Professional Documents
Culture Documents
02nd Feb’2021
SECTION X
Package F Package G
Precasting Erection
PC Yard X LG X
PC Yard Y LG Y
Start
SCOPE 156.600
##
243.770
I
156.675
210.525
6
156.700
11
245.770 157.050
699 d ( 23 mths )
157.070
8.1
I
247.770 157.135
217.925
12.7
157.200
249.770 217.965
159.600
2.5
Crossover
1277 d ( 42 mths )
1
253.770 Approach 159.670
830 d ( 27 mths )
Sections to Stretches
254.515 159.840
12
254.585 Approach 161.840
7
254.655 Crossover
163.840
7.5
254.725 219.185
I
255.725 164.840
256.725 165.840
167.327
CCB
3.1
699 d ( 23 mths )
256.725 Crossover
I
219.220 Approach
257.831 219.260
13
223.000
Approach
257.901
225.000
2
Crossover
168.587
6.0
8
259.831 227.000
I
168.692
15.9
261.831
Section 2
229.000 168.732
263.757 172.192
263.827
231.000
I
263.967
176.800
14
Crossover
9
830 d ( 27 mths )
1277 d ( 42 mths )
Approach 235.204
699 d ( 23 mths )
235.274
178.800
Section - 3
Section - 1
Approach 235.484
Crossover
265.141 235.554 180.800
15
3
265.176
267.141
182.800
269.141
237.484
10.7
16
184.800
271.141
185.600
1277 d ( 42 mths )
275.870
5.9
10
275.940
187.900
R
276.660
17
241.440 189.900
276.730
41.5
278.300 191.900
4.3
280.972 193.900
4
241.510
281.192 Out of
195.500
Scope
18
283.192 197.200
1277 d ( 42 mths )
4.6
285.807 198.200
285.877 199.200
1277 d ( 42 mths )
286.037
286.107 201.200
0.5
286.569
5
286.639 203.200
290.300 205.200
292.300
10.5
208.000
19
294.300
1277 d ( 42 mths )
210.205
6
296.957
297.027 210.315
1277 ( 42 mt
Out of
Out of Scope
297.287
333.606
334.876
335.876 299.287
336.876
27
20
336.876 301.287
303.287
304.287
338.876 305.287
307.287
340.876
343.900 14.6 309.287
28
310.287
344.100
26.1
21
311.287
345.000
347.000
312.287
348.000 313.287
349.000 314.287
29
315.977
353.000 316.977
2.7
317.277
354.000 317.347
1094 d ( 36 mths )
356.000 317.447
1277 d ( 42 mths )
317.517
358.000
22
317.482
359.000 318.482
2.9
319.482
30
361.000
320.321
Section -5
362.000 320.251
Section -4
321.581
23
365.500
321.651
366.500
322.417
0.8
367.500
322.452
369.500
SB
Crossover
31
24.1
372.500
Approach
375.500
378.500
24
379.500
380.500
382.500
381.500 Approach
383.500
384.500
SB
Crossover
384.425
323.767
I
384.500 323.922
32
1277 d ( 42 mths )
2.8
384.605 326.702
326.772
1183 d ( 39 mths )
25
384.675 327.002
0.3
327.072
384.871 328.002
384.941
385.011
385.081 329.002
386.081
6.13
388.081 330.002
26
8.6
33
390.081
333.002
1183 d ( 39 mths )
393.700
LARSEN & TOUBRO
333.206
333.276
Depots and Stations Finishes
A B C D E
• Bilimora Station M41 • Surat Station M42 • Bharuch Station M41 • Vadodara
• CCB • Surat Maint Depot • Bharuch Maint Depot Maint Depot
• Vapi Station M42
• SSP 8 & 9 • SSP 10 & 11 • SSP 12 & 13 • SSP 14 & 15
