ORP-MPT-1378SIL (IPF) Event 3 16-Sep-18 18-Sep-18
TES-ORP-MPT-1379SIL (IPF) Report 10 18-Sep-18 28-Sep-18
TES-ORP-MPT-1380SIL (IPF) Closeout Report 20 08-Oct-18 28-Oct-18
Procurement Support 120 29-Jun-18 27-Oct-18 27-Oct-18, Procurement Support
Mechanical 101 29-Jun-18 08-Oct-18 08-Oct-18, Mechanical
Multipurpose Tank 101 29-Jun-18 08-Oct-18 08-Oct-18, Multipurpose Tank
TES-ORP-MPT-1382MR for Multipurose tank 14 29-Jun-18 13-Jul-18
TES-ORP-MPT-1384Technical Queries 9 22-Jul-18 31-Jul-18
TES-ORP-MPT-1385Technical Bid Evaluation 4 10-Aug-18 14-Aug-18
TES-ORP-MPT-1386Vendor Data Review 14 24-Sep-18 08-Oct-18
AR Change Pumps 85 03-Jul-18 26-Sep-18 26-Sep-18, AR Change Pumps
TES-ORP-MPT-1388MR for AR Change Pumps 14 03-Jul-18 17-Jul-18
TES-ORP-MPT-1389Technical Queries 9 26-Jul-18 04-Aug-18
TES-ORP-MPT-1390Technical Bid Evaluation 4 14-Aug-18 18-Aug-18
TES-ORP-MPT-1391Vendor Data Review 14 12-Sep-18 26-Sep-18
Side Entry Mixers 87 08-Jul-18 02-Oct-18 02-Oct-18, Side Entry Mixers
TES-ORP-MPT-1360MR for Side Entry Mixers 14 08-Jul-18 21-Jul-18
TES-ORP-MPT-1472Technical Queries 9 01-Aug-18 10-Aug-18
TES-ORP-MPT-1473Technical Bid Evaluation 4 20-Aug-18 24-Aug-18
TES-ORP-MPT-1474Vendor Data Review 14 19-Sep-18 02-Oct-18
AR Circulation Heater 80 07-Jul-18 25-Sep-18 25-Sep-18, AR Circulation Heater
TES-ORP-MPT-1392MR for AR Circulation Heater 14 07-Jul-18 21-Jul-18
TES-ORP-MPT-1394Technical Queries 9 25-Jul-18 03-Aug-18
TES-ORP-MPT-1396Technical Bid Evaluation 4 13-Aug-18 18-Aug-18
TES-ORP-MPT-1397Vendor Data Review 14 12-Sep-18 25-Sep-18
Material Handling Equipment (Mono-rail) 74 13-Jul-18 25-Sep-18 25-Sep-18, Material Handling Equipment (Mono-rail)
TES-ORP-MPT-1361MR for Material Handling Equipments 14 13-Jul-18 26-Jul-18
TES-ORP-MPT-1469Technical Queries 9 31-Jul-18 09-Aug-18
TES-ORP-MPT-1470Technical Bid Evaluation 5 19-Aug-18 24-Aug-18
TES-ORP-MPT-1471Vendor Data Review 14 11-Sep-18 25-Sep-18
Instrumentation 120 29-Jun-18 27-Oct-18 27-Oct-18, Instrumentation
Control Valves 79 29-Jun-18 16-Sep-18 16-Sep-18, Control Valves
TES-ORP-MPT-1325Technical Queries 11 14-Jul-18 24-Jul-18
TES-ORP-MPT-1326Technical Bid Evaluation 5 04-Aug-18 08-Aug-18
TES-ORP-MPT-1327Vendor Data Review 14 03-Sep-18 16-Sep-18
TES-ORP-MPT-1367MR for Control Valve 10 29-Jun-18 09-Jul-18
MOV 70 04-Jul-18 12-Sep-18 12-Sep-18, MOV
TES-ORP-MPT-1328Technical Queries 6 18-Jul-18 24-Jul-18
TES-ORP-MPT-1329Technical Bid Evaluation 5 04-Aug-18 08-Aug-18
TES-ORP-MPT-1334Vendor Data Review 9 03-Sep-18 12-Sep-18
TES-ORP-MPT-1403MR for MOV 10 04-Jul-18 13-Jul-18
Level Instruments 54 09-Jul-18 01-Sep-18 01-Sep-18, Level Instruments
TES-ORP-MPT-1340Technical Queries 5 22-Jul-18 27-Jul-18
TES-ORP-MPT-1341Technical Bid Evaluation 3 10-Aug-18 13-Aug-18
TES-ORP-MPT-1342Vendor Data Review 9 23-Aug-18 01-Sep-18
TES-ORP-MPT-1370MR for Level Instruments 7 09-Jul-18 16-Jul-18
Pressure Instruments 56 16-Jul-18 10-Sep-18 10-Sep-18, Pressure Instruments
TES-ORP-MPT-1407MR for Pressure Instruments 7 16-Jul-18 23-Jul-18
TES-ORP-MPT-1408Technical Queries 5 29-Jul-18 03-Aug-18
TES-ORP-MPT-1409Technical Bid Evaluation 4 17-Aug-18 21-Aug-18
TES-ORP-MPT-1410Vendor Data Review 10 31-Aug-18 10-Sep-18
Flow Instruments 55 23-Jul-18 16-Sep-18 16-Sep-18, Flow Instruments
TES-ORP-MPT-1412MR for Flow Instruments 7 23-Jul-18 30-Jul-18
TES-ORP-MPT-1413Technical Queries 5 05-Aug-18 10-Aug-18
TES-ORP-MPT-1414Technical Bid Evaluation 3 24-Aug-18 27-Aug-18
TES-ORP-MPT-1416Vendor Data Review 10 06-Sep-18 16-Sep-18
Temperature Instruments 51 30-Jul-18 19-Sep-18 19-Sep-18, Temperature Instruments
TES-ORP-MPT-1418MR for Temperature Instruments 7 30-Jul-18 06-Aug-18
TES-ORP-MPT-1421Technical Queries 3 12-Aug-18 16-Aug-18
TES-ORP-MPT-1422Technical Bid Evaluation 3 30-Aug-18 02-Sep-18
TES-ORP-MPT-1423Vendor Data Review 7 12-Sep-18 19-Sep-18
MOV System 55 17-Aug-18 11-Oct-18 11-Oct-18, MOV System
TES-ORP-MPT-1335Vendor Data Review 10 01-Oct-18 11-Oct-18

