DHA BWP (EOT) Classic WBS Layout 19-Dec-18 02:59

Activity ID Activity Name Original Start Finish 2017 2018 2019


Duration Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

DHA BWP (EOT) 732 02-Jan-17 30-Jun-19

Premobilization 11 02-Jan-17 14-Jan-17 14-Jan-17, Premobilization


A1000 Project Start/ Notice to Commence 0 02-Jan-17 02-Jan-17 Project Start/ Notice to Commence
A1010 Submission of Work Schedule 10 02-Jan-17 12-Jan-17 Submission of Work Schedule
A1020 Submission of Work Methodology 10 02-Jan-17 12-Jan-17 Submission of Work Methodology
A1030 Effective Access & Site Possesstion 1 14-Jan-17 14-Jan-17 Effective Access & Site Possesstion
Mobilization 20 14-Jan-17 05-Feb-17 05-Feb-17, Mobilization
A1040 Resource Mobilization 5 14-Jan-17 18-Jan-17 Resource Mobilization
A1050 Provision of Employer's and Engineer's Facilities
15 19-Jan-17 05-Feb-17 Provision of Employer's and Engineer's Facilities
Survey and Design 619 19-Jan-17 26-Feb-19 26-Feb-19, Survey and
A1060 Survey of Project Area 255 19-Jan-17 12-Nov-17 Survey of Project Area
A1070 Issuance of Construction Drawings 500 25-Jan-17 11-Oct-18 Issuance of Construction Drawi
A1080 Submission of Shop Drawings 600 06-Feb-17 26-Feb-19 Submission of Shop D
DHA BWP Sector B 717 19-Jan-17 30-Jun-19
Roadworks 717 19-Jan-17 30-Jun-19
Tube Well and Rising Main Works 567 13-Jul-17 30-Jun-19

Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.