You are on page 1of 2

List of RFI raised- Works

Submission Approved / Not


Sl.No. RFI No Description Unit Quantity Location Inspection Date Comments/Observations by Engineer Remarks
Date Approved
Measurement taken by measuring tape. The
distance from excavation location to dumping
Haulage Qty & Lead Measurement from Byasi
RKSH-KNPG/TUNNELS/PK- yard at Byasi = 340 m. The additional lead
1 02-08-2020 Station Excavation location to dumping yard m3-Km 1229.69 Byasi open excavation 04-08-2020 Approved
2/LNT/201/RFI/200163/A0 beyond 200m = 140m. Therefore the haulage
during the month of Jul'20
quantity for Jul'20 for BOQ item No. 1002a =
1229.689 Cum-Km
RKSH-KNPG/TUNNELS/PK- Work is completed. Survey and
2 04-08-2020 Slope Excavation and Manual Dressing for T2P1 m3 T2P1 portal, Shivpuri 05-08-2020
2/LNT/201/RFI/200164/A0 joint measurements to be done.

RKSH-KNPG/TUNNELS/PK- Random Rubble Masonry (Parapet Wall) for Pipe


3 04-08-2020 m3 2.83 Shivpuri approach road 05-08-2020 Work executed at Site. Total Qty = 2.83 m3. Approved
2/LNT/250/RFI/200165/A0 Culvert No.3

RKSH-KNPG/TUNNELS/PK- Work and survey completed. Joint


4 04-08-2020 Excavation for Invert PCC m3 Construction Adit-2 05-08-2020
2/LNT/202/RFI/200166/A0 measurements under process.

RKSH-KNPG/TUNNELS/PK- Work and survey completed. Joint


5 04-08-2020 Laying of Invert Lean Concrete (M15) m3 Construction Adit-2 05-08-2020
2/LNT/202/RFI/200167/A0 measurements under process.

RKSH-KNPG/TUNNELS/PK- 1st layer Shotcreting for T2P1 (Excavation Work is completed. Survey and
6 05-08-2020 m3 T2P1 portal, Shivpuri 06-08-2020
2/LNT/201/RFI/200168/A0 Supporting works) joint measurements to be done.

RKSH-KNPG/TUNNELS/PK- Work and survey completed. Joint


7 05-08-2020 Excavation for Invert PCC m3 Construction Adit-2 06-08-2020
2/LNT/202/RFI/200169/A0 measurements under process.

RKSH-KNPG/TUNNELS/PK- Work and survey completed. Joint


8 05-08-2020 Laying of Invert Lean Concrete (M15) m3 Construction Adit-2 06-08-2020
2/LNT/202/RFI/200170/A0 measurements under process.
Plan and Cross section submitted. Joint
Measurement singed by the
RKSH-KNPG/TUNNELS/PK- Rock Excavation for T3P2 Portal (Escape Tunnel measurement sheet attached. Total qty of Rock
9 06-08-2020 m3 151.46 T3P2 portal, Byasi 07-08-2020 "Engineer" and closing/approval of
2/LNT/201/RFI/200171/A0 Portion) not requiring blasting (BOQ No. 1002b) = 151.45
RFI under process.
m3
RKSH-KNPG/TUNNELS/PK- 1st layer of Wiremesh fixing for T2P1 (Excavation Work is completed. Survey and
10 06-08-2020 MT T2P1 portal, Shivpuri 07-08-2020
2/LNT/201/RFI/200172/A0 Supporting works) joint measurements to be done.

RKSH-KNPG/TUNNELS/PK- Work and survey completed. Joint


11 06-08-2020 Excavation for Invert PCC m3 Construction Adit-2 07-08-2020
2/LNT/202/RFI/200173/A0 measurements under process.

RKSH-KNPG/TUNNELS/PK- Work and survey completed. Joint


12 06-08-2020 Laying of Invert Lean Concrete (M15) m3 Construction Adit-2 07-08-2020
2/LNT/202/RFI/200174/A0 measurements under process.

RKSH-KNPG/TUNNELS/PK-
13 06-08-2020 Open excavation for station embankment m3 Byasi open excavation 07-08-2020 Work in Progress
2/LNT/201/RFI/200175/A0

RKSH-KNPG/TUNNELS/PK- TRAVERSING NEAR ADIT :[2] FROM CH [-0] TO


14 08-08-2020 - - Construction Adit-2 10-08-2020 Work in Progress
2/LNT/210/RFI/200176/A0 [555]

RKSH-KNPG/TUNNELS/PK- Inspection & measurement of Rock not requiring


15 08-08-2020 m3 Byasi open excavation 10-08-2020 Joint measurement under process.
2/LNT/201/RFI/200177/A0 blasting

RKSH-KNPG/TUNNELS/PK- Inspection & measurement of Rock requiring Measurement taken. Blasting is to


16 08-08-2020 m3 Byasi open excavation 10-08-2020
2/LNT/201/RFI/200178/A0 blasting be done.