Primary Baseline Critical Remaining Work Page 3 of 8

Actual Work Milestone


Remaining Work Summary
EPCC FOR MULTIPURPOSE TANK PROJECT TOWELL ENGINEERING SERVICES CO LLC 01-Apr-18
Client : ORPIC

Contractor: TOWELL ENGINEERING SERVICES CO LLC

Activity ID Activity Name Original Start Finish 2018 2019 2020


Duration May
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
TES-ORP-MPT-1366SOW for MOV System 13 17-Aug-18 30-Aug-18
F & G System 71 17-Aug-18 27-Oct-18 27-Oct-18, F & G System
TES-ORP-MPT-1336Technical Queries 9 05-Sep-18 14-Sep-18
TES-ORP-MPT-1337Technical Bid Evaluation 5 24-Sep-18 28-Sep-18
TES-ORP-MPT-1338Vendor Data Review 14 14-Oct-18 27-Oct-18
TES-ORP-MPT-1369MR for F&G system 10 17-Aug-18 27-Aug-18
DCS / FGS 55 30-Aug-18 24-Oct-18 24-Oct-18, DCS / FGS
TES-ORP-MPT-1400SOW for DCS / FGS 13 30-Aug-18 12-Sep-18
TES-ORP-MPT-1401Vendor Data Review 10 14-Oct-18 24-Oct-18
TGS 49 31-Aug-18 18-Oct-18 18-Oct-18, TGS
TES-ORP-MPT-1404SOW for TGS 10 31-Aug-18 10-Sep-18
TES-ORP-MPT-1405Vendor Data Review 14 05-Oct-18 18-Oct-18
Electrical 99 18-Jul-18 25-Oct-18 25-Oct-18, Electrical
LV Switchgear 74 18-Jul-18 30-Sep-18 30-Sep-18, LV Switchgear
TES-ORP-MPT-1362MR for LV Switchgear 15 18-Jul-18 02-Aug-18
TES-ORP-MPT-1398Technical Queries 6 08-Aug-18 14-Aug-18
TES-ORP-MPT-1399Technical Bid Evaluation 5 29-Aug-18 02-Sep-18
TES-ORP-MPT-1475Vendor Data Review 14 16-Sep-18 30-Sep-18
MV Switchgear 76 31-Jul-18 15-Oct-18 15-Oct-18, MV Switchgear
TES-ORP-MPT-1363MR for MV Switchgear 12 31-Jul-18 12-Aug-18
TES-ORP-MPT-1480Technical Queries 4 19-Aug-18 23-Aug-18
TES-ORP-MPT-1481Technical Bid Evaluation 5 06-Sep-18 11-Sep-18
TES-ORP-MPT-1482Vendor Data Review 14 01-Oct-18 15-Oct-18
MOV DB 80 05-Aug-18 25-Oct-18 25-Oct-18, MOV DB
TES-ORP-MPT-1364MR for MOV DB 12 05-Aug-18 17-Aug-18
TES-ORP-MPT-1476Technical Queries 9 24-Aug-18 02-Sep-18
TES-ORP-MPT-1477Technical Bid Evaluation 5 16-Sep-18 21-Sep-18
TES-ORP-MPT-1478Vendor Data Review 14 11-Oct-18 25-Oct-18
415 01-May-18 20-Jun-19 20-Jun-19, Procurement
Procurement