• Vapi Maint Depot
• SER 10 & 11 • SER 12 & 13 • SER 14 & 15 • SER 16 & 17
• SSP 6 & 7
• TSS 6 • TSS 7 • TSS 7 • TSS 9
• SER 8 & 9
• SP 5 • SP 6 & 7 • SP 8
• TSS 5
VIADUCT DESIGN
UTILITY IDENTIFICATION REVISED PRELIMINARY FIELD BORE LOG & LAB TEST
( BY GPR ) SPAN CONFIGURATION REPORT SUBMISSION
FOUNDATION SELECTION/
UTILITY
NO RECOMMENDATION
INFRINGEMENT
AS PER DFM
YES
YES NOT OK
DIVERSION FINAL SPAN RUNNING SAFETY
POSSIBLE CONFIGURATION CHECK
NO OK
May
Nov
May
Nov
May
Nov
May
Mar
Mar
Mar
Mar
Dec
Dec
Dec
Aug
Aug
Aug
Feb
Sep
Feb
Sep
Feb
Sep
Feb
Apr
Apr
Apr
Apr
Jun
Jun
Jun
Jun
Oct
Oct
Oct
Jan
Jan
Jan
Jan
Jul
Jul
Jul
Geotechnical Investigation BH 563 1 8 21 30 42 21 21 21 42 91 91 91 83
Piling Nos 4770 5 40 91 116 107 45 77 71 83 81 243 270 152 254 268 272 365 142 121 72 54 65 133 194 174 310 235 261 79 260 65 62 3
Pile Cap Nos 853 4 6 6 8 9 26 6 10 7 33 49 33 42 52 56 65 48 24 21 10 10 21 36 34 33 38 49 32 33 34 12 6
Section 1
May
Nov
May
Nov
May
Nov
May
Mar
Mar
Mar
Mar
Dec
Dec
Dec
Aug
Aug
Aug
Feb
Sep
Feb
Sep
Feb
Sep
Feb
Apr
Apr
Apr
Apr
Jun
Jun
Jun
Jun
Oct
Oct
Oct
Jan
Jan
Jan
Jan
Jul
Jul
Jul
Geotechnical Investigation BH 2446 7 47 112 164 238 128 128 128 268 271 273 273 265 144
Piling Nos 26875 21 205 555 704 995 979 961 1035 1151 1039 923 1132 1370 1350 1498 1352 1201 1252 1052 938 887 725 651 719 863 794 678 445 437 246 379 151 145 29 13
Pile Cap Nos 5275 16 64 93 160 185 196 203 192 237 181 200 246 260 284 275 251 250 226 202 195 154 134 144 161 161 141 103 97 84 77 53 32 13 5
Project
Asking rate 1 7 17 25 36 40 40 40 40 40 40 40 40 30
GTI Rigs
Deployment plan 1 10 20 30 40 40 40 40 40 40 40 40 40 35
Asking rate 1 5 14 18 25 24 24 26 29 26 23 28 34 34 37 34 30 31 26 23 22 18 16 18 22 20 17 11 11 6 9 4 4 1
Piling Rigs
Major Resources Requirements
Deployment plan 2 10 15 20 25 30 30 30 30 30 30 30 35 40 40 40 40 40 40 35 35 35 30 30 30 30 30 25 25 25 15 15 15 10 10
Asking rate 1 3 10 14 25 30 30 32 31 40 31 31 36 40 43 42 38 39 39 35 34 25 19 21 23 24 24 15 14 12 11 8 5 6 8 2
Foundation sets
Deployment plan 5 5 10 15 20 25 35 40 40 40 40 40 40 40 45 46 46 46 46 46 46 46 35 35 30 30 30 30 25 25 20 20 15 10 10 10 10
Asking rate 8 20 43 49 61 73 75 73 73 70 72 68 100 95 90 90 81 85 83 86 79 48 46 57 55 58 51 35 30 20 20 16 10 15 19
Pier Sets
Deployment plan 5 10 15 45 55 65 80 80 90 90 90 100 110 120 120 120 120 120 120 120 120 120 100 80 80 80 80 80 50 50 50 50 50 50 50 50
Asking rate 4 10 11 13 11 10 13 12 9 9 10 9 10 10 5 4 3 3 9 9 9 7 3 2 2 2 2 4 4 3 1 1 1 1
Span By Span Mould
Deployment plan 5 10 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 13 8 8 8 8 8 8 5 5 5
Asking rate 17 21 27 47 56 64 55 61 66 68 71 68 67 61 57 69 66 62 65 73 59 34 61 67 63 67 62 67 58 38 13 2