RKSH-KNPG/TUNNELS/PK- 1st layer Shotcreting for T2P1 (Excavation Work is completed. Survey and
17 10-08-2020 m3 T2P1 portal, Shivpuri 11-08-2020
2/LNT/201/RFI/200179/A0 Supporting works) joint measurements to be done.
Submission Approved / Not
Sl.No. RFI No Description Unit Quantity Location Inspection Date Comments/Observations by Engineer Remarks
Date Approved
RKSH-KNPG/TUNNELS/PK- 1st layer of Wiremesh fixing for T2P1 (Excavation Work is completed. Survey and
18 10-08-2020 MT T2P1 portal, Shivpuri 11-08-2020
2/LNT/201/RFI/200180/A0 Supporting works) joint measurements to be done.

RKSH-KNPG/TUNNELS/PK-
19 10-08-2020 Shotcreting for T3P2 (Main Tunnel Portion) m3 T3P2 portal, Byasi 11-08-2020 Work in progress
2/LNT/201/RFI/200181/A0

RKSH-KNPG/TUNNELS/PK- Wiremesh fixing (1st & 2nd Layers) for T3P2 (Main
20 10-08-2020 MT T3P2 portal, Byasi 11-08-2020 Work in progress
2/LNT/201/RFI/200182/A0 Tunnel Portion)

RKSH-KNPG/TUNNELS/PK-
21 10-08-2020 Excavation for T3P2 (Escape Tunnel Portion) m3 T3P2 portal, Byasi 11-08-2020 Work in progress
2/LNT/201/RFI/200183/A0

RKSH-KNPG/TUNNELS/PK-
22 10-08-2020 Shotcreting for T3P2 (Escape Tunnel Portion) m3 T3P2 portal, Byasi 11-08-2020 Work in progress
2/LNT/201/RFI/200184/A0

RKSH-KNPG/TUNNELS/PK- 2nd layer Shotcreting for T2P1 (Excavation Work is completed. Survey and
23 11-08-2020 m3 T2P1 portal, Shivpuri 12-08-2020
2/LNT/201/RFI/200185/A0 Supporting works) joint measurements to be done.

RKSH-KNPG/TUNNELS/PK- 2nd layer of Wiremesh fixing for T2P1 (Excavation Work is completed. Survey and
24 11-08-2020 MT T2P1 portal, Shivpuri 12-08-2020
2/LNT/201/RFI/200186/A0 Supporting works) joint measurements to be done.

RKSH-KNPG/TUNNELS/PK- 3rd layer Shotcreting for T2P1 (Excavation Work is completed. Survey and
25 11-08-2020 m3 T2P1 portal, Shivpuri 12-08-2020
2/LNT/201/RFI/200187/A0 Supporting works) joint measurements to be done.

RKSH-KNPG/TUNNELS/PK- Wiremesh fixing (1st & 2nd Layers) for T3P2


26 11-08-2020 MT T3P2 portal, Byasi 12-08-2020 Work in progress
2/LNT/201/RFI/200188/A0 (Escape Tunnel Portion)
Maintenance work of approach road from Pipe
RKSH-KNPG/TUNNELS/PK- Shivpuri Approach Road from
27 13-08-2020 Culvert-3 to T2P1 Portal for road damages due to m3 14-08-2020 Work in progress
2/LNT/250/RFI/200189/A0 Portal to Culvert No-03
flood
RKSH-KNPG/TUNNELS/PK-
28 14-08-2020 Drilling, Installation and Grouting of SDA Bolts m T2P1 portal, Shivpuri 16-08-2020 Work in progress
2/LNT/201/RFI/200190/A0

RKSH-KNPG/TUNNELS/PK-
29 16-08-2020 Weep hole drilling and installation of PVC pipes m T2P1 portal, Shivpuri 17-08-2020 Work in progress
2/LNT/201/RFI/200191/A0

RKSH-KNPG/Tunnels/PK- Inspection for Shotcrete Machine (Meyco Supporting documents to be


30 17-08-2020 Nos 1 Byasi 18-08-2020
2/LNT/136/RFI/200192/A0 Potenza) submitted.

RKSH-KNPG/Tunnels/PK- Excavation and Manual slope dressing for


31 17-08-2020 m3 T2P1 portal, Shivpuri 18-08-2020 Wok in Progress
2/LNT/201/RFI/200193/A0 maintaining the slopes
Measurement for rock not requiring blasting
RKSH-KNPG/Tunnels/PK-
32 17-08-2020 shifting from Byasi Station to D6 dumping m3 Byasi open excavation 18-08-2020 Work in Progress
2/LNT/201/RFI/200194/A0
yard/Crusher plant