LLI's 415 01-May-18 20-Jun-19 20-Jun-19, LLI's
Aluminium Dome 239 13-Jul-18 08-Mar-19 08-Mar-19, Aluminium Dome
TES-ORP-MPT-1050 Enquiry Floating 5 13-Jul-18 18-Jul-18
TES-ORP-MPT-1051 Receipt of Offers & Evaluation 14 31-Jul-18 14-Aug-18
TES-ORP-MPT-1052 MAS Approval 14 14-Aug-18 28-Aug-18
TES-ORP-MPT-1053 Order Placement 10 30-Aug-18 09-Sep-18
TES-ORP-MPT-1072 Manufacturing / Fabrication 145 09-Sep-18 01-Feb-19
TES-ORP-MPT-1073 FAT 5 01-Feb-19 06-Feb-19
TES-ORP-MPT-1074 Delivery 30 06-Feb-19 08-Mar-19
AR Charge Pumps 214 17-Jul-18 15-Feb-19 15-Feb-19, AR Charge Pumps
TES-ORP-MPT-1075 Enquiry Floating 5 17-Jul-18 22-Jul-18
TES-ORP-MPT-1076 Receipt of Offers & Evaluation 14 04-Aug-18 18-Aug-18
TES-ORP-MPT-1077 MAS Approval 14 18-Aug-18 01-Sep-18
TES-ORP-MPT-1078 Order Placement 10 03-Sep-18 13-Sep-18
TES-ORP-MPT-1079 Manufacturing 120 13-Sep-18 11-Jan-19
TES-ORP-MPT-1080 FAT 5 11-Jan-19 16-Jan-19
TES-ORP-MPT-1081 Delivery 30 16-Jan-19 15-Feb-19
AR Circulation Heater 334 21-Jul-18 20-Jun-19 20-Jun-19, AR Circulation Heater
TES-ORP-MPT-1082 Enquiry Floating 5 21-Jul-18 26-Jul-18
TES-ORP-MPT-1083 Receipt of Offers & Evaluation 14 03-Aug-18 17-Aug-18
TES-ORP-MPT-1084 MAS Approval 14 18-Aug-18 01-Sep-18
TES-ORP-MPT-1085 Order Placement 10 03-Sep-18 13-Sep-18
TES-ORP-MPT-1086 Manufacturing 240 13-Sep-18 11-May-19
TES-ORP-MPT-1087 FAT 10 11-May-19 21-May-19
TES-ORP-MPT-1088 Delivery 30 21-May-19 20-Jun-19
Roof drain 228 01-May-18 14-Dec-18 14-Dec-18, Roof drain
TES-ORP-MPT-1096 Enquiry Floating 5 01-May-18 05-May-18
TES-ORP-MPT-1097 Receipt of Offers & Evaluation 14 06-May-18 19-May-18
TES-ORP-MPT-1098 MAS Approval 14 20-May-18 02-Jun-18
TES-ORP-MPT-1099 Order Placement 10 03-Jun-18 12-Jun-18
TES-ORP-MPT-1100 Manufacturing / Fabrication 150 13-Jun-18 09-Nov-18
TES-ORP-MPT-1101 FAT 5 10-Nov-18 14-Nov-18
TES-ORP-MPT-1102 Delivery 30 15-Nov-18 14-Dec-18

Primary Baseline Critical Remaining Work Page 4 of 8

Actual Work Milestone


Remaining Work Summary
EPCC FOR MULTIPURPOSE TANK PROJECT TOWELL ENGINEERING SERVICES CO LLC 01-Apr-18
Client : ORPIC