Full Span Mould
Deployment plan 10 20 30 50 60 70 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 72 35
Asking rate 1 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 2 1
Span By Span LG
Deployment plan 2 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3 3
Asking rate 1 2 3 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 3
Full Span LG
Deployment plan 3 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
May-21
May-22
May-23
May-24
Mar-21
Aug-21
Nov-21
Mar-22
Aug-22
Nov-22
Mar-23
Aug-23
Nov-23
Mar-24
Feb-21
Apr-21
Sep-21
Oct-21
Dec-21
Feb-22
Apr-22
Sep-22
Oct-22
Dec-22
Feb-23
Apr-23
Sep-23
Oct-23
Dec-23
Feb-24
Apr-24
Jan-21
Jun-21
Jan-22
Jun-22
Jan-23
Jun-23
Jan-24
Jun-24
Jul-21
Jul-22
Jul-23
Activity Uom Scope
Geotechnical Investigation BH 5 2 3
Geotechnical Investigation BH 10 5 5
Geotechnical Investigation BH 19 4 5 5 5
In line with the Cl 2.5.2.2 of Division 02000 from Design Requirement & Criteria the well foundations may be changed to Pile foundations if
design permits
01-May-22
01-May-23
01-Mar-22
01-Mar-23
01-Nov-21
01-Nov-22
01-Nov-23
01-Aug-21
01-Aug-22
01-Aug-23
01-Sep-21
01-Dec-21
01-Sep-22
01-Dec-22
01-Sep-23
01-Apr-22
01-Feb-22
01-Feb-23
01-Apr-23
01-Jun-22
01-Jun-21
01-Oct-21
01-Oct-22
01-Jun-23
01-Oct-23
01-Jan-22
01-Jan-23
01-Jul-21
01-Jul-22
01-Jul-23
Qty
Section Stretch Activity
(Nos)
May-21
May-22
May-23
May-24
Mar-21
Mar-22
Mar-23
Mar-24
Nov-21
Nov-22
Nov-23
Aug-21
Dec-21
Aug-22
Dec-22
Aug-23
Dec-23
Feb-21
Apr-21
Sep-21
Feb-22
Apr-22
Sep-22
Feb-23
Apr-23
Sep-23
Feb-24
Apr-24
Oct-21
Oct-22
Oct-23
Jun-22
Jan-21
Jun-21
Jan-22
Jan-23
Jun-23
Jan-24
Jun-24
Jul-22
Jul-21
Jul-23
Section Activity Uom Scope
Ramp Nos 78 4 2 4 2 2 4 2 4 2 2 2 10 8 4 4 6 6 4 2 4
Pile Nos 3510 8 98 104 80 104 92 110 34 82 90 18 98 130 40 64 64 56 234 354 360 230 130 210 188 68 16 80 58 106 134 70
Overall - Ramps (SMD and
Pile Cap Nos 702 16 22 10 20 20 28 10 10 20 6 14 28 12 8 10 14 36 62 78 58 26 38 44 16 6 10 10 22 26 20 2
Vehicular)
Pier & Pier Cap Nos 702 4 20 12 6 18 36 22 10 16 18 6 22 24 6 6 10 24 44 80 72 38 26 46 32 12 4 6 22 20 26 14
I-Girder Erection Spans 624 4 8 14 24 32 22 6 14 12 12 16 10 8 12 10 22 40 54 56 46 30 38 32 10 10 10 16 20 20 12 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
Station /
2021 2022 2023 2024
Month
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Mandatory approvals,
Vapi GTI Piling Framed Structure Structural steel, Architectural , Finishing & MEP
Testing & Commissioning
Mandatory approvals,
Surat GTI Piling Framed Structure Structural steel, Architectural , Finishing & MEP
Testing & Commissioning
Mandatory approvals,
