28.08.2018
e Date
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
Contract No N-15558
Name of Main Contractor Larsen & Toubro Ltd, ECC Construction Group.
CONTENTS
LARSEN &TOUBRO LIMITED, ECC Construction Group.
Effectiv
28.08.2018
e Date
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
1. Activity
3. References
4. Terminology
8. Managing Change
9. Environmental Impacts
12. Training
15. Records
16. Attachments
1. ACTIVITY
LARSEN &TOUBRO LIMITED, ECC Construction Group.
Effectiv
28.08.2018
e Date
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
Temporary access road works at the 220/33kV Substation at Towayya and related
220kV cable works
2. PURPOSE AND SCOPE
The purpose of this Method Statement is to describe the logical sequence of
activities involved in Temporary access road works. This method statement is
applicable for all activities related to the Temporary access road (Diversion of old
road to the substation, with reference to the Key plan attached) works in N-15558,
Supply and Installation of New 220/33kV Substation at Towayyah and related
220kV cable works.
3. REFERENCES
Reference Drawing
NOC’s Status
4. TERMINOLOGIES
Underground services.
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
Eye injury.
Excavator
Shovel / JCB
Bulldozer
Tipper
Pick-axe
Hand Shovel
Wheel barrow
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
Project Manager:
Overall responsibility for the
this activity.
HSE Engineer:
To ensure the HSE requirements
implementation effectively.
Construction Manager:
1) Preparing Method Statement &
Risk Assessment and follow up with Document Controller:
authorities for approval. 2) 1) Submitting the document to the
Implement the Method Statement & consultant and TRANSCO and updating
Risk Assessment in all respect. 3) the status. 2) Receiving the approval
Arrange and follow up the resources. copies and updating all the parties.
QA/QC Engineer:
1) Prepare the ITP. 2) Pre inspects the
activities, materials and ensures the work as
complied with the approved drawings and
specifications and method statement. 3)
Coordinate with consultant for site
inspections.4) Issuing non-conformance. 5)
Reporting to QEHS Head and partially to
project manager regarding any non -
a) Site Engineers / Competent
compliance Person:
and to ensure the compliance to
the requirements.
LARSEN &TOUBRO LIMITED, ECC Construction Group.
Effectiv
28.08.2018
e Date
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
b) Surveyor:
Perform survey works under the direction and guidance of the Engineer in
charge.
Check the accuracy of established primary horizontal and vertical control
points including reference points and references ties for re-establishing the
points in the field.
Perform regular checks of the setting out to verify proper execution and
accuracy.
Maintain equipment in proper condition and perform frequent calibration
checks.
Ensure that the works are being constructed to the latest construction and
shop drawings.
Record all measurements and calculations etc. neatly and accurately in
field books as the work progress.
Check completed work for conformance to the line and grade required by
the project plans in coordination with the inspector assigned in the work.
LARSEN &TOUBRO LIMITED, ECC Construction Group.
Effectiv
28.08.2018
e Date
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
c) QA/QC Engineer:
d) HSE Engineer:
Shall ensure the pre task briefing (PTB) by engineers and supervisors.
Check for the work permit and complete PPE.
Monitor the work location periodically to advise the site team for safe work
execution.
Review risk assessment and monitor during execution of works.
e) Construction Manager:
Prepare daily, weekly and monthly schedule as per 3 months look ahead
program in consultations with planning engineer.
Responsible to prepare & get approval of method statements from
Consultant/Client.
Allocate resources as per the request from site engineer/supporting team.
Control and monitor the progress.
Ensure work is carried out as per approved Project EHS plan.
Always follow current documents and identify superseded & separate the
same.
Authorized to review the QMS and Non- Conformities identified in the
processes, materials & decided disposal action on time.
LARSEN &TOUBRO LIMITED, ECC Construction Group.
Effectiv
28.08.2018
e Date
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
f) Project Manager:
g) Supervisor/Foreman:
8 Managing Change
During execution of project the following area has the potential of changes. All
kind of changes shall be carefully included in all method of statements and Risk
assessments to eliminate any potential hazard arise because of changes.
9 Environmental Impacts
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
Excavation works to be managed to control the dust. Wet the earth by water
spray and limiting the height of the material dumping.
All vehicles engaged at site shall follow the speed limit 20 KPH.
Construction Materials which shall fly due to wind shall be properly covered.
Accumulation of flying materials shall be avoided.
Fuel, oil storage shall be done to prevent leak of oil, penetration to ground.
Drip trays to be used for prevent the oil/chemical spill.
Maintenance of vehicle shall be done in the designated area.
Oil, waste etc., shall be disposed as per the environmental norms.
Sewage shall be browsed as per the regulations.
EHS Engineer should conduct noise survey, Identify the high noise activity,
measuring the noise level using sound meter. The effect of the noise on
workmen and surrounding. The existing noise level and the allowable exposure
time is should be within the below given table.
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
The waste generation & disposal of waste material shall be monitored by the Project
management. Waste material shall be classified as below
1. Municipal waste.
2. Non- hazardous Waste.
3. Hazardous Industrial Waste
Proper disposal of waste shall be insured by the project management as per the Federal
Environment Law (24) 1999.
The formation shall be rolled to an even and uniform surface and Rolling
shall be carried out with power driven roller.
LARSEN &TOUBRO LIMITED, ECC Construction Group.
Effectiv
28.08.2018
e Date
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
11.2 Excavation
Proposed Divesrion
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
12. TRAINING
The following EHS training shall be delivered to the workers & supervisors but not
limited to:
1. Awareness about emergency response.
2. Safety working procedure for the equipment and power tools.
3. Method statement and Risk assessment Briefing.
4. Safe disposal of waste.
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
hand gloves
Electrical insulated gloves (if required)
Safety helmet
Nose mask
Ear plugs
First Aid box
Safety Goggles
Available first aiders, with ready access to first aid boxes kept at site shall be
ensured at worksite.
All the emergency numbers including the nearby hospital will be displayed at
working site.
To stabilize their condition and prevent deterioration. Site Male Nurse / First
Aider decide whether the worker needs additional diagnosis and treatment,
then the injured person shall be initially transferred to the local accident and
emergency unit.
LARSEN &TOUBRO LIMITED, ECC Construction Group.
Effectiv
28.08.2018
e Date
Project - N-15558 – 220/33kV Substation at Towayyah and Related 220kV cable works
Method Statement for Temporary Access Road
If you discover a fire, alert the people in the area and need to evacuate.
Activate the nearest fire alarm.
15 ATTACHMENTS
a) Reference Drawings
b) Risk Assessment