Contractor: TOWELL ENGINEERING SERVICES CO LLC

Activity ID Activity Name Original Start Finish 2018 2019 2020


Duration May
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Breather Valves 228 06-May-18 19-Dec-18 19-Dec-18, Breather Valves
TES-ORP-MPT-1103 Enquiry Floating 5 06-May-18 10-May-18
TES-ORP-MPT-1104 Receipt of Offers & Evaluation 14 11-May-18 24-May-18
TES-ORP-MPT-1105 MAS Approval 14 25-May-18 07-Jun-18
TES-ORP-MPT-1106 Order Placement 10 08-Jun-18 17-Jun-18
TES-ORP-MPT-1107 Manufacturing / Fabrication 150 18-Jun-18 14-Nov-18
TES-ORP-MPT-1108 FAT 5 15-Nov-18 19-Nov-18
TES-ORP-MPT-1109 Delivery 30 20-Nov-18 19-Dec-18
Manual Valves 168 20-Oct-18 06-Apr-19 06-Apr-19, Manual Valves
TES-ORP-MPT-1110 Enquiry Floating 5 20-Oct-18 25-Oct-18
TES-ORP-MPT-1111 Receipt of Offers & Evaluation 14 25-Oct-18 08-Nov-18
TES-ORP-MPT-1112 MAS Approval 14 08-Nov-18 22-Nov-18
TES-ORP-MPT-1113 Order Placement 10 22-Nov-18 02-Dec-18
TES-ORP-MPT-1114 Manufacturing / Fabrication 90 02-Dec-18 02-Mar-19
TES-ORP-MPT-1115 FAT 5 02-Mar-19 07-Mar-19
TES-ORP-MPT-1116 Delivery 30 07-Mar-19 06-Apr-19
MOV's 290 24-Jul-18 11-May-19 11-May-19, MOV's
TES-ORP-MPT-1117 Enquiry Floating 5 24-Jul-18 29-Jul-18
TES-ORP-MPT-1118 Receipt of Offers & Evaluation 14 08-Aug-18 22-Aug-18
TES-ORP-MPT-1119 MAS Approval 14 12-Sep-18 26-Sep-18
TES-ORP-MPT-1120 Order Placement 10 28-Sep-18 08-Oct-18
TES-ORP-MPT-1121 Manufacturing / Fabrication 180 08-Oct-18 06-Apr-19
TES-ORP-MPT-1122 FAT 5 06-Apr-19 11-Apr-19
TES-ORP-MPT-1123 Delivery 30 11-Apr-19 11-May-19
Control valves 235 24-Jul-18 16-Mar-19 16-Mar-19, Control valves
TES-ORP-MPT-1124 Enquiry Floating 5 24-Jul-18 29-Jul-18
TES-ORP-MPT-1125 Receipt of Offers & Evaluation 14 08-Aug-18 22-Aug-18
TES-ORP-MPT-1126 MAS Approval 14 16-Sep-18 30-Sep-18
TES-ORP-MPT-1127 Order Placement 10 02-Oct-18 12-Oct-18
TES-ORP-MPT-1128 Manufacturing / Fabrication 120 12-Oct-18 09-Feb-19
TES-ORP-MPT-1129 FAT 5 09-Feb-19 14-Feb-19
TES-ORP-MPT-1130 Delivery 30 14-Feb-19 16-Mar-19
Tank Guaging system 217 27-Jul-18 01-Mar-19 01-Mar-19, Tank Guagin g system
TES-ORP-MPT-1131 Enquiry Floating 5 27-Jul-18 01-Aug-18
TES-ORP-MPT-1132 Receipt of Offers & Evaluation 14 13-Aug-18 27-Aug-18
TES-ORP-MPT-1133 MAS Approval 14 01-Sep-18 15-Sep-18
TES-ORP-MPT-1134 Order Placement 10 17-Sep-18 27-Sep-18
TES-ORP-MPT-1135 Manufacturing / Fabrication 120 27-Sep-18 25-Jan-19
TES-ORP-MPT-1136 FAT 5 25-Jan-19 30-Jan-19
TES-ORP-MPT-1137 Delivery 30 30-Jan-19 01-Mar-19
MV & LV Switch Gears 211 12-Aug-18 11-Mar-19 11-Mar-19, MV & LV Switch Gears
TES-ORP-MPT-1138 Enquiry Floating 5 12-Aug-18 17-Aug-18
TES-ORP-MPT-1139 Receipt of Offers & Evaluation 14 23-Aug-18 06-Sep-18
TES-ORP-MPT-1140 MAS Approval 14 11-Sep-18 25-Sep-18
TES-ORP-MPT-1141 Order Placement 10 27-Sep-18 07-Oct-18
TES-ORP-MPT-1142 Manufacturing / Fabrication 120 07-Oct-18 04-Feb-19
TES-ORP-MPT-1143 FAT 5 04-Feb-19 09-Feb-19
TES-ORP-MPT-1144 Delivery 30 09-Feb-19 11-Mar-19
Bulk & Other Procurements 322 12-Jul-18 30-May-19 30-May-19, Bulk & Other Procurements
Tank Plates 113 12-Jul-18 02-Nov-18 02-Nov-18, Tank Plates
TES-ORP-MPT-1145 Enquiry Floating 5 12-Jul-18 17-Jul-18
TES-ORP-MPT-1146 Receipt of Offers & Evaluation 14 17-Jul-18 31-Jul-18
TES-ORP-MPT-1147 MAS Approval 14 31-Jul-18 14-Aug-18
TES-ORP-MPT-1148 Order Placement 20 14-Aug-18 03-Sep-18
TES-ORP-MPT-1149 Delivery 60 03-Sep-18 02-Nov-18
Tank Appurtenances 118 17-Jul-18 12-Nov-18 12-Nov-18, Tank Appurtenances
TES-ORP-MPT-1150 Enquiry Floating 5 17-Jul-18 22-Jul-18
TES-ORP-MPT-1151 Receipt of Offers & Evaluation 14 22-Jul-18 05-Aug-18
TES-ORP-MPT-1152 MAS Approval 14 05-Aug-18 19-Aug-18
TES-ORP-MPT-1153 Order Placement 10 19-Aug-18 29-Aug-18
TES-ORP-MPT-1154 Delivery 75 29-Aug-18 12-Nov-18
Structural Materials 88 17-Jul-18 13-Oct-18 13-Oct-18, Structural Materials