Bharuch GTI Piling Framed Structure Structural steel, Architectural , Finishing & MEP
Testing & Commissioning
To Electrical Contractor To Track Contractor
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
Foundati
GTI Ground Stabilization Civil St.Steel Finishing & MEP
169.9 on
Compound Wall Casting Compound Wall
Vapi Depot
Drain & Chamber Casting Drains & Chambers
170.7
Road & Track
Foundati
GTI Ground Stabilization Civil St.Steel Finishing & MEP
262.7 on
Compound Wall Casting Compound Wall
Surat Depot
Drain & Chamber Casting Drains & Chambers
263.27
Road & Track
Foundati
GTI Ground Stabilization Civil St.Steel Finishing & MEP
324.9 on
Compound Wall Casting Compound Wall
Bharuch Depot
Drain & Chamber Casting Drains & Chambers
325.69
Road & Track
Foundati
GTI Ground Stabilization Civil St.Steel Finishing & MEP
382.61 on
Vadodara Compound Wall Casting Compound Wall
Depot
Drain & Chamber Casting Drains & Chambers
383.38
Road & Track
Land Handover To T-2 Contractor
To Train Washing Track / Wheel Reprofiling Track
Connectivity of Approach line the Train Washing Track to Leading
Sensitivity: LNT Construction Internal Use LARSEN & TOUBRO
GTI
to GTI
Jan-21
Jan-23
Jan-24
Jan-22
Sep-21
Sep-23
Sep-22
May-21
May-22
May-23
0
Foundations
GTI Vs. Piling
Description
1000
393 166 Mar-21
3 782 330 Apr-21
27 1345 568 May-21
99 1648 696 Jun-21
196 1952 824 Jul-21
2000
356 2255 952 Aug-21
562 2880 1216 Sep-21
Foundations
771 3529 1490 Oct-21
992 4176 1763 Nov-21
USLG 219.185
7
Crane
USLG
I
Crane 219.220
223.000
CYF-2/1
225.000
225.973
227.000
8
15.9
Section 2
229.000
405 Spans
231.000
9
699 d ( 23 mths )
235.204
2
235.274
699d / 830d
235.484
2
235.554
10
237.484
CYF-1/1
5.9
150 Spans
238.48
241.440
2
241.510
Out of
2
241.770
242.770
2 Sections
243.770
11
245.770
247.770
12.7
322 Spans
CYF-3/1
249.770
249.19
253.770
12
830 d ( 27 mths )
254.515
2
254.585
254.655
9 Stretches
3
254.725
255.725
256.725
254.725
CYS-2
256.725
Section 3
13
699 d ( 23 mths )
257.831
9.1
257.901
225 Spans
259.831
Yards
261.831
4 Casting
263.757
263.827
14
I
263.967
Crossover
830 d ( 27 mths )
Approach
Surat
Station
LARSEN & TOUBRO
15
Approach
Crossover
Logistics
Section 2 Section 3
699 d ( 23 mths ) 830 d ( 27 mths ) 699 d ( 23 mths ) 830 d ( 27 mths )
241.770
242.770
243.770
245.770
247.770
249.770
253.770
254.515
254.585
254.655
254.725
255.725
256.725
256.725
257.831
257.901
259.831
261.831
263.757
263.827
263.967
Crossover
Crossover
Crossover
Crossover
Approach
Approach
Approach
Approach
223.000
225.000
227.000
229.000
231.000
235.204
235.484
237.484
241.440
219.185
219.220
219.260
235.274
235.554
241.510
Out of
I I 15.9 5.9 12.7 9.1 I
Bilimora
Station
Station
Crane
USLG
USLG
USLG