Primary Baseline Critical Remaining Work Page 5 of 8

Actual Work Milestone


Remaining Work Summary
EPCC FOR MULTIPURPOSE TANK PROJECT TOWELL ENGINEERING SERVICES CO LLC 01-Apr-18
Client : ORPIC

Contractor: TOWELL ENGINEERING SERVICES CO LLC

Activity ID Activity Name Original Start Finish 2018 2019 2020


Duration May
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
TES-ORP-MPT-1155 Enquiry Floating 5 17-Jul-18 22-Jul-18
TES-ORP-MPT-1156 Receipt of Offers & Evaluation 14 22-Jul-18 05-Aug-18
TES-ORP-MPT-1157 MAS Approval 14 05-Aug-18 19-Aug-18
TES-ORP-MPT-1158 Order Placement 10 19-Aug-18 29-Aug-18
TES-ORP-MPT-1159 Delivery 45 29-Aug-18 13-Oct-18
Pipes & Fittings 134 05-Oct-18 16-Feb-19 16-Feb-19, Pipes & Fittings
TES-ORP-MPT-1160 Enquiry Floating 5 05-Oct-18 10-Oct-18
TES-ORP-MPT-1161 Receipt of Offers & Evaluation 14 10-Oct-18 24-Oct-18
TES-ORP-MPT-1162 MAS Approval 25 24-Oct-18 18-Nov-18
TES-ORP-MPT-1163 Order Placement 30 18-Nov-18 18-Dec-18
TES-ORP-MPT-1164 Delivery 60 18-Dec-18 16-Feb-19
Field Instruments 141 06-Aug-18 25-Dec-18 25-Dec-18, Field Instruments
TES-ORP-MPT-1165 Enquiry Floating 5 06-Aug-18 11-Aug-18
TES-ORP-MPT-1166 Receipt of Offers & Evaluation 14 16-Aug-18 30-Aug-18
TES-ORP-MPT-1167 MAS Approval 14 02-Sep-18 16-Sep-18
TES-ORP-MPT-1168 Order Placement 10 16-Sep-18 26-Sep-18
TES-ORP-MPT-1169 Delivery 90 26-Sep-18 25-Dec-18
Electrical Cables 88 04-Oct-18 31-Dec-18 31-Dec-18, Electrical Cables
TES-ORP-MPT-1170 Enquiry Floating 5 04-Oct-18 09-Oct-18
TES-ORP-MPT-1171 Receipt of Offers & Evaluation 14 09-Oct-18 23-Oct-18
TES-ORP-MPT-1172 MAS Approval 14 23-Oct-18 06-Nov-18
TES-ORP-MPT-1173 Order Placement 10 06-Nov-18 16-Nov-18
TES-ORP-MPT-1174 Delivery 45 16-Nov-18 31-Dec-18
Instrumentation cables 88 29-Oct-18 24-Jan-19 24-Jan-19, Instrumentation cables
TES-ORP-MPT-1492 Enquiry Floating 5 29-Oct-18 02-Nov-18
TES-ORP-MPT-1502 Receipt of Offers & Evaluation 14 03-Nov-18 16-Nov-18
TES-ORP-MPT-1512 MAS Approval 14 17-Nov-18 30-Nov-18
TES-ORP-MPT-1522 Order Placement 10 01-Dec-18 10-Dec-18
TES-ORP-MPT-1532 Delivery 45 11-Dec-18 24-Jan-19
LCS, Distribution boards 103 14-Dec-18 27-Mar-19 27-Mar-19, LCS, Distribution boards
TES-ORP-MPT-1180 Enquiry Floating 5 14-Dec-18 19-Dec-18
TES-ORP-MPT-1181 Receipt of Offers & Evaluation 14 19-Dec-18 02-Jan-19
TES-ORP-MPT-1182 MAS Approval 14 02-Jan-19 16-Jan-19
TES-ORP-MPT-1183 Order Placement 10 16-Jan-19 26-Jan-19
TES-ORP-MPT-1184 Delivery 60 26-Jan-19 27-Mar-19
Lighting fixtures 103 19-Dec-18 01-Apr-19 01-Apr-19, Lighting fixtures
TES-ORP-MPT-1185 Enquiry Floating 5 19-Dec-18 24-Dec-18

TES-ORP-MPT-1186 Receipt of Offers & Evaluation 14 24-Dec-18 07-Jan-19


TES-ORP-MPT-1187 MAS Approval 14 07-Jan-19 21-Jan-19
TES-ORP-MPT-1188 Order Placement 10 21-Jan-19 31-Jan-19
TES-ORP-MPT-1189 Delivery 60 31-Jan-19 01-Apr-19
Other Piping Bulk Materials 123 27-Jan-19 30-May-19 30-May-19, Other Piping Bulk Materials
TES-ORP-MPT-1190 Enquiry Floating 5 27-Jan-19 01-Feb-19
TES-ORP-MPT-1191 Receipt of Offers & Evaluation 14 01-Feb-19 15-Feb-19
TES-ORP-MPT-1192 Order Placement 14 15-Feb-19 01-Mar-19
TES-ORP-MPT-1193 Delivery 90 01-Mar-19 30-May-19
Other E&I Bulk Materials 123 09-Jan-19 12-May-19 12-May-19, Other E&I Bulk Materials
TES-ORP-MPT-1194 Enquiry Floating 5 09-Jan-19 14-Jan-19
TES-ORP-MPT-1195 Receipt of Offers & Evaluation 14 14-Jan-19 28-Jan-19
TES-ORP-MPT-1196 Order Placement 14 28-Jan-19 11-Feb-19
TES-ORP-MPT-1197 Delivery 90 11-Feb-19 12-May-19
534 08-Jun-18 24-Nov-19 24-Nov-19, Construction Works
Construction Works
Civil Works 308 08-Jun-18 12-Apr-19 12-Apr-19, Civil Works
Tank Foundations 115 08-Jun-18 01-Oct-18 01-Oct-18, Tank Foundations
TES-ORP-MPT-1250 Excavation 25 08-Jun-18 03-Jul-18
TES-ORP-MPT-1252 Soil Improvement 30 03-Jul-18 02-Aug-18
TES-ORP-MPT-1254 Backfilling 15 02-Aug-18 17-Aug-18
TES-ORP-MPT-1256 Construction of crushed stone ring 20 17-Aug-18 06-Sep-18
TES-ORP-MPT-1257 Sand filling & Compaction 15 06-Sep-18 21-Sep-18
TES-ORP-MPT-1258 Bitumen pad 10 21-Sep-18 01-Oct-18
AR Circulation Heater Foundations 37 01-Oct-18 07-Nov-18 07-Nov-18, AR Circulation Heater Foundations
TES-ORP-MPT-1233 Excavation 10 01-Oct-18 11-Oct-18

Primary Baseline Critical Remaining Work Page 6 of 8

Actual Work Milestone


Remaining Work Summary
EPCC FOR MULTIPURPOSE TANK PROJECT TOWELL ENGINEERING SERVICES CO LLC 01-Apr-18
Client : ORPIC