Crane
Surat
405 Spans 2 2 150 Spans 2 2 322 Spans 2 3 225 Spans
01-May-21
01-May-22
01-Mar-21
01-Mar-22
01-Mar-23
01-Nov-21
01-Nov-22
01-Aug-21
01-Aug-22
10-Dec-20
01-Dec-21
01-Dec-22
01-Feb-21
01-Apr-21
01-Sep-21
01-Oct-21
01-Feb-22
01-Apr-22
01-Sep-22
01-Jun-21
01-Jun-22
01-Oct-22
01-Feb-23
15-Jan-21
01-Jan-22
01-Jan-23
01-Jul-21
01-Jul-22
Stretch Activity Unit Quantity
ROW Kms 6 6
CH 217.96 to 224 & Bilimora
Station
GTI Nos 49 8 8 8 5 5 5 5 5
Stretch-11
01-May-21
01-May-22
01-Mar-21
01-Mar-22
01-Mar-23
01-Nov-21
01-Nov-22
01-Aug-21
01-Aug-22
10-Dec-20
01-Dec-21
01-Dec-22
01-Feb-21
01-Apr-21
01-Sep-21
01-Feb-22
01-Apr-22
01-Feb-23
01-Jun-21
01-Oct-21
01-Sep-22
01-Jun-22
01-Oct-22
15-Jan-21
01-Jan-22
01-Jan-23
01-Jul-21
01-Jul-22
Stretch Activity Unit Quantity
Pile Cap
Pier & Pier Cap
Nos
Nos
203
203
21 31
29
28
30
31
28
23
32
10
16
10
10
11
11
9
9
10
10
11
11
8
10 7 27 M
Precasting - Full Span Nos 198 20 30 30 31 31 31 25
Precasting - SBS Nos 5 3 2
Full Span Erection Nos 198 17 30 33 26 27 51 14
SBS Erection Nos 5 3 2
ROW Kms 3.44 3.44
Preconstruction activities/Road Kms 3.44
CH 255 to 258.5
GTI Nos 40 1 6 6 10 16 1
Stretch-13
Station
Piles Nos 45 27 18
Pile Cap Nos 9 3 5 1
Pier & Pier Cap
Precasting - SBS
Nos
Nos
9
9
3 4 2
1 3 3 2
23 M
SBS Erection Nos 9 6 3
01-May-21
01-May-22
01-Mar-21
01-Mar-22
01-Mar-23
01-Nov-21
01-Nov-22
01-Aug-21
01-Aug-22
10-Dec-20
01-Dec-21
01-Dec-22
01-Feb-21
01-Apr-21
01-Sep-21
01-Apr-22
01-Sep-22
01-Feb-23
01-Jun-21
01-Oct-21
01-Feb-22
01-Jun-22
01-Oct-22
15-Jan-21
01-Jan-22
01-Jan-23
01-Jul-21
01-Jul-22
Activity Unit Quantity
Priority Stretch
Pier & Pier Cap Nos 1161 52 75 98 103 105 99 116 92 97 76 68 64 49 42 12 7 5 1
Precasting - Full Span Spans 883 50 64 80 76 106 85 59 72 71 71 70 54 25
Precasting - SBS Spans 272 6 22 26 31 27 25 24 26 22 18 15 13 12 5
Precasting - I Grider Spans 6 2 2 2
Full Span Erection Spans 883 16 37 94 108 100 113 101 69 78 90 63 14
SBS Erection Spans 275 4 10 14 20 22 27 28 23 32 24 21 14 12 12 11 1
I Girder Erection Spans 6 2 2 2
Concrete quantity (cum.) 576 3060 19014 31418 40730 46204 49332 46152 49202 59470 64270 85718 94182 85558 83768 77548 53216 48306 48838 34444 12120 5336 536
Section 2 Section 3
699 d ( 23 mths ) 830 d ( 27 mths ) 699 d ( 23 mths ) 830 d ( 27 mths )
241.770
242.770
243.770
245.770
247.770
249.770
253.770
254.515
254.585
254.655
254.725
255.725
256.725
256.725
257.831
257.901
259.831
261.831
263.757
263.827
263.967
Crossover
Crossover
Crossover
Crossover
Approach
Approach
Approach
Approach
223.000
225.000
227.000
229.000
231.000
235.204
235.484
237.484
241.440
219.185
219.220
219.260
235.274
235.554
241.510
Out of
I I 15.9 5.9 12.7 9.1 I
Bilimora
Station