Contractor: TOWELL ENGINEERING SERVICES CO LLC

Activity ID Activity Name Original Start Finish 2018 2019 2020


Duration May
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
TES-ORP-MPT-1234 Compaction 3 11-Oct-18 14-Oct-18
TES-ORP-MPT-1235 PCC & Protection coating for PCC top 3 14-Oct-18 17-Oct-18
TES-ORP-MPT-1236 Reinforcement works 5 17-Oct-18 22-Oct-18
TES-ORP-MPT-1237 Shuttering works 5 22-Oct-18 27-Oct-18
TES-ORP-MPT-1238 Concrete 7 27-Oct-18 03-Nov-18
TES-ORP-MPT-1239 Concrete Protection Painting 2 03-Nov-18 05-Nov-18
TES-ORP-MPT-1241 Backfilling 2 05-Nov-18 07-Nov-18
Pumps Foundations 37 11-Oct-18 17-Nov-18 17-Nov-18, Pumps Foundations
TES-ORP-MPT-1242 Excavation 10 11-Oct-18 21-Oct-18
TES-ORP-MPT-1243 Compaction 3 21-Oct-18 24-Oct-18
TES-ORP-MPT-1244 PCC & Protection coating for PCC top 3 24-Oct-18 27-Oct-18
TES-ORP-MPT-1245 Reinforcement works 5 27-Oct-18 01-Nov-18
TES-ORP-MPT-1246 Shuttering works 5 01-Nov-18 06-Nov-18
TES-ORP-MPT-1247 Concrete 7 06-Nov-18 13-Nov-18
TES-ORP-MPT-1248 Concrete Protection Painting 2 13-Nov-18 15-Nov-18
TES-ORP-MPT-1249 Backfilling 2 15-Nov-18 17-Nov-18
Road works 26 17-Dec-18 12-Jan-19 12-Jan-19, Road works
TES-ORP-MPT-1259 Site Preparation works 5 17-Dec-18 22-Dec-18
TES-ORP-MPT-1260 Spraying of Water and Compaction 5 18-Dec-18 23-Dec-18
TES-ORP-MPT-1261 Sub grade Materials 12 23-Dec-18 04-Jan-19
TES-ORP-MPT-1262 Sub Base Works 12 25-Dec-18 06-Jan-19
TES-ORP-MPT-1263 Final Base works 12 27-Dec-18 08-Jan-19
TES-ORP-MPT-1264 Asphalt Works 12 29-Dec-18 10-Jan-19
TES-ORP-MPT-1265 Bitument Painting 12 31-Dec-18 12-Jan-19
Under ground facilties 156 07-Nov-18 12-Apr-19 12-Apr-19, Under ground facilties
TES-ORP-MPT-1267 Electrical Trench Works 35 22-Jan-19 26-Feb-19
TES-ORP-MPT-1268 Control cable Trench Works 45 26-Feb-19 12-Apr-19
TES-ORP-MPT-1269 Drains Pits 30 24-Nov-18 24-Dec-18
TES-ORP-MPT-1271 Culverts 50 07-Nov-18 27-Dec-18
Tank Construction Works 418 02-Oct-18 24-Nov-19 24-Nov-19, Tank Construc tion Works
TES-ORP-MPT-1272 Marking & Cutting of Plates 10 02-Oct-18 12-Oct-18
TES-ORP-MPT-1273 Rolling of Shell Plates 60 07-Oct-18 06-Dec-18
TES-ORP-MPT-1276 Placement of Bottom & Annular Plates 6 12-Oct-18 18-Oct-18
TES-ORP-MPT-1277 Fitup of Bottom & Annular Plates 20 14-Oct-18 03-Nov-18
TES-ORP-MPT-1278 Lap Welding of Bottom & Annular Plates 35 03-Nov-18 08-Dec-18
TES-ORP-MPT-1279 Vaccum Box Test 5 08-Dec-18 13-Dec-18
TES-ORP-MPT-1280 NDT Works (MPI / UT) 5 13-Dec-18 18-Dec-18
TES-ORP-MPT-1282 Degree Marking for Shell Plate Erection 1 08-Dec-18 09-Dec-18

TES-ORP-MPT-1283 Fitup, Welding & Erection of Shell Plates, Wind Girder, Kerb Angle
160 09-Dec-18 18-May-19
TES-ORP-MPT-1285 NDT Works 120 14-Dec-18 13-Apr-19
TES-ORP-MPT-1285.1 Spiral Stair way works 25 18-May-19 12-Jun-19
TES-ORP-MPT-1288 Assembly of Aluminium Dome 25 18-May-19 12-Jun-19
TES-ORP-MPT-1289 Erection, Fixing of Aluminium Dome 4 12-Jun-19 16-Jun-19
TES-ORP-MPT-1290 Nozzle & Appurtanances Installation & PWHT 30 23-Apr-19 23-May-19
TES-ORP-MPT-1293 Construction of Double Deck Floating Roof 45 16-Jun-19 31-Jul-19
TES-ORP-MPT-1294 Vaccum Box Test & NDT Works 5 31-Jul-19 05-Aug-19
TES-ORP-MPT-1295 Fixing of Primary & Secondary Seal 10 05-Aug-19 15-Aug-19
TES-ORP-MPT-1296 Assemble and Erection of Roof Drain 5 05-Aug-19 10-Aug-19
TES-ORP-MPT-1297 Floating Suction Erection works 5 10-Aug-19 15-Aug-19
TES-ORP-MPT-1298 Hydrotesting 14 15-Aug-19 29-Aug-19
TES-ORP-MPT-1299 Painting works 60 29-Aug-19 28-Oct-19
TES-ORP-MPT-1300 Calibration of Tanks 2 28-Oct-19 30-Oct-19
TES-ORP-MPT-1301 Tank Insulation works 25 30-Oct-19 24-Nov-19

Fire Fighting works 85 12-Jun-19 05-Sep-19 05-Sep-19, Fire Fighting works


TES-ORP-MPT-1000 Medium Velocity Water Spray system for tank 45 12-Jun-19 27-Jul-19
TES-ORP-MPT-1001 Fire Water sys tem - (Installation of Pumps, Deluge Valves & Water
30 17-Jun-19
Tank ) 17-Jul-19
TES-ORP-MPT-1003 Foam system installations 40 27-Jul-19 05-Sep-19
TES-ORP-MPT-1005 Rim seal Fire Protection system 25 31-Jul-19 25-Aug-19
Piping Works 255 16-Feb-19 29-Oct-19 29-Oct-19, Piping Works
TES-ORP-MPT-1006 Pipe Spool Fabrications 120 16-Feb-19 16-Jun-19
TES-ORP-MPT-1008 NDT 120 08-Mar-19 06-Jul-19

Primary Baseline Critical Remaining Work Page 7 of 8

Actual Work Milestone


Remaining Work Summary
EPCC FOR MULTIPURPOSE TANK PROJECT TOWELL ENGINEERING SERVICES CO LLC 01-Apr-18
Client : ORPIC

Contractor: TOWELL ENGINEERING SERVICES CO LLC

Activity ID Activity Name Original Start Finish 2018 2019 2020


Duration May
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
TES-ORP-MPT-1009 Pipe spool painting works 75 02-May-19 16-Jul-19
TES-ORP-MPT-1010 Demolition & Rerouting Works 20 02-May-19 22-May-19
TES-ORP-MPT-1016 Erection of Piping Spools 100 22-May-19 30-Aug-19
TES-ORP-MPT-1017 Pipe Support Erections 100 01-Jun-19 09-Sep-19
TES-ORP-MPT-1018 Manual Valve / Spectacle Blind Installations 30 20-Aug-19 19-Sep-19
TES-ORP-MPT-1019 Hydrotesting of the Pipings 30 30-Aug-19 29-Sep-19
TES-ORP-MPT-1020 Tie In connectio ns 30 30-Aug-19 29-Sep-19
TES-ORP-MPT-1041 Steam Tracing works 30 29-Sep-19 29-Oct-19
Mechanical Works 145 15-Jun-19 07-Nov-19 07-Nov-19, Mechanical Works
TES-ORP-MPT-1021 Installation of Tank Mixers 10 28-Oct-19 07-Nov-19
TES-ORP-MPT-1022 Installation of AR Charge Pumps 10 15-Jun-19 25-Jun-19
TES-ORP-MPT-1023 Installation of Circulation Heaters 10 20-Jun-19 30-Jun-19

TES-ORP-MPT-1024 Instalation of Valves (MOV, CV etc...) 25 09-Sep-19 04-Oct-19


Electrical Works 125 11-Feb-19 16-Jun-19 16-Jun-19, Electrical Works
TES-ORP-MPT-1025 Cable Laying - Electrical 60 11-Feb-19 12-Apr-19
TES-ORP-MPT-1026 Lighting Installations 45 08-Mar-19 22-Apr-19
TES-ORP-MPT-1027 Earthing Works 30 28-Mar-19 27-Apr-19

TES-ORP-MPT-1028 DB Installation 25 12-Apr-19 07-May-19


TES-ORP-MPT-1029 Cable & Termination 20 07-May-19 27-May-19
TES-ORP-MPT-1030 MV & LV Switch Gear Installation 15 07-May-19 22-May-19
TES-ORP-MPT-1031 Relay settings 15 22-May-19 06-Jun-19
TES-ORP-MPT-1032 Testing of Equipments 25 22-May-19 16-Jun-19
Instrumentation Works 234 18-Mar-19 07-Nov-19 07-Nov-19, Instrumentation Works
TES-ORP-MPT-1033 Cable Laying 75 18-Mar-19 01-Jun-19
TES-ORP-MPT-1034 Installation of JB 35 01-Jun-19 06-Jul-19
TES-ORP-MPT-1035 F&G Detector Installation 30 06-Jul-19 05-Aug-19
TES-ORP-MPT-1036 Installation of Leak detection system 15 06-Jul-19 21-Jul-19

TES-ORP-MPT-1037 Installation of Tank Guaging Instr ument s 15 18-Sep-19 03-Oct-19


TES-ORP-MPT-1038 Glanding & terminations 20 06-Jul-19 26-Jul-19
TES-ORP-MPT-1039 DCS Modifications 20 03-Oct-19 23-Oct-19
TES-ORP-MPT-1040 Loop Checking 15 23-Oct-19 07-Nov-19
36 29-Oct-19 04-Dec-19 04-Dec-19, Pre-Commisioning & Commisioning Works
Pre-Commisioning & Commisioning Works
TES-ORP-MPT-1042 Mechanical and E&IPunch list clearances 15 09-Nov-19 24-Nov-19
TES-ORP-MPT-1043 Commisioning of Tank 10 24-Nov-19 04-Dec-19
TES-ORP-MPT-1044 Commisioning Electrical Equipments 15 12-Nov-19 27-Nov-19
TES-ORP-MPT-1045 Commisoning of Pumps & Pipings 20 29-Oct-19 18-Nov-19
TES-ORP-MPT-1046 Commisioning of Other systems 15 07-Nov-19 22-Nov-19
38 14-Nov-19 22-Dec-19 22-Dec-19, Final Completion
Final Completion
TES-ORP-MPT-1047 Performance Run Test 7 04-Dec-19 11-Dec-19
TES-ORP-MPT-1048 Submission of As Built drawings 35 14-Nov-19 19-Dec-19
TES-ORP-MPT-1049 Handing over to client 3 19-Dec-19 22-Dec-19

Primary Baseline Critical Remaining Work Page 8 of 8

Actual Work Milestone


Remaining Work Summary