Station
Crane
USLG
USLG
USLG
Crane
Surat
405 Spans 2 2 150 Spans 2 2 322 Spans 2 3 225 Spans
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
Station /
Month Jan- Feb Mar Apr May Jun- Jul- Aug Sep Oct- Nov Dec Jan- Feb Mar Apr May Jun- Jul- Aug Sep Oct- Nov Dec Jan- Feb Mar Apr May Jun- Jul- Aug Sep Oct- Nov Dec Jan- Feb Mar Apr May Jun- Jul- Aug Sep Oct- Nov Dec
21 -21 -21 -21 -21 21 21 -21 -21 21 -21 -21 22 -22 -22 -22 -22 22 22 -22 -22 22 -22 -22 23 -23 -23 -23 -23 23 23 -23 -23 23 -23 -23 24 -24 -24 -24 -24 24 24 -24 -24 24 -24 -24
Geotech
nical Mandatory approvals, Testing
Bilimora Piling Framed Structure Structural steel, Architectural , Finishing & MEP
Investiga & Commissioning
tion
Geotech
nical Mandatory approvals,
Surat Piling Framed Structure Structural steel, Architectural , Finishing & MEP
Investiga Testing & Commissioning
tion
Erection Methodology
1% VAPI BILIMORA SURAT BHARUCH
14%
Sections Section - 1 Section - 2 Section - 3 Section - 4 Section - 5
Description / Chainage 159 166 189 217 226 238 249 256 270 278 290 308 321 333 359 385
Batching Plant
85% Steel Centres
Workmen Accommodation
Quality Lab
Start of C4 End of C4
120 Cum Batching Plants - 3 nos (M5-M40) Full Span Mould – 72 Sets (M8-M40)
90 Cum Batching Plants - 17 nos (M4-M41) SBS Mould – 13 Long Line + 27 Short Line (M6-M40)
60 Cum Batching Plants - 8 nos (M4-M41) I Girder Moulds – 26 Sets (M3-M40)
Cut & Bend Dedicated Batching Rebar Couplers and Elastomeric Bearings
NATM agencies
Reinforcement Steel Plants Threading agencies & Seismic Stoppers
Road works & Temporary Bridges & PIT and CHSL tests Quarrying and
GTI & Piling
Earthwork Coffer Dams agencies Crushing
Aggregate Stacking
Rebar Jig
Batching Plant RMS Plant
Straddle Carrier
1100 MT Cap.
Stacking bay
May-22
May-23
May-24
Mar-22
Mar-23
Mar-23
Mar-24
Nov-21
Nov-22
Nov-23
Aug-22
Aug-23
Dec-21
Dec-22
Dec-22
Dec-23
Sep-22
Sep-23
Apr-22
Apr-23
Apr-24
Feb-22
Feb-24
Oct-22
Oct-23
Jun-22
Jun-23
Jan-22
Jan-23
Jan-24
Jul-22
Jul-23
Full Span Launching Plan
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
Ch 235.554 to 241.475 S2
Ch 385.086 to 393.7 S5
Full Span LG 1
Ch 276.73 to 285.842 S3
Ch 210.555 to 217.96 S2
Ch 219.26 to 235.204 S2
Full Span LG 2 Ch 265.176 to 275.905 S3 S3
Ch 286.639 to 296.957 S3 S3
Ch 241.838 to 254.515 S3
Full Span LG 3 Ch 159.84 to 167.367 S1
Ch 327.072 to 333.241 S4
Ch 333.676 to 359.793 S5
Full Span LG 4
Ch 297.357 to 308.0 S4
Ch 359.793 to 384.46 S5
Full Span LG 5
Ch 308.0 to 316.003 S4
Casting ( 322 Spans ) Casting ( 269 Spans ) Casting ( 228 Spans ) Casting ( 263 Spans )
Mobilisation – 11M Mobilisation – 20M Mobilisation – 25M Mobilisation – 30M
Casting month – M12 – M20 (9M ) Casting month – M22 – M30 ( 9 M) Casting month – M26 – M30 ( 5 M) Casting month – M32 – M39 ( 8 M)
No. of Mould - 12 Moulds No. of Mould - 10 Moulds No. of Mould - 16 Moulds No. of Mould - 12 Moulds
Productivity per moth – 3.0 Spans Productivity per moth – 3.0 Spans Productivity per moth – 2.9 Spans Productivity per moth – 2.7 Spans
Cycle Time – 10 Days / span Cycle Time – 10 Days / span Cycle Time – 10 Days / span Cycle Time – 11 Days / span
Erection ( 322 Spans ) Erection ( 269 Spans ) Erection ( 228Spans ) Erection ( 263Spans )
LG No : FSL 3/1 (Mobilisation –12M) LG No : FSL 2/1 (Mobilisation –24M) LG No : FSL1/3 (Mobilisation –27M) LG No : FSL 2/3 (Mobilisation –34M)
Erection Month – M14 – M22( 9 M) Erection Month – M25 – M31(7 M ) Erection Month – M28 – M32(5 M ) Erection Month – M35 – M40 ( 6 M)
Productivity per month – 36 Spans Productivity per month – 38 Spans Productivity per month – 46 Spans Productivity per month – 43 Spans
Cycle Time – 1.2 span/Day Cycle Time – 1.3 span/Day Cycle Time – 1.5 span/Day Cycle Time – 1.2 span/Day
FSLM (760 spans) FSLM( 520 spans) FSLM (216 Spans) END
CYS-1
CYS-2
NARMADHA CYS-3
CYS-4
Duration of Erection
Productivity per LG
LG Id No. of spans LG mobilization month Start End Working No. of LG’s /month
month month months (Cycle time in Days)
210.315
210.525
241.770
SURAT MAINTENANCE DEPOT
C4-PACKAGE SURAT DEPOT APPROACH
58 Nos.
START 12 Nos. VAPI STATION 22 Nos. BILIMORA STATION 6 Nos. SURAT STATION
156.600
CONFIRMATION CAR BASE
STATION APPROACH VAPI MAINTENANCE DEPOT STATION APPROACH
12 Nos. 29 Nos. (I - GIRDER 32 Nos.)
(I - GIRDER 32 Nos.)
VAPI DEPOT APPROACH CCB APPROACH LINE
56 Nos. 19 Nos.
CY -1
275.144
215.872
156.600
150km 160km 170km 180km 190km 200km 210km 220km 230km 240km 250km 260km 270km 275.144km
Duration of Casting
Mould
Working
Spans mobilization No. of moulds Start Productivity
End month months
month month
I - GIRDER 278 11 6 12 32 21 2
T - GIRDER 402 11 7 12 34 23 2
297.027
297.287
333.276
333.606
BHARUCH STATION
C4-PACKAGE
END
VADODARA MAINTENANCE DEPOT 393.700
STATION 28 Nos. 22 Nos.
APPROACH
(I - GIRDER 110 Nos.) VADODARA DEPOT APPROACH
40 Nos.
CY -2
275.144
334.417
393.700
TOTAL - I - GIRDER IN CY-2
(250)
275.144km 280km 290km 300km 310km 320km 330km 340km 350km 360km 370km 380km 390km
Duration of Casting
Mould
Working
Spans mobilization No. of moulds Start Productivity
End month months
month month
I - GIRDER 250 12 5 13 34 22 2
T - GIRDER 402 12 7 13 36 24 2
REINFORCEMENT TYING
AT REBAR JIG
CURING 7 DAYS
FIXING OF INSERT AND
INSERT INNER FORM LONGITUDINAL STRESSING LIFT SPAN TO PLACE AT
TRANSVERSE CABLE CONCRETING OF SPAN
SHUTTER OF SPAN STACKING YARD
PROFILING
CURING 3 DAYS